GAO Cost Guide and 10 Years of Cost Estimate Assessments

Benjamin Wilder

Slide 1

Slide 1

2 of 30

Outline

  • Background (GAO)
  • Best Practice Guides
  • 10 Years of Assessments
  • Case Study: Credible Characteristic

Slide 2

Slide 2

3 of 30

Background

Slide 3

Slide 3

4 of 30

Overview: About GAO

  • GAO is an independent, nonpartisan agency serving the Congress to help improve the performance and ensure the accountability of the federal government.

  • Core values are Accountability, Integrity, and Reliability.

  • To ensure independence, the Comptroller General (CG) is appointed to a 15-year term by the President. Other than the CG, there are no political appointees at GAO.

Oversight, Insight, Foresight

Slide 4

5 of 30

Overview: About GAO (Our Work)

  • GAO work is primarily done at the request of congressional committees or subcommittees or is mandated by public laws or committee reports. We also undertake research under the authority of the Comptroller General.
  • Some examples of our work include:
    • Auditing agency operations to determine whether federal funds are being spent efficiently and effectively
    • Investigating allegations of illegal and improper activities
    • Reporting on how well government programs and policies are meeting their objectives
    • Performing policy analyses and outlining options for congressional consideration
    • Issuing legal decisions and opinions, such as bid protest rulings and reports on agency rules
  • In 2018, Congress directed the formation of the Science, Technology Assessment, and Analytics (STAA) team, recognizing that the accelerating pace of innovation has created a need for more and deeper analysis of science and technology.

More information about GAO can be found at www.gao.gov

Slide 5

6 of 30

Best Practice Guides

Slide 6

Slide 6

7 of 30

Overview: Best Practice Guides

  • Legislators, government officials, and the public want to know whether government programs are achieving their goals and what these programs are expected to cost and when they are expected to be finished.
    • Best practice guides provide clear criteria to establish the quality of program artifacts and whether they provide managers and oversight organizations enough information to make informed decisions.�
  • Developing reliable program cost and schedule estimates is critical to
    • Effectively using public funds
    • Meeting OMB’s capital programming process
    • Avoiding cost overruns, missed deadlines, and performance shortfalls

  • The Guides help provide a framework for managing the government’s complex efforts and ensuring the successful development and integration of cutting-edge technologies and their integration into large and complex systems.

Why develop best practice guides?

Slide 7

8 of 30

Overview: Best Practice Guides

  • Cost Estimating and Assessment Guide
    • Issued: March 2020, GAO-20-195G

  • Schedule Assessment Guide
    • Issued: December 2015, GAO-16-89G

  • Technology Readiness Assessment Guide
    • Issued: January 2020, GAO-20-48G

  • Agile Assessment Guide
    • Issued: November 2023, GAO-24-105506

Slide 8

9 of 30

Cost Estimating and Assessment Guide

GAO Criteria

GAO Cost Guide: https://www.gao.gov/products/GAO-20-195G

Through the evaluation of 18 best practices

By determining the extent to which the estimates are:

Comprehensive

Well-documented

Accurate

Credible

Assess program life cycle cost estimates

Cost Assessment

Slide 9

10 of 30

Cost Estimating 12 Step Process

Slide 10

11 of 30

Comprehensive Characteristic

Slide 11

12 of 30

Well Documented Characteristic

Slide 12

13 of 30

Accurate Characteristic

Slide 13

14 of 30

Credible Characteristic

Slide 14

15 of 30

10 Years of Assessments

Slide 15

Slide 15

16 of 30

10 Years of Assessments

  • We performed cost estimate assessments for 117 programs across the federal government contributing to the publication of 75 GAO reports.
  • Program selection is primarily done at the request of Congress.
  • Often programs are selected due to risk level or existing performance issues.
  • Majority of reports lead to recommendations for areas of improvement.
  • When recommendations are addressed by the agency a follow up assessment is performed and a determination is made whether to close the recommendation.

Slide 16

17 of 30

Who Have We Assessed

23 Agencies

10 Air Force

6 Army

6 Navy

6 Marine Corps

6 Other DoD Entities

10 National Nuclear Security Administration

5 Office of Environmental Management

6 Other DOE Entities

U.S. Department of Homeland Security

5 Customs and Border Protection

4 Transportation Security Administration

4 U.S. Coast Guard

7 Other DHS Entities

Other Government Agencies

5 Housing and Urban Development

5 Veterans Affairs

3 Commerce

3 Agriculture

3 State

3 Administrative Office of the U.S. Courts

2 NASA�2 Labor

2 Treasury

2 General Services Administration�2 Architect of the Capitol

2 Library of Congress

8 Other Government Entities

Cost Estimate Assessments 2014-2023

Slide 17

18 of 30

How Are Assessments Scored

  • Each best practice has associated criteria.
  • We assess evidence against these criteria to determine how well they were met.
    • Criteria can be found at the end of each Step chapter in the Cost Guide.
  • We rate each best practice based on the fulfillment of its criteria.
  • We average the rating of each best practice to determine the score of the overall characteristic.
  • A cost estimate is considered reliable if the overall assessment ratings for each of the four characteristics are substantially or fully met.
  • If any of the characteristics are not met, minimally met, or partially met, then the cost estimate does not fully reflect the characteristics of a high-quality estimate and cannot be considered reliable.

