Tangga Core Depan (Tangga 1)
Sudah Ter-Cor
7/01/25
3 m3
Adhimix
17/01/25
5 m3
PBI
7/2/25
4 m3
Adhimix
Tangga Core Depan (Tangga 1)
Sudah Ter-Cor
5/3/25
5 m3
MERAK
10/4/25
4 m3
MERAK
11/05/25
4,5 m3
MERAK
Tangga Core Depan (Tangga 1)
Sudah Ter-Cor
21/05/25
4,5 m3
MERAK
11/06/25
4,5 m3
MERAK
17/06/25
4,5 m3
MERAK
Tangga Core Depan (Tangga 1)
Sudah Ter-Cor
21/06/25
4,5 m3
MERAK
26/06/25
4,5 m3
MERAK
01/07/25
4,5 m3
MERAK
25/07/25
Tangga Core Depan (Tangga 1)
Sudah Ter-Cor
02/07/25
4,5 m3
MERAK
09/07/25
4,5 m3
MERAK
27/07/25
4,5 m3
MERAK
Tangga Core Depan (Tangga 1)
Sudah Ter-Cor
10/07/25
4,5 m3
MERAK
10/07/25
4,5 m3
MERAK
Tangga Core Depan (Tangga 1)
Sudah Ter-Cor
13/07/25
4,5 m3
MERAK
Tangga Core Depan (Tangga 1)
Sudah Ter-Cor
16/07/25
5 m3
MERAK
28/07/25
5 m3
MERAK
Tangga Core Depan (Tangga 1)
Sudah Ter-Cor
30/07/25
5 m3
MERAK
03/08/25
5 m3
MERAK
Tangga Core Depan (Tangga 1)
Sudah Ter-Cor
05/08/25
5 m3
MERAK
20/08/25
4,5 m3
MERAK
26/08/25
3 m3
MERAK
Tangga Utara (tangga 2)
Sudah Ter-Cor
11/02/25
5 m3
Adhimix
19/02/25
8 m3
Adhimix
2/3/25
5 m3
Merak
Tangga Utara (tangga 2)
Sudah Ter-Cor
10/4/25
4,5 m3
Merak
30/4/25
5 m3
Merak
15/5/25
5,5 m3
Merak
21/5/25
5 m3
Merak
Tangga Utara (tangga 2)
Sudah Ter-Cor
04/6/25
4,5 m3
Merak
15/6/25
4,5 m3
Merak
Tangga Utara (tangga 2)
Sudah Ter-Cor
22/06/25
4,5 m3
Merak
13/07/25
4,5 m3
Merak
25/07/25
4,5 m3
Merak
Tangga Utara (tangga 2)
Sudah Ter-Cor
11/08/25
m3
Merak
Tangga Core Belakang (Tangga 3)
21/12/24
6m3
Merak
30/7/24
4,5 m3
Merak
8/11/24
5 m3
Merak
Sudah Ter-cor
2/2/25
4,5 m3
Adhimix
9/1/25
3 m3
PBI
Tangga Core Belakang (Tangga 3)
Sudah Ter-cor
11/3/25
m3
PBI
Tangga Core Belakang (Tangga 3)
Sudah Ter-cor
13/4/25
4 m3
Merak
30/4/25
4,5 m3
Merak
13/05/25
4,5 m3
Adhimix
13/4/25
4,5 m3
MERAK
19/05/25
5 m3
MERAK
20/05/25
5 m3
MERAK
Tangga Core Belakang (Tangga 3)
Sudah Ter-cor
27/4/25
4,5 M3
Adhimix
16/05/25
5,5 M3
Adhimix
24/05/25
4,5 M3
Merak
Tangga Core Belakang (Tangga 3)
Sudah Ter-cor
25/5/25
4,5 M3
Merak
29/5/25
4,5 M3
Merak
01/6/25
4,5 M3
Merak
Tangga Core Belakang (Tangga 3)
Sudah Ter-cor
Tangga Core Belakang (Tangga 3)
Sudah Ter-cor
17/06/25
4,5 M3
Merak
25/06/25
4,5 M3
Merak
27/06/25
4,5 M3
Merak
Tangga Core Belakang (Tangga 3)
Sudah Ter-cor
09/07/25
4,5 M3
Merak
23/07/25
4,5 M3
Merak
8/11/24
15/11/24
PILECAP B3
19/11/24
11/12/24
19/11/24
28/05/25
45m3 (Merak)
21/05/25
(Merak)
14/06/25
42,5m3 (Merak)
BASEMENT 3
5/8/24
ADHIMIX 448 m3
11/7/24
ADHIMIX
29/11/24
Merak
84,5m3
21/12/24
Merak
58,5m3
27/01/25
MERAK 98 m3
21/05/25
MERAK
m3
28/05/25
MERAK
45m3
03/06/25
MERAK
