BASIC ELECTRICAL ENGINEERING
Lecture slides by
MR. A BHUYAN
ASST. PROFESSOR
GIET, BBSR
Hydro Power
How Hydropower Works!
How Hydropower Works! (ctd…)
POTENTIAL
Potential
Continent Wide distribution
REGION | THEORETICAL POTENTIAL (TWh) | TECHNICAL POTENTIAL (TWh) |
AFRICA | 10118 | 3140 |
N. AMERICA | 6150 | 3120 |
LATIN AMERICA | 5670 | 3780 |
ASIA | 20486 | 7530 |
OCEANIA | 1500 | 390 |
EUROPE | 4360 | 1430 |
WORLD | 44280 | 19390 |
Top ten countries (in terms of capacity)
COUNTRY | POWER CAPACITY (GWh) | INSTALLED CAPACITY (GW) |
TAJIKISTAN | 527000 | 4000 |
CANADA | 341312 | 66954 |
USA | 319484 | 79511 |
BRAZIL | 285603 | 57517 |
CHINA | 204300 | 65000 |
RUSSIA | 160500 | 44000 |
NORWAY | 121824 | 27528 |
JAPAN | 84500 | 27229 |
INDIA | 82237 | 22083 |
FRANCE | 77500 | 77500 |
UNDP estimates
Continued…
Global Installed Capacity
Under Construction…
The Indian Scenario
Continued …
India’s Basin wise potential
Rivers | Potential at 60%LF (MW) | Probable installed capacity (MW) |
Indus | 19988 | 33832 |
Ganga | 10715 | 20711 |
Central Indian rivers | 2740 | 4152 |
West flowing | 6149 | 9430 |
East flowing | 9532 | 14511 |
Brahmaputra | 34920 | 66065 |
Total | 84044 | 148701 |
Region wise status of hydro development
REGION | POTENTIAL ASSESSED (60% LF) | POTENTIAL DEVELOPED (MW) | % DEVELOPED | UNDER DEVELOPMENT |
NORTH | 30155 | 4591 | 15.2 | 2514 |
WEST | 5679 | 1858 | 32.7 | 1501 |
SOUTH | 10763 | 5797 | 53.9 | 632 |
EAST | 5590 | 1369 | 24.5 | 339 |
NORTH EAST | 31857 | 389 | 1.2 | 310 |
INDIA | 84044 | 14003 | 16.7 | 5294 |
Major Hydropower generating units
NAME | STATA | CAPACITY (MW) |
BHAKRA | PUNJAB | 1100 |
NAGARJUNA | ANDHRA PRADESH | 960 |
KOYNA | MAHARASHTRA | 920 |
DEHAR | HIMACHAL PRADESH | 990 |
SHARAVATHY | KARNATAKA | 891 |
KALINADI | KARNATAKA | 810 |
SRISAILAM | ANDHRA PRADESH | 770 |
Installed Capacity
REGION | HYDRO | THERMAL | WIND | NUCLEAR | TOTAL |
NORTH | 8331.57 | 17806.99 | 4.25 | 1320 | 27462.81 |
WEST | 4307.13 | 25653.98 | 346.59 | 760 | 31067.7 |
SOUTH | 9369.64 | 14116.78 | 917.53 | 780 | 25183.95 |
EAST | 2453.51 | 13614.58 | 1.10 | 0 | 16069.19 |
N.EAST | 679.93 | 1122.32 | 0.16 | 0 | 1802.41 |
INDIA | 25141.78 | 72358.67 | 1269.63 | 2860 | 101630.08 |
Region wise contribution of Hydropower
REGION | PERCENTAGE |
NORTH | 30.34 |
WEST | 13.86 |
SOUTH | 37.2 |
EAST | 15.27 |
NORTH-EAST | 37.72 |
INDIA | 24.74 |
Annual gross generation (GWh)
YEAR | GROSS GENERATION |
85/86 | 51021 |
90/91 | 71641 |
91/92 | 72757 |
92/93 | 69869 |
93/94 | 70643 |
94/95 | 82712 |
95/96 | 72579 |
96/97 | 68901 |
97/98 | 74582 |
98/99 | 82690 |
99/2000 | 80533 |
00/01 | 74346 |
Potential of Small Hydropower
Small Hydro in India
STATE | TOTAL CAPACITY (MW) |
ARUNACHAL PRADESH | 1059.03 |
HIMACHAL PRADESH | 1624.78 |
UTTAR PRADESH & UTTARANCHAL | 1472.93 |
JAMMU & KASHMIR | 1207.27 |
KARNATAKA | 652.51 |
MAHARASHTRA | 599.47 |
Sites (up to 3 MW) identified by UNDP
STATE | TOTAL SITES | CAPACITY |
NORTH | 562 | 370 |
EAST | 164 | 175 |
NORTH EAST | 640 | 465 |
TOTAL | 1366 | 1010 |
