Public
Public
Ontario Vehicle Production, 2010-2019
Public
Toyota & Honda % of Production, 2010-2019
Public
Ontario Vehicle Production, 2010-2024
Public
Toyota & Honda % of Production, 2010-2024
Public
The Way Forward (2020) – 3 Options
Public
‘There’s more work to do. But it’s the automotive industry. There’s always more work to do. And that’s a lot better than having no work to do.’
Public
‘There’s more work to do. But it’s the automotive industry. There’s always more work to do. And that’s a lot better than having no work to do.’
- Brendan
Public
Battery Plants – What to Expect?
Battery cell manufacturing ≠ vehicle assembly
New people from outside of Ontario, initially
Workforce strategy & hiring in stages
Engagement colleges (and universities) when time is right
Battery production in step with several assembly plants
Public
Policy Environment
Different companies have different electrification strategies
Different companies have different time horizons for ROI
Canada does incentives by contract, not legislation
Major employers are already making contributions to liveable communities, need all-hands approach & wrap-around supports
Public
Public
PowerCo Canada�Overview�
October 25, 2024
Public
Department | Presentation title | CSD-class
14
01.01.2024
Brent Hinson �
Chief Finance Officer – CFO
PowerCo Canada
Motivation to join PowerCo
Prior experience
Skills and knowledge
Personal interests
Excited about starting a brand new factory with new technologies and the future for the VW Group.
Public
Relationship with Volkswagen
Who we are
15
Public
Sustainability forms the backbone of the company
Product and technology
Industrialization and equipment
Vertical �integration
Capital�market
Sustainability
Public
St. Thomas
First overseas Gigafactory and PowerCo’s biggest production facility
17
08.27.2024
Size: ~ 150ha
Capacity: up to 90+ GWh/a
SOP: 01/2027
Valencia
2027
40+ GWh/a
~200ha
Salzgitter
2025
40 GWh/a
~ 40ha
Headquarter
Public
PowerCo Canada Inc. – 2024 Project Highlights
Site levelling and PowerCo Canada team growth on track
18
08.27.2024
Celebration phase 1 site levelling complete
PowerCo Supplier Days in Toronto
Phase 3 site levelling ongoing
Drilling event & phase 2 site levelling complete
CW 15 ‘24
CW 26 ‘24
CW 5 ‘24
CW 50 ‘23
CW 32 ‘24
CW 32 ‘24
Opening of 2nd floor of Temp Office
Visit of Mr. Schmall and Sebastian Wolf
Public
Gigafactory St. Thomas
1
2
3
5
4
6
7
8
9
Process flow
Inbound |
Cell Production |
Formation & Ageing |
Outbound |
Utility Center |
Employee parking |
Central building |
Guard house |
Shunting yard |
Gigafactory St. Thomas
1
2
3
4
5
6
7
8
9
Public
Our Product - the Unified Cell
Low complexity, high standardization
20
Energy Storage Systems
Busses
Trucks
Passenger Cars
LFP
NMC
ASSB
NMC-blends
Si-Anode
Na-Ion
Public
Thank you!
Public