2 m3
04/06/25
MERAK
70 m3
11/06/25
MERAK
6 m3
14/06/25
MERAK
42,5 m3
26/06/25
MERAK
3m3
BASEMENT 3
13/06/25
MERAK
33 m3
13/06/25
MERAK
8 m3
13/06/25
MERAK
2 m3
19/06/25
MERAK
23 m3
22/06/25
MERAK
16 m3
25/06/25
MERAK
35 m3
26/06/25
MERAK
21 m3
28/06/25
MERAK
1 m3
12/3/25
21m3
Merak
Lantai Mezz STP Slab dan Balok (FFL -6.200 & FFL -6.400)
13/3/25
Merak
16/4/25
52 m3
Merak
Lantai Mezz STP Dinding Dan Kolom (FFL -6.200 & FFL -6.400)
12/3/25
12 m3
Merak
9/3/2025
PBI dan Merak
1m3
BASEMENT 2
11/06/24
ADHIMIX 226 m3
03/05/24
ADHIMIX
266 m3
26/05/24
ADHIMIX
27/05/24
ADHIMIX 345 m3
14/06/24
ADHIMIX 331 m3
15/7/24
ADHIMIX
3/7/24
ADHIMIX
8/09/24
ADHIMIX
7/9/24
ADHIMIX
18/9/24
ADHIMIX
21/06/2
4
28/06/24
ADHIMIX
25/06/24
ADHIMIX
18/07/24
ADHIMIX
9/4/25
MERAK
10 m3
17/04/25
Merak
52 m3
23/04/25
Merak
5 m3
02/05/25
Adhimix
5 m3
07/05/25
MERAK
7 m3
13/07/25
Merak
135 m3
BASEMENT 2
9/3/2025
PBI dan Merak
1m3
DINDING PARAPET BASEMENT 2 - B1
LS 1
LS 2
LS 3
LANTAI BASEMENT 2
SEPARATOR BEAM
SEPARATOR BEAM
BAJA OPENINGAN
DINDING LIFT
BASEMENT 1
29/7/24
PBI 154 m3
9/8/24
ADHIMIX 105 m3
15/9/24
PBI
68 m3
10/9/24
ADHIMIX 110 m3
17/9/24
ADHIMIX
126 m3
13/9/24
ADHIMIX 28 m3
24/9/24
PBI 193 m3
16/8/24
ADHIMIX 119 m3
30/8/24
PBI 28 m3
7/9/24
PBI
2/10/24
ADHIMIX
160,5 m3
8/10/24
ADHIMIX 84 m3
12/9/24
ADHIMIX 28 m3
24/10/24
ADHIMIX
18/4/25
Merak 6,5 m3
23/04/25
MERAK
95 m3
26/4/25
Merak 6 m3
03/05/25
ADHIMIX 49 m3
10/05/25
Adhimix 18 m3
11/05/25
Merak
4 m3
12/05/25
Adhimix
8 m3
13/05/25
Adhimix
7 m3
15/05/25
Merak
7 m3
16/05/25
Adhimix
5 m3
22/05/25
Merak
7 m3
04/6/25
Merak 4 m3
11/6/25
Merak 5 m3
25/06/25
Merak
3 m3
28/6/25
Merak 11 m3
23/07/25
Merak
10 m3
24/07/25
Merak
7 m3
25/07/25
Merak
6,5 m3
28/07/25
Merak
35 m3
BASEMENT 1
|
|
|
|
7/9/24
8/8/24
ADHIMIX
7 m3
11/8/24
ADHIMIX 17 m3
12/8/24
ADHIMIX 14 m3
13/8/24
ADHIMIX 18 m3 (
19/8/24
ADHIMIX 28 m3
21/8/24
ADHIMIX
28 m3
20/9/24
14/8/24
15/9/24
13/9/24
19/9/24
21/9/24
4/9/24
ADHIMIX 13 m3
7/10/24
ADHIMIX
7 m3
7/10/24
ADHIMIX 14 m3 (
9/10/24
MERAK 11,5 m3
12/10/24
ADHIMIX 14 m3
5/11/24
27/04/25
ADHIMIX 3 m3
27/04/25
ADHIMIX 3 m3
11/05/25
MERAK 1 m3
04/07/25
MERAK 1 m3
29/05/25
Merak
1 m3
25/06/25
Merak
1 m3
DINDING PARAPET LT BASEMENT 1
04/07/25
Merak Vol = 5 m3
06/07/25
Merak Vol = 5 m3
10/07/25
Merak Vol = 6 m3
15/07/25
Merak Vol = 6,5 m3
LS 1
LS 2
LS 3
LANTAI BASEMENT 1
SEPARATOR BEAM
SEPARATOR BEAM
BAJA OPENINGAN
DINDING LIFT
LANTAI 1
21/9/24
ADHIMIX 166 m3
15/9/24
PBI 49 m3
27/8/24
ADHIMIX 133 m3
3/10/24
ADHIMIX 98 m3
1/9/24
PBI 109 m3
26/9/24
Adhimix
189 m3
30/9/24
ADHIMIX
