John George, Yamuna Gajendra, SAP
11/09/2025
Elaraby CDP
Weekly Status Report
INTERNAL – SAP Only
1
CONFIDENTIAL
Project Schedule
2
CONFIDENTIAL
Project Schedule (revised – 18May25)
We are here
3
CONFIDENTIAL
Project Schedule (revised – 10Apr25)
We are here
4
CONFIDENTIAL
Project Schedule (revised – 22Apr25)
We are here
5
CONFIDENTIAL
Project Schedule (revised – 06Aug25)
We are here
6
CONFIDENTIAL
SAP CDP (Customer Data Platform) Project Status Update
Open Items:
Activities Completed
Activities Work in Progress
Activities Planned (Next Week)
Planned Go-Live Date:
14-Aug-2025
Project Health
Description | Date DD/MM/YYYY |
Start Date | 12/01/2025 |
Prepare | 23/01/2025 |
Realize | |
Build & UT | 15/05/2025 |
SIT closure | 05/06/2025 |
UAT closure | 26/06/2025 |
Cutover & GOLIVE | 14/08/2025 |
PGLS | 11/09/2025 |
Project Timeline
NOTE:
7
CONFIDENTIAL
Production Cutover progress
8
CONFIDENTIAL
Pending Cutover tasks
9
CONFIDENTIAL
PGLS Defect Summary
10
CONFIDENTIAL
SAP CDP (Customer Data Platform)
| No. | Action Summary | Date raised | Due | Owner | Status |
| 1 | Elaraby to complete the Cutover plan ( by 22Jun25) | | 03-June-25 | Elaraby | CLOSED |
| 2 | Elaraby to confirm correctness of one-time cutover sales data in Production – Due 9Jul25 | | 09-Jul-25 | Elaraby | CLOSED |
Issues
Risks
No. | Risk Summary | Mitigation Action | Probability | Owner | Due | Status |
1 | Delay in task completion as per plan, impacts timeline | SAP & Elaraby to meet planned deadline | High | SAP/Elaraby | Ongoing | Ongoing |
2 | Any changes in interfaces with CDP will lead to inconsistencies in data | Freez changes till after Go live and PGLS | High | Elaraby | Ongoing | CLOSED |
3 | Elaraby plans to Load data only in the evenings due to S/4 performance issue. This increases the timeline for data load. Risk on project timeline. Foresee additional1 week timeline extension to cover the delay & the risk. | Elaraby to try expedite the closure of load | Vhigh | Elaraby | Ongoing | CLOSED |
4 | Golive planned on 14Aug25. Any rescheduling will lead to CR | To follow the plan | Medium | Elaraby | Ongoing | CLOSED |
No. | Issue Summary | Resolution Action | Severity | Owner | Due | Status |
1 | Maxxing is unable to accept data, due to their server limitation. This is also impacting the load to Datasphere | Maxxing / Elaraby to address and load the data in Maxxing, asap. CR would be raised to cover the delay | Vhigh | Elaraby | Immediate | CLOSED |
Actions
11
CONFIDENTIAL
Thank you.
12
CONFIDENTIAL