PERSIAPAN PELAKSANAAN PEMBANGUNAN SPPG
21 September 2025
SKB MENTERI PU – BGN – MENDAGRI�LOKASI PEMBANGUNAN SPPG
REKAP LOKASI SPPG
TAHAPAN PELAKSANAAN
II.1 Linimasa Pembangunan Satuan Pelayanan Pemenuhan Gizi (Rencana Awal)
NO | URAIAN KEGIATAN | SEPTEMBER | OKTOBER | NOVEMBER | DESEMBER | ||||||||||||
4 | 5 | 1 | 2 | 3 | 4 | 5 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 5 | ||
1 | FINALISASI LOKASI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pemeriksaan ulang daftar lokasi SPPG bersama Satker provinsi |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Identifikasi lokasi yang akan diganti |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Rapat kesepakatan dan tindak lanjut lokasi bermasalah |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2 | KESEPAKATAN LINGKUP PEKERJAAN PU DAN BGN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Rapat koordinasi |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Penyusunan berita acara |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3 | FINALISASI PROTOTIPE SPPG 10x15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pembahasan draft prototipe SPPG 10x15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Finalisasi prototipe SPPG 10x15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Penyusunan Konsep SE Dirjen Prasarana Strategis |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pengesahan SE Dirjen Prasarana Strategis |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4 | FINALISASI DED DAN RAB DOKUMEN LELANG |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pendataan kesiapan Satker Prov untuk gambar situasi SPPG |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Survey dan identifikasi situasi dan siteplan per lokasi oleh konsultan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Finalisasi dokumen gambar lelang |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5 | PROSES REVISI ANGGARAN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
a | Proses Pemenuhan Data Dukung Revisi Anggaran |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Surat usulan revisi |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - KAK dan RAB |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Justifikasi Teknis |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Kronologis |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Surat Minat, Kesiapan Menerima Hibah, Menganggarkan OM |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Dokumen SAKTI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b | Penelaahan oleh Direktorat Kepatuhan Intern DJPS |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
c | Penelahaan oleh APIP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
d | Surat Permohonan Revisi Anggaran dari Dirjen PS ke Kemenkeu |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
e | Penelahaan oleh DJA KEMENKEU |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
f | Surat Pengesahan Revisi Anggaran (SPRA) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NO | URAIAN KEGIATAN | SEPTEMBER | OKTOBER | NOVEMBER | DESEMBER | ||||||||||||
4 | 5 | 1 | 2 | 3 | 4 | 5 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 5 | ||
6 | PERSIAPAN PENGADAAN BARANG DAN JASA |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
a | Mapping dan justifikasi penyedia jasa |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b | Penetapan Program Prioritas Pemerintah & Persetujuan PL oleh Mensesneg |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
c | Koordinasi dengan Ditjen Bina Konstruksi untuk Proses PL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
d | Proses penyiapan PL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Penyiapan dokumen pengadaan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Pembahasan PUH Direktorat |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Pembahasan PUH Pusat |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Penginputan SIPASTI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
e | Proses PL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7 | PROSES KONSTRUKSI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| SPPBJ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Rapat Persiapan Kontrak |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Penerbitan Jaminan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Kontrak dan SPMK |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| PCM bersama Satker Prov terkait, Tim BGN dan Konsultan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| MC-0 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pelaksanaan konstruksi & PHO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Serah terima operasional ke BGN |
|
|
|
|
| | |
|
|
|
|
|
|
|
|
|
II.1 Linimasa Pembangunan Satuan Pelayanan Pemenuhan Gizi (Realisasi)
NO | URAIAN KEGIATAN | SEPTEMBER | OKTOBER | NOVEMBER | DESEMBER | ||||||||||||
4 | 5 | 1 | 2 | 3 | 4 | 5 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 5 | ||
1 | FINALISASI LOKASI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pemeriksaan ulang daftar lokasi SPPG bersama Satker provinsi |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Identifikasi lokasi yang akan diganti |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Rapat kesepakatan dan tindak lanjut lokasi bermasalah |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2 | KESEPAKATAN LINGKUP PEKERJAAN PU DAN BGN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Rapat koordinasi |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Penyusunan berita acara |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3 | FINALISASI PROTOTIPE SPPG 10x15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pembahasan draft prototipe SPPG 10x15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Finalisasi prototipe SPPG 10x15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Penyusunan Konsep SE Dirjen Prasarana Strategis |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pengesahan SE Dirjen Prasarana Strategis |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4 | FINALISASI DED DAN RAB DOKUMEN LELANG |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pendataan kesiapan Satker Prov untuk gambar situasi SPPG |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Survey dan identifikasi situasi dan siteplan per lokasi oleh konsultan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Finalisasi dokumen gambar lelang (sampai dengan 6 d) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5 | PROSES REVISI ANGGARAN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
a | Proses Pemenuhan Data Dukung Revisi Anggaran |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Surat usulan revisi |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - KAK dan RAB |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Justifikasi Teknis |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Kronologis |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - SPTJM kelengkapan dokumen revisi |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Dokumen SAKTI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b | Penelaahan oleh Direktorat Kepatuhan Intern DJPS |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
c | Penelahaan oleh APIP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
d | Surat Permohonan Revisi Anggaran dari Dirjen PS ke Kemenkeu |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
e | Penelahaan oleh DJA KEMENKEU |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
f | Surat Pengesahan Revisi Anggaran (SPRA) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NO | URAIAN KEGIATAN | SEPTEMBER | OKTOBER | NOVEMBER | DESEMBER | ||||||||||||
4 | 5 | 1 | 2 | 3 | 4 | 5 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 5 | ||
6 | PERSIAPAN PENGADAAN BARANG DAN JASA |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
a | Mapping dan justifikasi penyedia jasa |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b | Penetapan Program Prioritas Pemerintah & Persetujuan PL oleh Mensesneg |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
c | Koordinasi dengan Ditjen Bina Konstruksi untuk Proses PL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
d | Proses penyiapan PL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Penyiapan dokumen pengadaan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Pembahasan PUH Direktorat |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Pembahasan PUH Pusat |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| - Penginputan SIPASTI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
e | Proses PL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7 | PROSES KONSTRUKSI |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| SPPBJ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Rapat Persiapan Kontrak |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Penerbitan Jaminan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Kontrak dan SPMK |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| PCM bersama Satker Prov terkait, Tim BGN dan Konsultan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| MC-0 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pelaksanaan konstruksi & PHO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Serah terima operasional ke BGN |
|
|
|
|
| | |
|
|
|
|
|
|
|
|
|
PENYUSUNAN DED & RAB TIAP LOKASI