147 m3
17/9/24
PBI 154 m3
15/10/24
ADHIMIX 238 m3
13/11/24
Merak
20 m3
15/11/24
ADHIMIX
2/12/24
Merak
65 m3
8/12/24
Adhimix
126m3
21/12/24
Merak
6m3
27/12/24
Adhimix
126m3
2/3/25
Merak
60 m3
3/3/25
Merak
28 m3
26/3/25
Adhimix
35 m3
20/04/25
Merak
45 m3
21/04/25
Merak
35 m3
22/04/25
Merak
21 m3
26/04/25
4 m3
01/05/25
Merak
30 m3
12/05/25
Adhimix
50m3
03/06/25
Merak
50 m3
26/06/25
Merak
55 m3
08/08/25
Merak
75m3
11/08/25
Merak
63 m3
17/08/25
Merak
36m3
LANTAI 1
30/8/24
ADHIMIX 35 m3
4/9/24
19/9/24
21/9/24
ADHIMIX 29 m3
27/9/24
3/9/24
|
|
|
|
9/9/24
16/8/24
29/9/24
1/10/24
2/10/24
ADHIMIX 38,5 m3
3/10/24
ADHIMIX 21 m3
4/10/24
ADHIMIX
9 m3
6/10/24
ADHIMIX
16/10/24
ADHIMIX
25/10/24
ADHIMIX
19/11/24
ADHIMIX 7 m3
15/11/24
ADHIMIX 4 m3
17/11/24
ADHIMIX 17 m3
21/11/24
ADHIMIX 40 m3
4/12/24
ADHIMIX 7 m3
7/12/24
ADHIMIX 14 m3
4/3/25
MERAK 11 m3
DINDING PARAPET LANTAI 1
29/5/25
Merak Vol = 1 m3
18/06/25
Merak Vol = 5 m3
19/06/25
Merak Vol = 4,5 m3
19/06/25
Merak Vol = 5 m3
06/07/25
Merak Vol = 6,5 m3
07/07/25
Merak Vol = 5 m3
LS 1
LS 2
LS 3
LANTAI 1
SEPARATOR BEAM
29/07/25
Merak
2 m3
SEPARATOR BEAM
BAJA OPENINGAN
DINDING LIFT
DINDING PARAPET LT. MEZZANINE
05/07/25
Merak Vol = m3
12/07/25
Merak Vol = 5 m3
14/07/25
Merak Vol = 11,5 m3
LS 1
LS 2
LS 3
LANTAI MEZANINE
SEPARATOR BEAM
16/08/25
Merak
3 m3
SEPARATOR BEAM
BAJA OPENINGAN
DINDING LIFT
LANTAI 2
4/10/24
ADHIMIX 39 m3
7/10/24
ADHIMIX 171 m3
11/10/24
MERAK 149 m3
17/10/24
ADHIMIX
140 m3
22/10/24
ADHIMIX
9/10/24
MERAK
19/11/24
ADHIMIX
Vol = 56 m3
17/12/24
PBI
73m3
13/3/25
MERAK
52m3
25/1/25
ADHIMIX
91M3
2/2/25
ADHIMIX
85M3
6/2/25
ADHIMIX
82 M3
16/2/2025
Adhimix
7m3
14/3/2025
Merak
90m3
15/4/25
MERAK
4 m3
19/05/25
Merak
5 m3
26/06/25
Merak
8m3
LANTAI 2
8/10/24
ADHIMIX 31 m3
7/10/24
ADHIMIX 14 m3
9/10/24
11/10/24
ADHIMIX 35 m3
12/10/24
ADHIMIX 24 m3 (
13/10/24
MERAK 26 m3
17/10/24
ADHIMIX
49 m3
18/10/24
20/10/24
ADHIMIX
23/10/24
ADHIMIX
35 m3 (+kolom lt. 3)
25/10/24
ADHIMIX 15 m3
30/10/24
21/11/2024
Adhimix
40 m3
7/11/2024
Merak
19,5 m3
19/12/2024
30/01/2025
9m3
14/3/25
MERAK 5,5 m3
DINDING PARAPET LANTAI 2
10/07/25
Merak Vol = 5 m3
11/07/25
Merak Vol = 5 m3
24/07/25
Merak Vol = 2 m3
22/07/25
Merak Vol = 6 m3
LS 1
LS 2
LS 3
LANTAI 2
SEPARATOR BEAM
23/05/25
Merak
2 m3
LANTAI 3
19/10/24
MERAK
84,5 m3
16/10/24
ADHIMIX 119 m3
20/10/24
ADHIMIX 224 m3
25/10/24
ADHIMIX 112 m3
4/11/24
ADHIMIX 189 m3
17/11/2024
19,5 m3
7/12/24
Adhimix
42m3
05/02/25
Adhimix
70 m3
13/02/25
Adhimix
84 m3
6/2/25
82m3
27/1/25
MERAK
13M3
21/2/25
Adhimix
115m3
26/2/25
Merak
6,5 m3
25/04/25
MERAK
110 m3
