Construction Update

2 of 7

Construction Update as of 6/13/2024:

  • Stormwater detention chamber completed

  • Restaurant windows completed and passed testing

  • Restaurant interiors 80% complete

  • Auditorium interiors 90% complete

  • Innovation Center interiors 80% complete

  • Sitework 80% complete

  • Current contract work scheduled to be complete 12/30/24

3 of 7

Aerial view of the CIP campus - 19 Apr 2024

4 of 7

Looking towards Diamond Head at Restaurant/Auditorium Building

5 of 7

Looking towards Kaimuki, view of the Auditorium entrance (left) and back of restaurant (right).

6 of 7

Looking East at Restaurant entryway and lookout area.

7 of 7

View of the Culinary Innovation Center -roofing and exterior sheathing complete.