Waste Isolation Pilot Plant

James Mason�Institutional Affairs Program Manager

Carlsbad Field Office�

2 of 11

Waste Isolation Pilot Plant Mission

2

To provide safe and compliant characterization, transportation, and disposal of the United States’ defense transuranic (TRU) waste while protecting workers, the public and the environment.

3 of 11

WIPP TRU Waste Disposal

  • WIPP Land Withdrawal Act (LWA)
  • Defense generated transuranic waste
  • Must meet WIPP Waste Acceptance Criteria
  • WIPP transuranic waste capacity 6.2M ft3
    • Current volume capacity filled = 2.7M ft3 (~45%)

3

Waste drums safely emplaced in a WIPP underground repository room

4 of 11

Waste Emplacement Update

432 waste shipments received in FY2025

Current status:

  • Emplacing waste in Panel Eight, Room 3
  • 29,226 containers in Panel Eight

4

5 of 11

Prepping the West Mains & Panel 11

5

6 of 11

Overall Mission Accomplishments

  • Total shipments: 14,704
  • FY26 shipments received: 103
  • Total loaded miles: 17,634,953
  • Total miles driven: 35,269,906

6

7 of 11

Infrastructure Investments

Projects will:

  • Provide full ventilation flow rate to the underground repository
  • Improve reliability
  • Enhance worker safety
  • Minor Construction Projects (MCP) support the Underground Ventilation System (UVS) & Utility Shaft (US) completion

7

New Utility Shaft

UVS Salt Reduction Building

UVS New Filter Building

8 of 11

Underground Ventilation System (UVS) Project Overview

8

The UVS project will provide a safety significant confinement ventilation system that can be operated in a HEPA-filtered mode or an unfiltered mode of operation with two buildings, New Filter Building (NFB) and the Salt Reduction Building (SRB).�

NFB

  • 22 HEPA Filters
  • Six Induced Draft Fans
  • Six Variable Frequency Drive
  • 540,000 CFM�

SRB

  • Six De-dusters and De-misters
  • Two Brine Water Storage 80,000 Tanks

9 of 11

Underground Ventilation System (UVS)

Progress

  • Operations 90-day run – Complete
  • Management Self Assessment Phase 1 – Complete
  • Management Self Assessment Phase 2 – Complete
  • Contractor Readiness Assessment – Complete
  • Wye connection – Complete
  • System brought online – Complete

9

Increasing airflow to the underground up to 540,000 cubic feet per minute

Completed exhaust shaft ductwork and support structure taking air to the new UVS.

10 of 11

Utility Shaft (US) Project Overview�

10

11 of 11