04/05/25
Adhimix
7 m3
23/05/25
Merak
8 m3
10/07/25
MERAK
4 m3
LANTAI 3
17/10/24
ADHIMIX 49 m3
19/10/24
22/10/24
42 m3
23/10/24
ADHIMIX 35 m3
24/10/24
ADHIMIX 7 m3 (
25/10/24
ADHIMIX
4 m3
27/10/24
ADHIMIX
19 m3
28/10/24
6/11/24
ADHIMIX
5/11/24
23/10/24
09/11/24
MERAK 19 m3
07/11/24
MERAK 13 m3
10/11/24
MERAK 9 m3
21/11/24
Adhimix 3 m3
10/12/24
Merak 19,5 m3
27/01/25
Merak 16,5 m3
7/2/25
Adhimix 3,5 m3
22/2/25
Merak 12 m3
14/4/25
Merak 2 m3
18/4/25
Merak 2 m3
18/05/25
Merak 3,5 m3
19/05/25
Merak 3,5 m3
DINDING PARAPET LANTAI 3
11/07/25
Merak Vol = 5 m3
12/07/25
Merak Vol = 5 m3
29/07/25
Merak Vol = 6 m3
19/05/25
Merak
7 m3
LANTAI 3
SEPARATOR BEAM
LS 1
LS 2
LS 3
LANTAI 4
29/10/24
MERAK 117 m3
1/10/24
MERAK
2/11/24
ADHIMIX 94 m3
6/11/24
ADHIMIX
112 m3
16/11/24
ADHIMIX
Vol : 140 m3
12/12/24
MERAK
32,5 m3
23/01/25
ADHIMIX 49 m3
16/2/25
Adhimix
60m3
1/3/25
Merak 85 m3
3/3/25
Merak 135 m3
17/3/25
Merak 85 m3
10/3/2025
26/04/25
ADHIMIX 45 m3
27/10/24
MERAK 78 m3
4/3/25
MERAK 26 m3
08/05/25
MERAK 10 m3
10/05/25
Adhimix
7,2 m³
31/05/25
MERAK
5 m3
27/06/25
Merak
2 m3
14/08/25
Merak
7m3
LANTAI 4
28/10/24
30/10/24
1/11/24
ADHIMIX 21 m3
3/11/24
ADHIMIX
2/11/24
ADHIMIX
5/11/24
ADHIMIX
4/11/24
ADHIMIX
6/11/24
ADHIMIX 21 m3
7/11/24
18/11/24
Merak Vol : 25.5 m3
19/11/24
Adhimix Vol : 21 m3
21/11/24
Adhimix Vol : 40 m3
18/2/25
Adhimix Vol : 12 m3
5/3/25
Merak Vol : 7 m3
7/3/25
Merak Vol : 3 m3
26/4/25
Merak Vol : 12 m3
3/4/25
Merak Vol : m3
DINDING PARAPET LANTAI 4
14/07/25
Merak Vol = 6,5 m3
08/08/25
Merak Vol = m3
LANTAI 4
SEPARATOR BEAM
LS 1
LS 2
LS 3
24/05/25
Merak
4 m3
LANTAI 5
7/11/24
ADHIMIX 94 m3
10/11/2024
Volume : 96 m3
(Merak)
SLAB LANTAI 5
13/11/2024
Volume : 180 m3
(Merak)
22/11/2024
Volume : 170 m3
(Adhimix)
25/11/24
225m3
24/2/25
51,5
Merak
29/1/25
Volume : 21 m3
(Adhimix)
26/2/25
60 m3
(Merak)
12/3/25
Volume : 78 m3
Merak
23/2/25
119 m3
(Adhimix)
14/3/25
52 m3
Merak
19/3/2025
15/3/25
80 m3
(Merak)
04/05/25
90 m3
(Merak)
10/4/25
20 m3
(Merak)
11/05/25
4 m3
(Merak)
Chiller
Chiller
16/05/25
7,2 m3
(Adhimix)
23/05/25
16 m3
(Merak)
11/06/25
4 m3
(Merak)
LANTAI 5
DINDING PARAPET LANTAI 5
22/11/2024
Volume : 170 m3
(Adhimix)
13/4/25
Merak Vol = 3 m3
12/4/25
Merak Vol = 7 m3
DINDING PARAPET LANTAI 5
25/4/25
Adhimix Vol = 6 m3
25/4/25
Adhimix Vol = 7 m3
24/5/25
Merak Vol = 5 m3
25/5/25
Merak Vol = 5 m3
27/5/25
Merak Vol = 5 m3
28/5/25
Merak Vol = 3 m3
30/5/25
Merak Vol = 3 m3
31/5/25
Merak Vol = 3 m3
26/06/25
Merak Vol = 2 m3
01/07/25
Merak Vol = 2 m3
04/07/25
Merak Vol = 4 m3
09/07/25
Merak Vol = 2 m3
24/07/25
