Home Renovation - Addition of a Nursery
Alyssa Plemel, Hailey Le Mere, Kaitlin Klein, Seng Raw, and Samantha Schwarz
Project Description
Jack and Annie Smith live in a four-bedroom home in Green Bay, Wisconsin. The couple recently found out that Annie is pregnant with their third child. Currently, the only spare bedroom in their house is being used as Jack’s office, so they’ve decided to hire a contractor to build a 12’ x 12’ addition on the ground floor.
Objectives
In Scope
|
|
|
|
|
|
|
|
|
|
|
|
| |
Out of Scope
Deliverables
Budget Estimates
Time Estimates
Floor Plan
12’
12’
List of Materials
Project Team
Priority Matrix
| Time | Performance | Cost |
Constrain | | | |
Enhance | | | |
Accept | | | |
Work Breakdown Structure (WBS)
WBS (Planning Section)
WBS (Foundation Section)
WBS (Exterior Section)
WBS (Interior Section)
Project Network Information
Activity | Description | Preceding activity | Activity time |
A | Design room | None | 15 days |
B | Gather bids | A | 10 days |
C | Choose contractor | B | 5 days |
D | *Secure financing | B | 3 days |
E | Acquire permits | B | 4 days |
F | *Meet contractor | C,D,E | 1 day |
G | Gather materials | F | 7 days |
H | Prepare site | G | 5 days |
Project Network Information (cont.)
Activity | Description | Preceding activity | Activity time |
I | Lay foundation | H | 2 days |
J | Frame room | I | 5 days |
K | Install roof | J | 4 days |
L | Add window, siding, HVAC, & wiring | K | 13 days |
M | Inspector signs off | L | 1 day |
N | Complete interior finishing | M | 32 days |
O | Add furniture & decor | N | 32 days |
Activity-on-Node Network (part 1)
Activity-on-Node Network (part 2)
Task Assignments
Task | Assignee |
Design room | Jack and Annie Smith |
Gather bids | Jack and Annie Smith |
Secure financing | Jack and Annie Smith |
Acquire permits | Jack and Annie Smith |
Choose contractor | Jack and Annie Smith |
Meet contractor | Jack and Annie Smith, Curt Contractor |
Dig (excavate) | Eddie Excavator, Ethan Excavator |
Level the property | Eddie Excavator, Ethan Excavator |
Task Assignments (cont.)
Task | Assignee |
Frame foundation | Brad Builder, Curt Contractor |
Pour concrete | Brad Builder, Curt Contractor |
Frame exterior | Brad Builder, Curt Contractor |
Shingles | Rick Roofer, Curt Contractor |
Gutter | Rick Roofer |
Window | Chris Carpenter |
Siding | Chris Carpenter, Brad Builder |
HVAC | Henry Heater |
Task Assignments (cont.)
Task | Assignee |
Frame walls | Chris Carpenter, Curt Contractor |
Insulate walls | Brad Builder, Chris Carpenter |
Drywall | Brad Builder, Chris Carpenter |
Paint | Curt Contractor |
Rough in electrical | Eli Electrician |
Install electrical | Eli Electrician |
Install laminate flooring | Chris Carpenter |
Trimwork | Chris Carpenter |
Task Assignments (cont.)
Task | Assignee |
Purchase and install furniture & decor | Jack and Annie Smith |
Final inspection | Ian Inspector |
Time Estimates (from WBS)
Time Estimates (cont.)
Cost Estimates (from WBS)
Resource Scheduling
S
Cost Scheduling
Cost Scheduling (cont.)
Risks and Contingencies
Risk Event | Response | Contingency Plan | Trigger |
Ground freezing before excavation | Mitigate: Monitor projected temperatures | Start excavation early | Projected low temperature of 35 degrees |
Security Issues | Transfer: Insurance | Purchase insurance to cover security risks | Project Begins |
Dissatisfied Customer | Mitigate: include customer in planning and give regular updates | Address concern right away and make adjustments accordingly | Customer has concern |
Supplier Issues | Mitigate: build relationships with multiple suppliers | Use a different supplier for these materials | A supplier is unable to deliver product on time |