Bond Planning Process
Board Workshop
September 13, 2022
Introductions
Introductions
Miller Canfield – Bond Legal Counsel
PFM Financial – Financial Advisor
Wakely Associates – Architect
Peter Basso Associates – Mechanical/Electrical Engineer
Spalding DeDecker – Civil Engineer
Barton Malow Builders – Construction Manager
Banach, Banach, & Cassidy – Campaign Specialist
Agenda
Capital Improvement Planning
AGENDA
Overview
Capital Improvement Planning
Overview
Life Cycle / Cost Analysis
Typically, a school district will Bond every 5-10 years to
keep current and replace building infrastructure. The
lifecycle of equipment varies and all equipment won’t
fail at the same time.
We try to minimize repair costs now because repair
costs and often exceed replacement cost.
Difficult to find replacement parts
STUDENT ABILITY TO LEARN IS AFFECTED BY NOISE, TEMPERATURE, CO2 LEVELS
Financial Information
Funding Options
Bonds
Qualified Bond
Non-Qualified Bond
Sinking Fund
Other
Financial Info
Qualified Bond History
With Millage Increase:
57% Pass Rate
Without Millage Increase: 91% Pass Rate
Financial Info
Macomb County Rates
School District | Debt | Sinking Fund | Total Debt |
Clintondale Community Schools | 13.0000 | | 13.0000 |
Mt Clemens Community Schools | 11.8000 | | 11.8000 |
Roseville Community Schools | 11.2000 | | 11.2000 |
Anchor Bay Schools | 10.0000 | | 10.0000 |
Van Dyke Public Schools | 9.7000 | 0.9846 | 10.6846 |
Fitzgerald Public Schools | 9.4000 | 3.0000 | 12.4000 |
Chippewa Valley Schools | 8.6400 | | 8.6400 |
Warren Woods Public Schools | 8.5400 | | 8.5400 |
New Haven Community Schools | 8.2600 | | 8.2600 |
Lakeview Public Schools | 7.5000 | | 7.5000 |
Centerline Public Schools | 7.4000 | | 7.4000 |
Armada Area Schools | 7.0000 | 0.8394 | 7.8394 |
Fraser Public Schools | 7.0000 | | 7.0000 |
L'Anse Creuse Public Schools | 7.0000 | | 7.0000 |
LakeShore Public Schools | 7.0000 | | 7.0000 |
Richmond Community Schools | 6.9500 | | 6.9500 |
South Lake Schools | 6.0212 | 0.9788 | 7.0000 |
Warren Consolidated Schools | 4.7800 | | 4.7800 |
Romeo Community Schools | 3.9900 | 1.2396 | 5.2296 |
Eastpointe Community Schools | 3.5000 | 3.0000 | 6.5000 |
Utica Community Schools | 3.5000 | | 3.5000 |
Financial Info
Qualified Bond Scenarios
Information provided by PFM
Timeframe
Capital Improvement Planning
PATH
May
August
Nov.
1 Year
COMPLETE
Timeframe
Develop Detailed Schedule
SAMPLE
Current Industry Status
Current Industry Status
Post Covid experience
Material Lead Times:
Facility Needs
Data Gathering
Scope
Capital Improvement Planning
Facility Needs Assessment
Categories
Prioritization
DRY, WARM, SAFE
Capital Improvement Planning
Site Work
Capital Improvement Planning
Building Exterior
Capital Improvement Planning
Mechanical Work
Capital Improvement Planning
Electrical Work
Capital Improvement Planning
Athletics, Arts, Academics
Capital Improvement Planning
Safety & Security
Capital Improvement Planning
Furniture, Equipment, Buses
Purchase 3 buses to replace 3 (C2 Thomas Built Busses) They are:
Bus 6 91,504 miles
Bus 8 91,375 miles
Bus 17 88,996 miles
Technology
Technology Update Overview
Schedule based on date purchased and expected lifespan. Also combined with dependent equipment needs.
Capital Improvement Planning
Technology
| 2023 Preliminary Bond Application Budgets | | |||||
| Infrastructure | Non- Instructional | Instructional | Contingency | Design | TOTAL | Building Total |
Disney | 66,348 | 6,425 | 470,867 | 27,206 | 9,675 | 580,521 | $ 514,095 |
Edison | 74,169 | 7,710 | 595,476 | 33,897 | 11,556 | 722,808 | $ 640,090 |
Eisenhower | 77,575 | 7,710 | 643,524 | 36,472 | 12,308 | 777,589 | $ 688,578 |
Emerson | 62,628 | 6,425 | 461,442 | 26,548 | 9,314 | 566,357 | $ 501,559 |
Salk | 87,035 | 6,425 | 719,656 | 40,692 | 13,784 | 867,592 | $ 768,183 |
Twain | 65,024 | 6,425 | 495,008 | 28,348 | 9,841 | 604,646 | $ 535,449 |
Richards | 376,458 | 61,040 | 1,512,334 | 97,580 | 42,488 | 2,089,900 | $ 1,852,363 |
Fraser High | 645,645 | 124,670 | 3,005,572 | 188,606 | 77,583 | 4,042,076 | $ 3,582,988 |
Dooley | 55,248 | 5,140 | 68,642 | 6,458 | 4,595 | 140,083 | $ 124,198 |
Admin | 126,894 | 12,208 | 16,737 | 7,800 | 9,044 | 172,683 | $ 153,339 |
O&M | 10,848 | 3,855 | 2,906 | 881 | 789 | 19,279 | $ 17,228 |
Bus garage (transportation) | 5,424 | 3,213 | 533 | 459 | 385 | 10,014 | $ 9,000 |
Sub-total | 1,653,295 | 251,246 | 7,992,695 | 494,947 | 201,362 | 10,593,544 | $ 9,387,066 |
Informational Campaign
Informational Campaign
Resources / Assistance
Informational Campaign
Next Steps
Next Steps
Timeline
September 2022 Refine Scope
October 24, 2022 Board Review Draft Bond Program
November 7, 2022 Board Review Bond Program
November 16, 2022 Review with Department of Treasury
December 2022 Develop Campaign Materials
January 23, 2023 Board Call for Election
February 2023 Inform Absentee Voters
March 2023 Absentee Ballots Available
April 2023 Continue Informational Campaign
May 2, 2023 Bond Vote
2023 - 2026 Design Phases
2024 - 2027 Construction Phases
2025 Technology Refresh
Thank You