Merak Vol = m3
01/08/25
Merak Vol = 3 m3
08/08/25
Merak Vol = 6 m3
KOLOM LANTAI 5
9/11/24
Merak Vol = 20 m3
10/11/24
Merak Vol = 7.5 m3
11/11/24
Merak Vol = 24 m3
12/11/24
Merak Vol = 4 m3
15/11/24
Adhimix Vol = 28 m3
16/11/24
Adhimix Vol = 49 m3
17/11/24
Merak Vol = 49 m3
21/11/24
Adhimix Vol = 35 m3
30/11/24
Adhimix Vol = 26 m3
1/12/24
Merak Vol = 19 m3
2/12/24
Merak Vol = 13 m3
23/11/24
Merak Vol = 18 m3
2/12/24
Merak Vol = 13 m3
25/2/25
Merak Vol = 11 m3
27/2/25
Merak Vol = 9 m3
9/4/25
Merak Vol = 17,5 m3
11/4/25
Merak Vol = 4 m3
18/4/25
Merak Vol = 11 m3
20/4/25
Merak Vol = 12 m3
06/04/25
Adhimix Vol = 3 m3
LS 1
LS 2
LS 3
LANTAI 5
SEPARATOR BEAM
24/05/25
Merak
1 m3
27/07/25
Merak
1 m3
SLAB LANTAI 6
25/11/24
Merak
160m3
30/11/24
Merak
149,5 m3
3/12/24
Merak
21,4m3
4/12/24
Adhimix
147
4/12/24
Adhimix
147m3
6/12/24
160m3
26/2/25
20 m3
(Merak)
5/3/25
78 m3
(Merak)
12/3/25
49 m3
(Merak)
9/4/25
35 m3
(Merak)
19/3/25
78 m3
(Merak)
23/4/25
80 m3
(Merak)
16/4/25
117 m3
(Adhimix)
10/05/25
45 m3
(Adhimix)
31/05/25
9 m3
(Merak)
11/06/25
5,5 m3
(Merak)
21/06/25
1,5 m3
(Merak)
12/4/25
Merak Vol = 7 m3
DINDING PARAPET LANTAI 6
15/4/25
Merak Vol = 3 m3
15/4/25
Merak Vol = 6,5 m3
07/05/25
Merak Vol = 4 m3
17/05/25
Merak Vol = 8 m3
04/06/25
Merak Vol = 3 m3
13/06/25
Merak Vol = 3 m3
19/06/25
Merak Vol = 4,5 m3
22/06/25
Merak Vol = 2,5 m3
26/06/25
Merak Vol = 2 m3
27/06/25
Merak Vol = m3
12/07/25
Merak Vol = 3 m3
21/07/25
Merak Vol = 3 m3
31/07/25
Merak Vol = 4 m3
11/08/25
Merak Vol = 6,5 m3
/08/25
Merak Vol = 6,5 m3
18/09/25
Merak Vol = 3 m3
30/11/24
Merak Vol = 6,5 m3
Kolom LANTAI 6
1/12/24
Merak Vol = 7 m3
2/12/24
Merak
8/12/24
Adhimix
28m3
7/12/24
Adhimix
18m3
9/12/24
Adhimix
28m3
10/12/24
Merak
6,5
27/2/25
Merak
3 m3
7/3/25
Merak
m3
14/3/25
Merak
7 m3
10/4/25
Merak
3,5 m3
24/4/25
Merak
11 m3
04/05/25
Merak
17,5 m3
08/05/25
Merak
11 m3
10/05/25
Adhimix
17 m3
12/05/25
Adhimix
5 m3
17/05/25
Merak
3 m3
17/05/25
Merak
3 m3
LANTAI 6
SEPARATOR BEAM
LS 1
LS 2
LS 3
24/05/25
Merak
1,5 m3
27/07/25
Merak
1 m3
10/12/24
Merak
110m3
16/12/24
PBI
189m3
18/12/24
Merak
110,5m3
19/12/24
Adhimix
200m3
SLAB LANTAI 7
10/3/25
PBI/MERAK 21 m3
19/04/25
Merak
119 m3
26/04/25
Merak &
Adhimix
40 m3
16/05/25
Adhimix
90 m3
18/05/25
Merak
50 m3
21/05/25
Adhimix
95 m3
21/06/25
8 m3
(Merak)
22/06/25
8 m3
(Merak)
26/04/25
Merak Vol = 11 m3
DINDING PARAPET LANTAI 7
12/05/25
Adhimix Vol = 15 m3
15/05/25
Merak Vol = 15 m3
17/05/25
Merak Vol = 10 m3
21/05/25
Merak Vol = 4,5 m3
03/06/25
Merak Vol = 3 m3
31/05/25
Merak Vol = 2,5 m3
15/06/25
Merak Vol = 3 m3