Slide 18

19 of 30

Best Practice Scoring

The organization provided no evidence that satisfies any of the criterion.

Not Met = 1

    • The organization provided evidence that satisfies a small portion of the criterion.

Minimally Met = 2

    • The organization provided evidence that satisfies about half of the criterion.

Partially Met = 3

    • The organization provided evidence that satisfies a large portion of the entire criterion.

Substantially Met = 4

    • The organization provided complete evidence that satisfies the entire criterion.

Fully Met = 5

Best Practice

Individual Assessment

Score

The cost estimate includes all life cycle costs

Substantially Met

4

The cost estimate is based on a technical baseline description that completely defines the program, reflects the current schedule, and is technically reasonable.

Partially Met

3

The cost estimate is based on a WBS that is product-oriented, traceable to the statement of work, and at an appropriate level of detail to ensure that cost elements are neither omitted nor double-counted.

Met

5

The cost estimate documents all cost-influencing ground rules and assumptions.

Minimally Met

2

Average Score (4 + 3 + 5 + 2) / 4 = 14 / 4

3.5

Comprehensive

Overall Assessment

Substantially Met

Slide 19

20 of 30

Agency Cost Estimate Ratings Varied Over Past 10 Years

  • Scores are reflections of the program estimates assessed, not the agency itself.

  • Scores are presented as of the assessment published in the GAO report.

  • Recommendation follow-ups occur after the published report that may lead to a higher score and closure of the recommendation.

  • Program cost estimates most consistently scored lowest in the best practices associated with the Credible characteristic.

Slide 20

21 of 30

Reliability Assessment - Data in Detail

A cost estimate is considered reliable if the overall assessment ratings for each of the four characteristics are substantially or fully met.

  • 88 Full Reliability Assessments
    • 6 Reliable (7%)
    • 82 Not Reliable (93%)

  • 20% of “Not Reliable” assessments are Near Misses – Only one of the four characteristics was scored lower than Substantially Met
      • 15 Credible Near Misses (17%)
      • 2 Well Documented Near Misses (2%)
      • 1 Comprehensive Near Miss (1%)

Slide 21

22 of 30

Reliability Assessment - Data in Detail (SW and IT)

Slide 22

23 of 30

Case Study:�Credible Characteristic

Slide 23

Slide 23

24 of 30

Revisiting the Credible Characteristic

Slide 24

25 of 30

Credible Characteristic Case Study: GAO-23-106067

As of June 2023, cost estimates for several Shipyard Improvement Optimization Program (SIOP) efforts had increased significantly from their original baseline estimate. One such project, the Portsmouth Naval Shipyard drydock grew 4x in 2.5 years. GAO assessed the extent to which the Portsmouth Naval Shipyard dry dock cost estimate met GAO’s best practices.

Slide 25

26 of 30

Credible Characteristic Case Study: GAO-23-106067

GAO Found:

    • Cost risk and uncertainty analysis and sensitivity analysis was performed on the January 2019 project estimate, representing a maturity level of 15 percent, but was not updated to reflect the final design estimate that informed the project budget request.
    • The project estimate did not contain any documented cross-checks
    • The Navy did not conduct an Independent Cost Estimate (ICE)

Substantially Met

Substantially Met

Fully Met

Minimally Met

GAO recommended the Navy update their cost risk and uncertainty and sensitivity analyses of key SIOP projects throughout the design process as well as ensure that high-value cost elements are cross-checked using different estimating methodologies

Slide 26

27 of 30

Thank you

Guides Available Online and Downloadable in PDF:

GAO Cost Estimating and Assessment Guide:

https://www.gao.gov/products/gao-20-195g

GAO Schedule Assessment Guide:

https://www.gao.gov/products/gao-16-89g

GAO Technical Readiness Assessment Guide:

https://www.gao.gov/products/gao-20-48g

GAO Agile Assessment Guide:

https://www.gao.gov/products/gao-24-105506

Slide 27

Slide 27

28 of 30

GAO on the Web

Web site: http://www.gao.gov/ 

Facebook: https://www.facebook.com/usgao

Twitter: https://twitter.com/usgao

YouTube: https://youtube.com/user/usgao

Podcasts: http://www.gao.gov/podcast/watchdog.html

Copyright

This is a work of the U.S. government and is not subject to copyright protection in the United States. The published product may be reproduced and distributed in its entirety without further permission from GAO. However, because this work may contain copyrighted images or other material, permission from the copyright holder may be necessary if you wish to reproduce this material separately.

Slide 28

Slide 28

29 of 30

Back Up

Slide 29

Slide 29

30 of 30

Cost Estimating Best Practices

Comprehensive

    • Includes all life cycle costs
    • Based on a technical baseline description
    • Documents cost-influencing ground rules and assumptions
    • Based on a product oriented WBS

Well-Documented

    • Shows the source data used
    • Describes step by step how the estimate was developed
    • Discusses the technical baseline description
    • Provides evidence that the cost estimate was reviewed and accepted

Accurate

    • Adjusted properly for inflation
    • Based on a historical record
    • Uses the best methodology from the data collected
    • Contains few, if any, minor mistakes
    • Documents and explains variances
    • Regularly updated

Credible

    • Conduct sensitivity analysis
    • Conduct risk and uncertainty analysis
    • Perform cross checks
    • Compare to an independent estimate

Slide 30