Improved Future IF

2 of 14

AGENDA IF

Project duration: 2 year

From 2008-12-01 to 2010-11-30

1

3 of 14

Kick off Meeting IF27th and 28th January 2009

Tuesday, 27th January 2009

09:30 – 12:30 Welcome and presentation of partners

The project aims, objectives

The operational steps and products expected

12:30 – 14:00 Lunch

14:00 – 18:00 Looking through the work packages

Estimated calenda , Further steps – Deadlines

Meeting dates

20:00 Dinner

2

4 of 14

Kick off Meeting IF27th and 28th January 2009

Wednesday, 28th January 2009

09:30 – 12:00 Administrative and financial framework:

Budget, reporting, supporting documents

Any other issues

Short summary of the kick-off meeting and decision taken

13:00 Lunch

After Lunch – individual meetings in the lobby

3

5 of 14

The project partnership IF

Austria BEST ( Core Partner)

Holland ROC/Nijmegen ( Core Partner)

Denmark PP/Peter Plant ( Expert)

Romania Carpathian Foundation Romania( Learning Partner)

United Kingdom University of Glasgow ( Expert)

Turkiye TEK-SAV ( Learning Partner)

Germany Qualifizierungs und Vermittungs GmbH ( Core P)

France IRFA SUD ( Core Partner)

Bulgaria Business Foundation for Education

( Internal Evaluator)

Sweden Folkuniversitetet ( Lead Organization)

4

6 of 14

Project aim IF

5

The aim of the project is to assist and/or train individuals involved in the guidance and counseling sector and educational sector to increase their knowledge and understanding of the barriers that encumbers immigrants and promote social dialogue in order to facilitate better support to immigrants

7 of 14

Project objectives IF

6

-Collect information and identify existing barriers about immigrants in respectively partners’ country and the guidance and counseling sector what their thoughts about these barriers and what measurements could be implicated to prevent the exclusion.

-Establish strategic advisory committee that will provide feedback and viewpoints during the projects work packages. The strategic advisory committee will also be an important part in the valorization strategy.

8 of 14

Project objectives IF

7

-Develop a course and material to address and understand the question of immigration more effectively and adequately.

-The partners will then implement the developed methodological approaches in training seminars for individuals in the guidance and counselling sector and educational sector.

9 of 14

Products expected IF

8

To make a report of the current immigration trends and situation in the core partner countries

A handbook ” European Solution to Facilitate Immigrants into the Labour Market”

Adaption manual for core partner countries

Training seminar for personnel involved in guidance and counselling for immigrants

10 of 14

Work package IF

9

Workpackage

Workpackage results

Package leader

Project management

Delivery of project outcomes, project website, monitor inter-action and cooperation between workpackages…

Sweden

Network coordination

Establish a strategic advisory board, an enlarged national/regional/local network…

Sweden

Analysis of current immigration trends and situation in the core partners countries…

National review reports, a synthesis report, publish material on the projects website….

Holland

Transfer of innovation phase

Adaption material that is suitable for incorporation to a curriculum for counsellor and guidance staff…

United Kingdom

Course adaption and development

A course, a handbook and training seminar…

Denmark

11 of 14

Work package IF

10

Workpackage

Workpackage results

Package leader

Adaption and Validation phase

Training seminar in respective country, analysis about the training material, a synthesis report…

Austria

Website

Project website

Sweden

Dissemination and Valorisation

Information material about the project, publications in professional journals, national dissemination seminars….

Austria

Evaluation plan

Interim report, a final evaluation report, ongoing analysis and recommendations

Bulgaria

Quality Management

Review that fixed criteria meet the quality management plan

Sweden, Bulgaria

12 of 14

11

Dec

08

Jan

09

Feb

09

Mar

09

Apr

09

May

09

Jun

09

Jul

09

Aug

09

Sep

09

Oct

09

Nov

09

Dec

09

Jan

10

Feb

10

Mar

10

Apr

10

May

10

Jun

10

Jul

10

Aug

10

Sep

10

Oct

10

Nov

10

WP 1

Project

Management

WP 2

Network

Coordination

WP 3

Analysis

WP 4

Transfer

WP 5

Course

adaption

WP 6

Adaption

WP 7

Website

2012-11-31

WP 8

Dissemination

and valorisation

WP 9

Evaluation

WP 10

Quality management

13 of 14

Meeting Days IF

12

27-28 January France

26-27 may 2009 Romania

20-21 October 2009 Turkiye

13-14 April 2010 Bulgaria

28-29 Sep.(2010) Sweden