SAP Plant Maintenance

Performance Based

Preventive Maintenance

based on Measuring Point

(Engine Hours)

2 of 113

  1. Create Characteristics “Z20_HOURS” (CT04).
  2. Create Equipment “ZEQ20” with Measuring Point (IE01).
  3. Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  4. Check Measuring Document entered in previous step (IE03).
  5. Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  6. Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  7. Maintenance Plan Category “PM” (IMG).
  8. Create Strategy Plan “ZMP20” (IP42).
  9. Schedule the Maintenance Plan “261” (IP10).
  10. Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  11. Check Measuring Documents in the Equipment (IE03).
  12. Schedule the Maintenance Plan “261” again (IP10).
  13. Display the Maintenance Order Called (IP10).
  14. Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  15. Check Counter Readings in the Equipment Master (IE03).
  16. Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  17. Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  18. Schedule the Maintenance Plan “261” again (IP10).

3 of 113

in CT04, create Characteristics Z20_HOURS for Engine Hours Measuring Point

4 of 113

Numeric Data Format

5 numbers with 0 decimals

UOM = “h” (for hours)

Mandatory

5 of 113

6 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

7 of 113

Create new Equipment ZEQ20 with a Counter Measuring Point using Characteristics Z20_HOURS

8 of 113

Enter necessary data and GOTO “Measuring points/counters”

9 of 113

Enter the new Characteristics Z20_HOURS, click “Counter” and

click “Details” ICON

10 of 113

Counter overflow Reading “999999” (max Counter number),

Estimate 20 hours a day (estimate work days 20 days a month), therefore 20 x 20 x 12 = 4800 per Year for the Annual Estimate.

The Preventive Scenario will be:

1200 hours (around 3 months) - Inspect & Lubricate

2400 hours (around 6 months) - Change Parts

4800 hours (around 12 months) - Full Service

11 of 113

Measuring Point 12042 created

12 of 113

13 of 113

14 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

15 of 113

Initialize the Measuring Point to 0 hours as it is a new Equipment

16 of 113

Overall the format to 0

17 of 113

note 0

SAVE

18 of 113

Measurement Document created for the Measuring Point initialization

19 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

20 of 113

Measuring Document entered for the Equipment can be view from the MP/Counters screen

21 of 113

Since there is only one Measurement Document, click this button

22 of 113

Counter Reading entered just now

23 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

24 of 113

Create new Strategy “ZS20” for Performance-based Preventive based on “Engine Hours” for the following Cycles:

1200 hours (around 3 months) - Inspect & Lubricate

2400 hours (around 6 months) - Change Parts

4800 hours (around 12 months) - Full Service

25 of 113

Scheduling indicator = “3 Activity” (for Counter-based) with Strategy unit “h” (must be same UOM as the Characteristics for the Measuring Point)

26 of 113

Call horizon “2 DAY” (meaning Maintenance Order is called 2 Days before its Due Date, Factory Calendar is Optional. Next, Double-click “Packages”

27 of 113

28 of 113

Create new Strategy “ZS20” for Performance-based Preventive based on “Engine Hours” for the following Cycles:

Package Cycle Length CycleTextHierarchy H.Text

1 1200 hours (around 3 months) - Inspect & Lubricate 12 1 H1

2 2400 hours (around 6 months) - Change Parts 24 1 H1

3 4800 hours (around 12 months) - Full Service 48 2 H2

29 of 113

Create new Strategy “ZS20” for Performance-based Preventive based on “Engine Hours” for the following Cycles:

Package Cycle Length CycleTextHierarchy H.Text

1 1200 hours (around 3 months) - Inspect & Lubricate 12 1 H1

2 2400 hours (around 6 months) - Change Parts 24 1 H1

3 4800 hours (around 12 months) - Full Service 48 2 H2

SAVE

30 of 113

31 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

32 of 113

Create a Strategy-based Maintenance Task List “PM20Z”

33 of 113

For Strategy-based Preventive Maintenance, the Maintenance Strategy is Mandatory

34 of 113

Act Operation Description Work Un.

10 Inspect & Lubricate 1 H

20 Change Parts 3 H

30 Full Service 10 H

35 of 113

Act Operation Description Work Un.

10 Inspect & Lubricate 1 H

20 Change Parts 3 H

30 Full Service 10 H

Press ENTER

36 of 113

37 of 113

Map the Operation to the correct Cycle from the Strategy “ZS20”

38 of 113

39 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

40 of 113

check Maintenance Plan Category “PM”

41 of 113

Maint.plan cat. set with Call Object “Maintenance Order or Service Order”

Indicator that you use to specify that the release of scheduling for a maintenance plan is also documented with a change document.

Indicator which specifies that changes in certain predefined fields in the order are to be recorded in a document.

Indicator: Separate completion of maintenance call date

User can use this indicator to influence the maintenance processing process. For example, user can prevent that every employee who can complete orders and notifications can also influence the scheduling of maintenance plans through the data.

