What still needs to be done?

  • Irrigation Pump
    • Landscaping
      • Phases 1-2

  • Increment #3

3 of 8

Franklin Elementary School

Increment #3 Demolition

CITIZENS’ BOND OVERSIGHT COMMITTEENovember 19, 2024

4 of 8

Franklin Elementary School

Increment #3 Demolition

CITIZENS’ BOND OVERSIGHT COMMITTEENovember 19, 2024

5 of 8

CITIZENS’ BOND OVERSIGHT COMMITTEENovember 19, 2024

6 of 8

CITIZENS’ BOND OVERSIGHT COMMITTEENovember 19, 2024

7 of 8

CITIZENS’ BOND OVERSIGHT COMMITTEENovember 19, 2024

What have we done?

  • Design Docs sent to DSA
  • Construction for Modular Classrooms has been awarded
  • PO issued for Shade structure and playground

What is next?

  • DSA Review scheduled to be complete in January
  • Construction of Buildings Begins
  • Demo/Site Work out to Bid (February)
  • Demo Work starts April
  • Summer 2025 - Classroom Installation
  • September / October - ribbon cutting