2 of 21

Why we are planning

Strategic Plan

Maximized resources

The belief that the district's talent, physical, and financial resources should be maximized to support student learning while maintaining sound fiscal management.

Tonight

Committee working session

Added time for the committee to work through options and considerations built from its own table discussions.

Arlington ISD

Arlington ISD

3 of 21

Where we are in the process

Sept 14

Why we are planning

COMPLETED

Oct 13

Analyzing data and sharing observations

COMPLETED

Oct 29

Working session: options and considerations

TONIGHT

Nov 9

Exploring options

Dec 14

Shaping recommendations

January

Board presentation

Arlington ISD

Arlington ISD

4 of 21

Tonight's work

Your input

Options presented tonight were shaped by each table's work on the 12 planning areas.

Additional options

Options that build on your input, drawn from a deeper look at each planning area.

Considerations

Points to weigh with each option as the committee works toward December.

Discussion

Time to talk through the options together.

Arlington ISD

Arlington ISD

5 of 21

Options and considerations

Built from committee input

Arlington ISD

6 of 21

Long Range Facilities Planning

Michael Hill, Chief Operations Officer

6

Arlington ISD

7 of 21

2030 Projections Elementary Schools PK-5

7

Arlington ISD

Arlington ISD

8 of 21

8

Planning Area 1

School

Total

Capacity

Spaces

% Utilization

Butler

502

544

42

92.3

Ellis

807

836

29

96.5

Larson

319

714

395

44.7

Peach

854

955

101

89.4

DRAFT CONCEPT ONLY

Closing Sherrod and redistributing to Peach and Ellis

Concept can work see estimated utilizations

Arlington ISD

9 of 21

9

Planning Area 2

DRAFT CONCEPT ONLY

Closing Speer and redistributing to Webb and Webb to Pope

Webb would be full. Additional zoning and/or programing

Concept can work see estimated utilizations

School

Total

Capacity

Spaces

% Utilization

Pope

456

543

87

84.0

Webb

794

797

3

99.6

Arlington ISD

10 of 21

10

Planning Area 3

DRAFT CONCEPT ONLY

Closing Johns and redistributing to Thonton and Rankin

Additional zoning and/or programing

Thornton would be full

Concept can work see estimated utilizations

School

Total

Capacity

Spaces

% Utilization

Berry

611

809

198

75.5

Crow

419

722

303

58.0

Rankin

678

786

108

86.3

Thornton

761

797

36

95.5

Arlington ISD

11 of 21

11

Planning Area 4

​

​

​

​

​

​

​

DRAFT CONCEPT ONLY

Closing Crouch and Farrell. Redistribute Crouch to

Patrick and Anderson. Redistribute Farrell to Remynse

Thornton would be full

Concept can work see estimated utilizations

School

Total

Capacity

Spaces

% Utilization

Anderson

556

677

121

82.1

Patrick

618

966

348

64.0

Remynse

595

739

144

80.5

Arlington ISD

12 of 21

12

Planning Area 5

DRAFT CONCEPT ONLY

Expansion of South Davis provides the

opportunity to adjust attendance zones

Arlington ISD

13 of 21

13

Planning Area 6

DRAFT CONCEPT ONLY

Two options to consider – Closing Ditto and

Redistributing to multiple schools Miller, Little and Dunn

Or Closing Key and redistributing to Short and Little

​

Key option moves Short to 73% utilization

and Little to 87% utilization

​

Ditto option moves Miller to 64% utilization, Little to 86%

And Dunn to 85%

Arlington ISD

14 of 21

14

Planning Area 7

DRAFT CONCEPT ONLY

Two options to consider – Closing Morton and redistributing

to Burgin and Consolidating Amos and Goodman into a

new campus. Attendance zone adjustments from Blanton

Likely putting Burgin and Goodman overcapacity.

Additional zones or program changes would be needed

​

​

School

Total

Capacity

Spaces

% Utilization

Burgin

808

737

-71

109.6

Goodman

657

566

-91

116.1

McNutt

568

843

275

67.4

Arlington ISD

15 of 21

15

Planning Area 8

School

Total

Capacity

Spaces

% Utilization

Adams

677

924

247

73.3

Hale

495

728

233

68.0

DRAFT CONCEPT ONLY

Consolidating Atherton into Adams and Hale can work

Arlington ISD

16 of 21

16

Planning Area 9

DRAFT CONCEPT ONLY

Attendance zone options can be considered

Arlington ISD

17 of 21

17

Planning Area 10

DRAFT CONCEPT ONLY

Two options to consider – Closing West and redistributing

to Starrett and Consolidating Fitzgerald into Bryant.

​

West would need to move into Starrett due to Starrett having

a larger capacity

​

Starrett utilization would be 89%

Bryant utilization would be 96%

​

Could also consider attendance zone and program

modifications to improve utilization rates

​

Arlington ISD

18 of 21

18

Planning Area 11

DRAFT CONCEPT ONLY

Table comment was to consider making Pearcy a

magnet school of choice and zoning students to

Ashworth and Beckham. Could improve utilization for

Ashworth and Beckham. Pearch utilization would be

dependent on the program draw which could also

Impact rates for nearby schools.

​

Utilization estimates for Ashworth 87%

Beckham 73%

Arlington ISD

19 of 21

19

Planning Area 12

​

​

​

​

​

​

​

Grades 6-8

DRAFT CONCEPT ONLY

Attendance zone options can be considered to

reduce Rodriguez and Workman. Look to improve feeder patterns

and improve overall utilization rates

Arlington ISD

20 of 21

What comes next

Tonight

Tables discuss the options and considerations.

Before Nov 9

Committee input is collected and summarized.

November 9

Meeting 3: building on tonight's discussion.

Arlington ISD

Arlington ISD

21 of 21

Next meeting: November 9

IN PARTNERSHIP WITH

Arlington ISD