Small Hydro in other countries
TECHNOLOGY
Technology
Hydropower
Technology
Impoundment
Diversion
Pumped
Storage
Impoundment facility
Dam Types
Arch Dams
Concrete Gravity Dams
Buttress Dams
Embankment Dams
Dams Construction
Diversion Facility
Pumped Storage
Pumped Storage
The Raccoon Mountain project
Sizes of Hydropower Plants
Large Scale Hydropower plant
Small Scale Hydropower Plant
Micro Hydropower Plant
Micro Hydropower Systems
Generating Technologies
Kaplan Turbine
Impulse Turbines
Pelton Wheels
Pelton Wheels (continued…)
Cross Flow Turbines
Cross Flow Turbines (continued…)
Reaction Turbines
Propeller Hydropower Turbine
Bulb Turbine
Others…
Kaplan Turbine
Francis Turbines
Francis Turbines (continued…)
Kinetic Energy Turbines
Hydroelectric Power Plants in India
Baspa II Binwa
Continued …
Gaj
Nathpa Jakri
Continued…
Rangit
Sardar Sarovar
ENVIRONMENTAL IMPACT
Benefits…
• No operational greenhouse gas emissions
• Savings (kg of CO2 per MWh of electricity):
– Coal 1000 kg
– Oil 800 kg
– Gas 400 kg
• No SO2 or NOX
– flood control, irrigation, transportation, fisheries and
– tourism.
Disadvantages
Loss of land
HYDROPLANT | COUNTRY | POPULATION DISPLACED |
Danjiangkou | China | 383000 |
Aswan | Egypt | 120000 |
Volta | Ghana | 78000 |
Narmada Sardar Sarovar | India | 70000 |
Three Gorges | China | 2000000 |
Interference with Sediment transport
RIVER | Kg/m3 |
Yellow River | 37.6 |
Colorado | 16.6 |
Amur | 2.3 |
Nile | 1.6 |
Effects
Climatic and Seismic effects
Some major/minor induced earthquakes
DAM NAME | COUNTRY | HEIGHT (m) | VOLUME OF RESERVOIR (m3) | MAGNITUDE |
KOYNA | INDIA | 103 | 2780 | 6.5 |
KREMASTA | GREECE | 165 | 4650 | 6.3 |
HSINFENGKIANG | CHINA | 105 | 10500 | 6.1 |
BENMORE | NEW ZEALAND | 118 | 2100 | 5.0 |
MONTEYNARD | FRANCE | 155 | 240 | 4.9 |
Eutrophication
Other problems
Methods to alleviate the negative impact
Case Study- Volta Lake, Ghana
Favorable impact
Negative Impact
Technological advancements
Continued…
ECONOMICS OF HYDRO POWER
Global HP Economics
Local HP Economics
Construction Costs
– Varies 25 to 80%
Production Costs
– No fuel costs
– Low O&M cost
– Long lifetime
Cost and Revenue of HP
Comparison with CCGT
Parameters
Payback
Effect of discounting payback
Effect of discounting payback: CCGT
Discounting and NPV
– Hydro’s high capital cost at near full value
– Its additional revenue far in future less
valuable
– CCGT has higher NPV
Unit cost
– Cost per kWh produced
– Discount costs and production
– 2 to 7 p/kWh typical range for HP
– 1.5 to 2.5 p/kWh for CCGT
Conclusion
Small HP costs
Small HP costs
-these two depend on maximum power output�
Typical costs of 100KW plant
| Low head | High head |
| £1000s | £1000s |
|
|
|
Machinery | 30 - 90 | 15 - 60 |
Civil works | 10 - 40 | 20 - 40 |
Electrical works | 10 - 20 | 10 - 20 |
External (no grid connection) | 8 - 15 | 8 - 15 |
| ________________ | ________________ |
Total: | 58 - 165 | 53 - 135 |
Sardar Sarovar Dam
Environmental Protection measures
Rehabilitation & Resettlement
The Three Gorges Project
Some Facts….
Environmental and Other Concerns