1 of 11

Gas-In &Start-UP� HSE �Induction

2 of 11

Site Access Control

  • Main gates to site Gate No.1 and Gate No.2
  • Two Gates Between Green area & Process area
  • Gate No. 3 for site vehicles and equipment
  • Gate No.4 for site personnel
  • Handover I.D. , Cigarettes , Matches and liters (recive Pigeonhole No.)
  • Switch off Mobil phone before Entry to process area .

3 of 11

Emergency Rules

  • Discontinuous siren
  • Evacuation to Assembly points
  • Four Assembly points identifies by green flag
  • Personnel account by Area coordinator
  • Continuous Siren Emergency Clearances and Back to work.

4 of 11

8-Golden Rules

  • Permit to Work
  • Working at Height
  • Energy Isolation
  • Vehicle Safety
  • Ground Disturbance
  • Confined Space Entry
  • Lifting Operations
  • Management of Change

5 of 11

Smoking rules

  • Smoking is not allowed at process area

  • Smoking only allowed at the Green area

6 of 11

Vehicle & Equipment� Entry

  • Using Gate No.2
  • Inspection
  • Installing Flame Arrestors with Exhaust
  • Provide fire Extinguishers

7 of 11

Hot work activates

  • Hot work Permit
  • Welding shed
  • Free Gas testing
  • Housekeeping
  • Fire extinguishers
  • Fire Watch

8 of 11

Thanks �

9 of 11

Driving Rules

  • Speed limit 20km/hrs
  • Keep set belt
  • No Mobil using
  • No deviation from Black road
  • In case of emergency Evacuation , keep your vehicle on right side for the road ,switch off engine & leave vehicle key in contact

4

10 of 11

Permit To Work system

  • UGDC Permit to work
  • Risk assessment
  • Golden rules
  • Permit Issuing and renewal from 2:00 Pm to 4:00 Pm
  • Permit Handover at 4:00 Pm daily

4

11 of 11

Site Lay out

3

5

2