1 of 12

Grapesyard Organization

Sent by:

Edmond Opondo Oloo

Executive Director

Grapesyard Organization

March 2022

UPDATE REPORT

Construction of Junior secondary school

for orphans and vulnerable children in Gorogocho

Shared with

Prof Richard Miller

2 of 12

Introduction.�

  • Grapesyard School is run by Grapesyard Organization, a Kenyan not for profit organization that work with orphans and vulnerable children in difficult social situation.
  • Kenya’s new education curriculum called competency based curriculum ( CBC) is designed for 6 years of primary schooling (grades 1 to six), 3 years for Junior secondary (grades 7,8 and 9). After junior secondary is senior secondary.
  • The first cohort of CBC students are currently in grade 6.
  • They will sit for the final primary education in the month of November 2022. Transition to Junior secondary will be in January 2023

3 of 12

The silent problem

  • Upon completion of primary education at grade 6, transition to junior secondary will not be done through selection and placement by Government.
  • Children are expected to join Junior Sec school within their school or home neighborhoods.
  • Korogocho & its neighborhood has only 3 Government schools to cater for over 100, 000 students.

4 of 12

The infrastructure gaps

  • Already the existing government schools are congested. This means they will not have space for children from other schools.
  • The effect of this means that children from community schools such as Grapesyard will not have space in Junior secondary.
  • Many children will drop out of school prematurely.

5 of 12

Filling the gaps

  • Grapeyard has embarked on a construction project to put up classrooms that will absorb its children for Junior secondary education. The challenge is raising enough funds.
  • The school has planed to construct 4 storey / floor building.
  • The building will host classrooms, science labs, one large dining hall, staffroom & offices.
  • One floor is designed for a medical clinic.

6 of 12

The house below was a private rental building within school compound. It was bought by school for space

7 of 12

Demolition of the old house to pave way for a 4 floor building.

8 of 12

Junior secondary bounding foundation construction

9 of 12

Current stage of construction has reached.

10 of 12

Grapesyard school – construction site� March 2022

11 of 12

Next steps…..

  • Casting of the foundation slab
  • Building the walls
  • First floor slab and finishes ready for current grade 6 students come January 2023.
  • Continue the rest of construction to realize 4 floors.

12 of 12

JOIN US IN MOBILIZING RESOURCES FROM FRIENDS AND WELL WISHERS