42 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

43 of 113

If blank, system use Internal Number Range assigned to the Maint.Plan Cat. “PM”

Maint.plan cat. “PM” (with Call Object as Maintenance Order”

Enter the new Strategy “ZS20”

44 of 113

Enter an appropriate Short Text

45 of 113

46 of 113

Counter from the Equipment is proposed

47 of 113

Measuring Point from the Equipment is proposed when the UOM (“h”) matches the UOM in the Strategy “ZS20” assigned

48 of 113

The Task List assigned must have the SAME Strategy as the Maint.Plan Header

49 of 113

Only when the Task List Strategy matches the Maint.Plan Strategy that the Cycles from the Strategy are Populated here

50 of 113

Strategy in the Maint.Plan Header CANNOT be Changed

51 of 113

Call Horizon is defaulted from the Strategy (or manual entered here)

52 of 113

Let’s say the Maint.Plan is valid for 3 years

53 of 113

Let Start Counter Reading is 0 (for new Equipment)

54 of 113

Internal number for Maint.Plan created

55 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

56 of 113

Online schedule the Maint.Plan

57 of 113

58 of 113

59 of 113

Current Counter Reading is 0

Packages as per the Strategy

60 of 113

Call dates are 2 days before the Plan date (Due date) due to the “Call Horizon”

All Packages on HOLD as there are NOT DUE yet

61 of 113

To simulate the Due of Package “12” (1200 hours), we shall enter a Measuring Document as 1210 hours

62 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11)
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

63 of 113

Enter next Counter Reading is 1210 hours in order to simulate the 1200 hour Cycle is due for Maintenance

64 of 113

Current Total Counter Reading is 0

Enter 1210 and press ENTER

65 of 113

New Total Counter Reading

66 of 113

Measuring Document for 1210 hours created

67 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

68 of 113

check Measurement Documents created for the Equipment

69 of 113

There are exactly 2 Measurement Documents created,

here I select the latest MeasDoc. and click “Measurement Document”

70 of 113

71 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

72 of 113

73 of 113

74 of 113

Notice, the latest Counter reading exceeding Package “12” cycle of 1200 hours

75 of 113

Package “12” (1200 hours) cycle is now DUE, and the Equipment is DUE for Maintenance

Note Call Date EMPTY, SAVE will Call a Maintenane Order

76 of 113

77 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

78 of 113

Access the Maint.Plan in IP10 to check the Called Maintenance Order

79 of 113

80 of 113

Planning Data from the Maintenance Item was used to create the Maintennece Order

81 of 113

82 of 113

Only Activity 10 is due as the Operation 0010 is assigned the the 1200 hour Cycle

83 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

84 of 113

Final Confirmation for the Maintenance Oder

85 of 113

TECO the MO

86 of 113

Reference Date and Time to update the Maint.Plan

Option to create Measurement Document (Counter Reading reported by Technician at time of Preventive Maint.work)

87 of 113

The Technician reported new Counter Reading at 1250 hours at time of Preventive Maintenance

(was 1210 previously)

88 of 113

Different between

Reading 2 (1210h)

Reading 3 (1250h) is 40h

89 of 113

See Slide 99 (this will update to the Call# in the Maint.Plan)

90 of 113

press ENTER again after SAVING

91 of 113

Maintenance Order is TECOed

92 of 113

Check the Counter Reading from the Technician

93 of 113

94 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

95 of 113

check Measurement Documents created for the Equipment at time of TECO

96 of 113

Measurement Document created for the Equipment at time of TECO

97 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

98 of 113

99 of 113

updated from the dates proposed (entered) at time of TECO (see slide 89)

Latest Counter Reading at time of TECO

100 of 113

New Due is Package for the

1200 hour and 2400 hour with 2 Operations

101 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

102 of 113

Enter Reading#4

at 2440 hours to simulate next Package Due for both 1200h and 2400h (result in 2 Operations in the MO)

103 of 113

Reading#3 was 1250

Reading#4 is 2440

Difference 1190

104 of 113

Reading#3 was 1250

Reading#4 is 2440

Measuring Document for Counter Reading#4 created

105 of 113

check Measurement Documents created for the Equipment (should be 4 Readings)

106 of 113

check Measurement Documents created for the Equipment (should be 4 Readings)

107 of 113

  • Create Characteristics “Z20_HOURS” (CT04).
  • Create Equipment “ZEQ20” with Measuring Point (IE01).
  • Initialize the Counter Reading of Measuring Point “12042” as zero hours (IK11).
  • Check Measuring Document entered in previous step (IE03).
  • Create a new Counter based Strategy “ZS20” with UOM “h” (hours) for multi-cycle Performance-based Preventive Maintenance (IP11).
  • Create a Strategy-based Maintenance Task List “PM20Z” (IA05).
  • Maintenance Plan Category “PM” (IMG).
  • Create Strategy Plan “ZMP20” (IP42).
  • Schedule the Maintenance Plan “261” (IP10).
  • Enter Measuring Document for Counter Reading as 1210 Hours (IK11).
  • Check Measuring Documents in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).
  • Display the Maintenance Order Called (IP10).
  • Confirm and TECO the 1200 hour Maintenance Order (IW42 & IW32).
  • Check Counter Readings in the Equipment Master (IE03).
  • Check Maintenance Order TECO and new Counter Reading in the Maintenance Plant (IP03).
  • Enter Measuring Document for Counter Reading as 2440 Hours (IK11) and All the Counter Readings in the Equipment (IE03).
  • Schedule the Maintenance Plan “261” again (IP10).

108 of 113

Schedule the Maintenance Plan “261” again (IP10).

109 of 113

Latest Counter Reading

2 Packages 1200h & 2400h now DUE, SAVE will create another Maintenance Order

110 of 113

111 of 113

112 of 113

113 of 113

Both Package 1200h and 2400h due and MO now with 2 Operations