1 of 56

Campus Master Plan

January 9, 2025

Presented by: Connie King, MAROTTA / MAIN Architects

Steve Gergely, Harbor Engineering

Dr. Dale Reimann, Acting Superintendent

Donna Robbins, Chief Operating Officer

Tom Koch, Plant Manager

Dave Rilatt, High School Principal

Tim Hollenback, Athletic Director

2 of 56

Agenda

2

  • Need
  • Process
  • Schedule
  • Schematic Drawings
  • Community Forum

3 of 56

Athletics Need Locations

3

  • Stadium
  • Journey Field
  • Baseball/Softball Fields
  • Additional Training Facility with Fitness Center

4 of 56

Stadium Concerns

4

  • Bleachers
  • Press Box
  • Lack of ADA Accessibility
  • Track
  • No Locker Rooms at Stadium

5 of 56

Home Bleacher Staircase at Stadium (Unstable)

5

6 of 56

Home Bleachers at Stadium - rust

6

7 of 56

Home Bleachers at Stadium - rust

7

8 of 56

Home Bleachers at Stadium

8

9 of 56

Home Bleacher Base at Stadium

9

10 of 56

Exterior of Pressbox

10

11 of 56

Top of Press Box

11

12 of 56

Press Box (Wood damage)

12

13 of 56

Press Box Windows

13

14 of 56

Press Box

14

15 of 56

Press Box

15

16 of 56

Stadium Field ADA Challenges - Visitor Bleachers

16

17 of 56

Stadium Field ADA Challenges - Visitor Bleachers

17

18 of 56

Issues with Track Surface - condition, holes, age

18

19 of 56

No Visiting Locker Room at Stadium (at Neff)

19

20 of 56

No Home Locker Room at Stadium (in HS Auditorium Lobby)

20

21 of 56

No Home Locker Room at Stadium (in HS Auditorium Lobby)

21

22 of 56

Need for a Higher Capacity Home Bleacher

22

23 of 56

Journey Field Concerns

23

  • ADA Accessibility
  • Lack of seating
  • Outdated Restrooms/Concessions
  • No Locker Rooms at Field
  • No Press Box
  • No Lights

24 of 56

Journey Field ADA Challenges - Entry Points

24

25 of 56

Journey Field ADA Challenges - Bleachers

25

26 of 56

Journey Field Seating

26

27 of 56

Journey Field Seating

27

28 of 56

Journey Field Seating

28

29 of 56

Journey Field

29

30 of 56

Outdated Restrooms. Trough and no doors in men’s room stalls.

30

31 of 56

Baseball/Softball Field Concerns

31

  • Title IX Inequality between fields
  • No Press Box or Concessions at Softball
  • Press Box/Concessions outdated at Baseball
  • Lack of irrigation at Softball
  • ADA Accessibility Concerns at Softball
  • Lack of Seating at both fields

32 of 56

Baseball Field View (Outdated Press Box & Concessions)

32

33 of 56

Softball Field View (No Press Box or Concessions)

33

34 of 56

Baseball

34

35 of 56

Baseball

35

36 of 56

Softball: No Press Box or Concessions

36

37 of 56

Challenges of Existing Training Areas

37

  • Stadium is our only lined turf football field for four football teams, marching band and color guard (significant scheduling constraint)
  • Lined grass football fields are on baseball fields, risking potential damage to those fields
  • Outdated and undersized weight room in the high school
  • Challenges during inclement weather

38 of 56

High School Weight Room Concerns

38

39 of 56

Opportunities of an Indoor Training Facility

39

  • Additional space for PE Department and MT Athletic teams to utilize in winter months or poor weather days
  • Flexible scheduling options for all teams, marching band, and color guard
  • Opportunity to rent the facility to local clubs and organizations
  • Modern and appropriately sized weight room

40 of 56

Maintenance Building (Insufficient space; aging structure & MEP, no life safety - alarms, sprinklers, etc.)

40

41 of 56

Process

41

    • September 2024 MTSD approves Marotta Main Architects & Harbor Engineering to proceed with Campus Master Plan work.
    • Oct. – Dec. 2024 Bi-Weekly meetings with Master Plan Team
      • Phase I Vendor engagement
      • Program definition
    • January 9th 2025 MTSD Board Update
    • February 12th 2025 Community Forum
    • March 2025 MTSD Board - Review and vote on proceeding with projects

42 of 56

Proposed Project Scope

PHASE I (no land development):

  • Softball, Baseball, and multi-purpose (field L) irrigation
  • Track resurfacing
  • Lighting - Journey Field
  • Demolition of fuel tanks
  • Stadium Bleacher - Refurbish home side

42

PHASE PH

43 of 56

Proposed Project Scope

PHASE II (land development):

  • Team Building/New Home Bleachers
    • New building
    • Demo existing visiting bleachers
  • Stadium
    • New home bleachers, decks, ramps, steps, pressbox
    • Journey Field bleachers
  • Sitework
    • New Neff parking lot
    • Walkways, fencing
    • Ticket Booths
    • Stormwater, E&S, grading, demo, landscaping, earthwork, etc.
  • Maintenance Building
    • Demo of existing building, new building, sitework & parking
  • Softball & Baseball
    • Bleachers, storage, concessions, pressbox
  • Landis Run Intermediate School
    • Parking lot / center lane
    • Stormwater, E&S, grading, demo, landscaping, earthwork, etc.
  • Field House
    • New field house building, sitework
  • Indoor Training Facility
    • Indoor turf practice field
    • Restrooms
    • Fitness Center

43

PHASE PH

44 of 56

Schedule

  • 1/9/25 – School Board Work Session
    • School Board Presentation - Campus Master Plan Update
  • 1/10/25 to 1/23/25
    • Building of website (project details, drawings / images)
  • 1/24/25 - Online Community Survey Open
  • 2/12/25 - Community Engagement Forum
    • 5:30 p.m. at MTMS
  • 2/13/25 - School Board Work Session
    • Present cost estimates
  • 2/14/25 - Online Community Survey Closes
  • 2/20/25 - School Board Debt Workshop
  • 3/13/25 - Present Debt Options to the Board - proposal to approve state-contract work/vendors

44

45 of 56

Schedule

45

46 of 56

Schematic Drawings

46

Site Plan

47 of 56

Schematic Drawings

47

Site Plan - Stadium

48 of 56

Schematic Drawings

48

Landis Run Intermediate School - Added Parking and Lane

49 of 56

Schematic Drawings

49

Team Building + New Home Bleachers

50 of 56

Schematic Drawings

50

Team Building + New Home Bleachers

51 of 56

Schematic Drawings

51

Field House + Journey Field

52 of 56

Schematic Drawings

52

Field House + Journey Field

53 of 56

Schematic Drawings

53

Softball and Baseball Upgrades - Initial Concept

54 of 56

Schematic Drawings

54

Maintenance Building

55 of 56

Schematic Drawings

55

Training Facility

56 of 56

Questions / Discussion

56