04/07/25
Merak Vol = 4 m3
16/07/25
Merak Vol = 5 m3
27/07/25
Merak Vol = 3 m3
29/07/25
Merak Vol = 3 m3
07/08/25
Merak Vol = 4 m3
11/08/25
Merak Vol = 3 m3
19/08/25
Merak Vol = 3 m3
/08/25
Merak Vol = m3
22/08/25
Merak Vol = 3m3
11/12/24
Merak
18,5m3
12/12/24
Merak
13m3
18/12/24
Merak
26m3
KOLOM LANTAI 7
19/12/24
Adhimix
26m3
22/12/24
Adhimix
28m3
23/12/24
Adhimix
28m3
24/12/24
Adhimix
9m3
15/3/25
MERAK
11m3
20/4/25
MERAK
11m3
23/4/25
MERAK
9 m3
28/4/25
MERAK & Adhimix
9 m3
12/05/25
Adhimix
10,5 m3
18/05/25
Merak
10,5 m3
19/05/25
Merak
14 m3
20/05/25
Merak
6 m3
24/05/25
Merak
11 m3
LS 1
LS 2
LS 3
LANTAI 7
SEPARATOR BEAM
26/05/25
Merak
3 m3
27/07/25
Merak
1 m3
SLAB LANTAI 8
3/1/25
Adhimix
178m3
5/1/25
Adhimix
210 m3
30/12/24
Merak
273m3
02/05/25
145 m3
Adhimix
05/05/25
Merak
45 m3
21/05/25
Merak
10 m3
31/05/25
Merak
50 m3
21/06/25
Merak
95 m3
02/07/25
Merak
130 m3
09/07/25
Merak
2 m3
24/05/25
Merak Vol = 8 m3
DINDING PARAPET LANTAI 8
13/06/25
Merak Vol = 5 m3
15/06/25
Merak Vol = 5 m3
18/06/25
Merak Vol = 4 m3
19/06/25
Merak Vol = 4 m3
27/06/25
Merak Vol = m3
27/07/25
Merak Vol = 3,5 m3
29/07/25
Merak Vol = 4 m3
31/07/25
Merak Vol = 6 m3
06/08/25
Merak Vol = 5 m3
11/08/25
Merak Vol = 6 m3
08/25
Merak Vol = 6 m3
08/25
Merak Vol = 6 m3
23/08/25
Merak Vol = 3 m3
KOLOM LANTAI 8
31/12/24
Adhimix
28m3
3/1/25
Adhimix
32m3
4/1/25
Adhimix
28m3
6/1/25
Adhimix
17 m3
7/1/25
Adhimix
23 m3
9/4/25
MERAK
9 m3
1/5/25
MERAK
7,5 m3
04/05/25
MERAK
6 m3
06/05/25
Adhimix
9 m3
08/05/25
Merak
6 m3
26/05/25
Merak
11 m3
02/06/25
Merak
7 m3
26/06/25
Merak
4 m3
LS 1
LS 2
LS 3
LANTAI 8
SEPARATOR BEAM
27/05/25
Merak
1,8 m3
14/06/25
Merak
1 m3
SLAB LANTAI 9
20/1/25
PBI�251m3
23/01/25�ADHIMIX�168m3
29/1/25
MERAK
224 m3
21-04-25
MERAK
52 m3
13-05-25
ADHIMIX
140 m3
15-05-25
MERAK
45 m3
31/05/25
10 m3
(Merak)
20-06-25
MERAK
55,5 m3
15/09/2025
Merak
35 m3
15/08/25
Merak Vol = 4 m3
DINDING PARAPET LANTAI 9
19/08/25
Merak Vol = 10 m3
20/08/25
Merak Vol = m3
21/08/25
Merak Vol = m3
20/01/25
PBI
14m3
22/01/25
PBI
35m3
23/01/25
MERAK
32,5m3
24/01/25
ADHIMIX
12m3
23/01/25
ADHIMIX
18m3
30/01/25
MERAK
25m3
23/04/25
MERAK
8m3
KOLOM LANTAI 9
15/05/25
MERAK
7,5 m3
16/05/25
Adhimix
14 m3
18/05/25
Merak
12 m3
22/06/25
Merak
6 m3
LS 1
LS 2
LS 3
LANTAI 9
SEPARATOR BEAM
04/06/25
Merak
3 m3
14/06/25
Merak
1 m3
03/08/25
Merak
1 m3
4/2/25
MERAK
220 M3
SLAB LANTAI 10
8/2/25
ADHIMIX
182m3
14/2/25
Adhimix
95m3
03/05/25
ADHIMIX 56 m3
28/05/25
MERAK 53 m3
20/06/25
MERAK
140 m3
11/2/25
ADHIMIX
135m3
22/06/25
8 m3
(Merak)
06/07/25
MERAK 55 m3
15/07/25
13 m3
(Merak)
