1 of 15

Lone Oak I.S.D.

2021 Bond Program

CONSTRUCTION UPDATE

February 19, 2024

2 of 15

BOND RECAP

  • November 2021 – Bond Passed
    • Partnered with Pogue Construction

  • March 2022 – Football Field Renovations & Turf GMP

  • July 2022 – Balance of Football Renovations

  • August 2022 – Baseball & Softball GMP

  • March 2023 – High School Additions GMP

3 of 15

SCOPE RECAP

  • Athletics
          • Football Field Renovations & Turf
          • New Baseball & Softball Complex

  • High School Additions
          • Classrooms & Science Labs
          • Dining Hall & Kitchen
          • Competition Gym
          • Weight Room & Locker Rooms
          • Band Hall
          • Safety Areas

4 of 15

5 of 15

6 of 15

CONSTRUCTION UPDATE

  • Athletics
          • Football Field Renovations & Turf
              • November 2021 – Start of Construction
              • October 2022 - Complete

          • New Baseball & Softball Complete
              • September 2022 – Start of Construction
              • December 2023 - Complete

  • High School Additions
              • June 2023 – Start of Construction

  • Overall Construction Progress - 48% Complete

7 of 15

8 of 15

9 of 15

10 of 15

11 of 15

12 of 15

WHERE WE’RE HEADED

13 of 15

14 of 15

15 of 15

www.pogueconstruction.com

QUESTIONS?