1 of 53

SAP Plant Maintenance

Inspection Round Planning

2 of 53

3 of 53

This presentation is to show how to create a Task List for Measurement Reading

4 of 53

Creating a General Task List for managing Measurement Readings of several Equipments or FL

5 of 53

Prepare 5 operations and assign each with an Equipment

6 of 53

Select to Highlight the 5 Operations and

Click “PRT”

7 of 53

Operation 10

Switch to Measuring Point

Dialogue

8 of 53

F4

9 of 53

Equipment TEQ-01 currently only have ONE MP, Double-click to select it

10 of 53

11 of 53

Goto the Next Operation

You can have One or more Measurement Point for an Operation related to the EQ

12 of 53

Use the same method illustrated earlier to select MPs from the respectively EQs assigned to the Operation

13 of 53

SAVE

MP assigned to the last operation 50

14 of 53

Use IA10 to show Measuring Point as PRT assigned to the Operations of the General Task List

15 of 53

Measuring Points were seen assigned to each Operation in

IA10

16 of 53

Create an MO for managing the Measurement Readings

17 of 53

Get General Task List created just now

18 of 53

19 of 53

Double click counter 2

20 of 53

Replace all Operations Work Centers to MECHANIK

21 of 53

Copy ALL Operations from the General Task list

22 of 53

General Task list copied to MO

23 of 53

Check PRT copied over

24 of 53

MP for TEQ-05 in the MO

25 of 53

MO# 816022

Released and SAVED

26 of 53

Job Ticket and Job Card from Std SAP shop paper prints the Measurement Points

27 of 53

You can find the Measuring Point in the Std SAP sho paper

Job Ticket

28 of 53

You can find the Measuring Point in the Std SAP sho paper

Job Card

29 of 53

Change Settings to get Profile with Measurement Point ENTRY screen segments

30 of 53

F4

31 of 53

32 of 53

Press ENTER to read MO into IW42

33 of 53

Record Operation Time for Measurement Readings

34 of 53

35 of 53

You can now begin recording the Measurement Readings

36 of 53

SAVE

37 of 53

You can find the Measurement Documents here

38 of 53

Measurement Documents

39 of 53

To Reverse the Measurement Reading, First SET to Change Mode

40 of 53

Access Detail Screen of Measurement Doc

41 of 53

42 of 53

43 of 53

SAVE

Note “Reversal” Indicator

44 of 53

Note “Reversal” Indicator

45 of 53

To Enter the correct Reading, Goto IW42 again.

You have to Manually Enter the MP and the Correct Readings

46 of 53

SAVE

47 of 53

48 of 53

New Reading

49 of 53

Related IMG

50 of 53

Confirmation Screen Segment with Measurement Reading

51 of 53

52 of 53

53 of 53

In the next PPT,

we shall see how to SETUP

Maintenance Plan for Inspection Round

(meaning, use MP to generate MO in a specific cycle like weekly or monthly for Measurement Reading via the Called MO)