7/2/25
17m3
Adhimix
8/2/25
17m3
Adhimix
10/2/25
23m3
Adhimix
9/2/25
17m3
Adhimix
11/2/25
8m3
Adhimix
12/2/25
15m3
Adhimix
15/2/25
16m3
Adhimix
16/2/25
23,5m3
Adhimix
18/2/25
15m3
Adhimix
KOLOM LANTAI 10
04/05/25
12 m3
Adhimix
29/05/25
10,5 m3
Merak
22/06/25
12 m3
Merak
24/06/25
6,5 m3
Merak
11/07/25
6 m3
Merak
LS 1
LS 2
LS 3
LANTAI 10
SEPARATOR BEAM
14/06/25
Merak
1 m3
11/07/25
Merak
4 m3
07/08/25
Merak
3,5 m3
03/08/25
Merak
1 m3
18/2/25
Adhimix
168m3
19/2/25
Adhimix
135m3
22/2/25
Merak
110
SLAB LANTAI 11
25/2/25
Merak
130m3
27/2/25
Merak
85 m3
12/05/25
Adhimix
50m3
17/06/25
Merak
52m3
27/06/25
3 m3
(Merak)
05/07/25
Merak
130m3
15/07/25
Merak
52m3
23/07/25
13 m3
(Merak)
19/2/25
14m3
Adhimix
21/2/25
16,5m3
Adhimix
23/2/25
26 m3
Merak
24/2/25
3,5 m3
Merak
KOLOM LANTAI 11
1/3/25
13 m3
Merak
3/3/25
21 m3
Merak
4/3/25
30 m3
Merak
11/3/25
3 m3
PBI / MERAK
14/05/25
10,5 m3
MERAK
19/06/25
11 m3
MERAK
11/07/25
10,5 m3
MERAK
13/07/25
16 m3
MERAK
16/07/25
6,5 m3
MERAK
LS 1
LS 2
LS 3
LANTAI 11
SEPARATOR BEAM
10/3/25
PBI
175 m3
16/3/25
Merak
188,5 m3
18/3/25
Merak
m3
22/3/25
Merak
m3
SLAB LANTAI 12
23/3/25
ADHIMIX
26 m3
27/05/25
Merak
50m3
04/07/25
3 m3
(Merak)
06/07/25
Merak
65m3
23/07/25
Merak
125 m3
27/07/25
32 m3
(Merak)
31/07/25
Merak
65m3
12/3/25
21m3
Merak
13/3/25
m3
Merak
14/3/25
3 m3
Merak
18/3/25
m3
Merak
20/3/25
13 m3
Merak
23/3/25
14 m3
Adhimix
24/3/25
24 m3
Adhimix
9/4/25
16 m3
MERAK
SLAB LANTAI 12
28/5/25
11 m3
MERAK
27/07/25
11 m3
MERAK
LS 1
LS 2
LANTAI 12
SEPARATOR BEAM
24/3/25
Adhimix
115 m3
13/4/25
Merak
120 m3
17/4/25
Merak
90 m3
18/4/25
Merak
90 m3
DENAH SLAB LANTAI 13
12/7/25
Merak
55 m3
06/08/25
Merak
98 m3
08/08/25
Merak
9 m3
11/4/25
9m3
Merak
12/4/25
14 m3
Merak
13/4/25
6.5 m3
Merak
14/4/25
6 m3
Merak
15/4/25
12 m3
Merak
18/4/25
4 m3
Merak
20/4/25
23 m3
Merak
20/4/25
16 m3
Merak
20/4/25
1 m3
Merak
21/4/25
32,8 m3
Merak
DENAH KOLOM DAN SW LANTAI 13
14/7/25
6,5 m3
Merak
08/08/25
8 m3
Merak
LS 1
LS 2
LANTAI 13
SEPARATOR BEAM
14/08/25
Merak
3 m3
21/4/25
Merak
135 m3
DENAH SLAB LANTAI 14
24/4/25
Merak
130 m3
28/4/25
Merak & Adhimix
194,5 m3
24/07/25
Merak
52 m3
14/08/25
Merak
4 m3
16/08/25
Merak
98 m3
DENAH KOLOM LANTAI 14
21/4/25
16 m3
Merak
23/4/25
15,5 m3
Merak
24/4/25
17 m3
Adhimix
25/4/25
14 m3
Adhimix
co
29/4/25
15 m3
Adhimix
01/05/25
31 m3
Adhimix
03/05/25
17 m3
Adhimix
co
25/07/25
7,5 m3
Adhimix
19/08/25
10 m3
Merak
LS 1
LS 2
LANTAI 14
SEPARATOR BEAM
15/08/25
Merak
6 m3
22/08/25
Merak
2 m3
02/5/25
Adhimix
120 m3
DENAH SLAB LANTAI 15
4/5/25
Adhimix
140 m3
07/05/25
Merak
165 m3
08/08/25
Merak
52 m3
22/08/25
Merak
9 m3
22/08/25
Merak
98 m3
DENAH KOLOM LANTAI 15
02/05/25
12 m3
Adhimix
03/05/25
20,5 m3
Merak
04/05/25
12,5 m3
Adhimix
06/05/25
16 m3
Adhimix
08/05/25
17 m3 Merak
11/05/25
38,5 m3 Merak
12/05/25
8 m3 Adhimix
/25
8 m3 Adhimix
LS 1
LS 2
LANTAI 15
SEPARATOR BEAM
19/08/25
Merak
3 m3
12/05/25
Merak & Adhimix
150 & 15 m3
DENAH SLAB LANTAI 16
17/05/25
Merak
135 m3
20/05/25
Merak
190 m3
23/08/25
Merak
52 m3
24/08/25
Merak
6 m3
28/08/25
Merak
98 m3
DENAH KOLOM LANTAI 16
13/05/25
16 m3
Adhimix
14/05/25
26,5 m3
Merak
15/05/25
6 m3
Merak
18/05/25
16 m3
Merak
21/05/25
26,5 m3
Merak
23/05/25
20,5 m3
Merak
25/05/25
17 m3
Merak
24/08/25
7 m3
Merak
/25
8 m3 Adhimix
LS 1
LANTAI 16
SEPARATOR BEAM
19/08/25
Merak
3 m3
22/08/25
Merak
2 m3
23/05/25
Merak
160 m3
DENAH SLAB LANTAI 17
26/05/25
Merak
143 m3
29/05/25
Merak
163 m3
30/08/25
Merak
52 m3
2/09/25
Merak
98 m3
DENAH KOLOM LANTAI 17
25/05/25
16 m3
Merak
26/05/25
16 m3
Merak
27/05/25
8,5 m3
Merak
28/05/25
18 m3
Merak
29/05/25
16,5 m3
Merak
30/05/25
31 m3
Merak
31/05/25
5 m3
Merak
01/06/25
10 m3
Merak
3/09/25
8 m3 Adhimix
LS 1
LS 2
LANTAI 17
SEPARATOR BEAM
20/08/25
Merak
3 m3
02/06/25
Merak
143 m3
DENAH SLAB LANTAI 18
13/06/25
Merak
147 m3
16/06/25
Merak
149,5 m3
11/09/25
Merak
143 m3
6/09/25
Merak
60 m3
DENAH KOLOM LANTAI 18
03/06/25
26 m3
Merak
13/06/25
15 m3
Merak
15/06/25
16 m3
Merak
17/06/25
25 m3
Merak
18/06/25
9 m3
Merak
19/06/25
20 m3
Merak
20/06/25
9 m3
Merak
12/09/25
8 m3 Adhimix
LS 1
LS 2
LANTAI 18
SEPARATOR BEAM
18/06/25
Merak
146,5 m3
DENAH SLAB LANTAI 19
23/06/25
Merak
118,5 m3
28/06/25
Merak
135 m3
13/09/25
Merak
56 m3
18/09/25
Merak
104 m3
DENAH KOLOM LANTAI 19
20/06/25
25 m3
Merak
22/06/25
15 m3
Merak
24/06/25
13 m3
Merak
29/06/25
15 m3
Merak
01/07/25
24,5 m3
Merak
02/07/25
15 m3
Merak
04/07/25
4,5 m3
Merak
15/09/25
7 m3
Merak
18/09/25
8 m3 Merak
LS 1
LS 2
LANTAI 19
SEPARATOR BEAM
04/07/25
Merak
148 m3
DENAH SLAB LANTAI 20
09/07/25
Merak
130 m3
11/07/25
Merak
160 m3
20/09/25
Merak
60 m3
23/09/25
Merak
100 m3
DENAH KOLOM LANTAI 20
09/07/25
34,5 m3
Merak
09/07/25
9 m3
Merak
11/07/25
24 m3
Merak
12/07/25
24 m3
Merak
13/07/25
25 m3
Merak
14/07/25
33,5 m3
Merak
15/07/25
8 m3
Merak
22/09/25
10 m3
Merak
23/09/25
8 m3 Merak
LS 1
LS 2
LANTAI 20
SEPARATOR BEAM
19/07/25
Merak
180 m3
DENAH SLAB LANTAI ATAP
27/07/25
Merak
220 m3
03/08/25
Merak
210 m3
4/10/25
Merak
120 m3
4/10/25
Merak
60 m3
Total 790 m3
DENAH KOLOM LANTAI ATAP
2 m3
Merak
19/08/25
2 m3
Merak
DENAH DINDING PARAPET LANTAI ATAP
06/08/25
6 m3
Merak
08/08/25
6 m3
Merak
14/08/25
2 m3
Merak
Merak