1 of 40

Lexington High School�School Building Committee

SBC Meeting

10/15/2024

2 of 40

  1. Call to Order
  2. Vote Previous Meeting Minutes 12:00 – 12:05 p.m.
    • September 30th, 2024
    • October 7th, 2024
  3. CM at Risk Selection Sub-Committee 12:05 – 12:10 p.m.
    • Vote: Qualified CM(s) for RFP Shortlist
    • Vote: Request for Proposal Approval
  4. Present PSR Cost Estimates 12:10 – 12:50 p.m.
  5. Present Solar PV Assessment 12:50 – 1:25 p.m.
  6. Confirm: "New Construction on Fields" Option 1:25 – 1:30 p.m.
  7. Confirm: "Phased-in-Place" Option 1:30 – 1:35 p.m.
  8. Public Comment 1:35 – 1:45 p.m.
  9. Reflections/Action Items 1:45 – 2:00 p.m.
  10. Adjourn 2:00 p.m.

SBC Meeting Agenda

2

10/15/2024

3 of 40

CM at Risk Selection Sub-Committee/ Schedule

  • Develop Construction Manager at Risk (CMR) sub-committee 08/19/2024
  • Develop Request for Qualifications (RFQ) 08/26 – 09/5/2024
  • Review RFQ with CMR sub-committee 09/09/2024
  • Issue RFQ 09/18/2024
  • CMR qualifications due 10/09/2024
  • Short list CMR 10/17/2024
  • CMR Request for Proposals (RFP) 10/17/2024
  • CMR site walkthrough 10/24/2024
  • CMR proposals due 11/14/2024
  • Review proposals with CMR sub-committee 11/14 – 11/22/2024
  • Interview CMR firms week of 12/03/2024
  • Award Schematic Design (SD) Purchase Order (PO) 12/16/2024

3

10/15/2024

4 of 40

PSR Cost Estimates

5 of 40

PSR Cost Estimates/ Construction Alternative Summary | Costs include the Central Office – No Field House

5

10/15/2024

B. Renovation & Addition

C. New Construction – On Fields

D. New Construction – Phased in Place

Alternative

B.1 Quad

B.4 Figure Eight

C.1d Branch

C.2b Braid

C.5b Bloom

D.2 Weave

Project Cost �School & CO

$672,000,000

$674,000,000

$619,000,000

$618,000,000

$621,000,000

$693,710,000

Construction Duration

6 Years

6.25 Years

4.5 Years

4.5 Years

4.5 Years

6.5 Years

# of Phases

4 + 1

5 + 1

1 + 1

1 + 1

1 + 1

4 + 1

Building Location

Existing Footprint

Existing Footprint

Fields

Fields

Fields

Existing Footprint

Modular Max Required

32

42

0

0

0

48

Costs are School Building and Central Office Only NO Field House or Pool

6 of 40

PSR Cost Estimates

6

10/15/2024

B.1 Quad

B.4 Figure Eight

C.1d Branch

C.2b Braid

C.5b Bloom

D.2 Weave

New High School

$649 Million

$651 Million

$596 Million

$595 Million

$598 Million

$670 Million

New High School + CO

$672 Million

$674 Million

$619 Million

$618 Million

$621 Million

$694 Million

New High School + CO

+ Renovated FH

$699 Million

$704 Million

$646 Million

$645 Million

$648 Million

$720 Million

New High School + CO

+ Add/Reno FH

$713 Million

$715 Million

$660 Million

$659 Million

$662 Million

$734 Million

New High School + CO

+ Small New FH

$710 Million

$712 Million

$657 Million

$656 Million

$659 Million

$731 Million

New High School + CO

+ Medium New FH

$732 Million

$734 Million

$679 Million

$678 Million

$681 Million

$754 Million

New High School + CO + Large New FH

$743 Million

$745 Million

$690 Million

$689 Million

$692 Million

$764 Million

CO = Central Office FH = Field House

7 of 40

PSR Cost Estimates/ Field House Alternative Summary

7

10/15/2024

Renovation

Add/Reno

Small

Medium

Large

Project Cost

$27,000,000

$41,000,000

$38,000,000

$60,000,000

$71,000,000

Footprint

34,000 SF

48,000 SF

36,000 SF

60,000 SF

72,000 SF

Track Size

146m

200m

146m

200m

200m

Lane Count

4

4

4

4

6

Bleacher Count

750

1500

750

1500

1500

8 of 40

Solar PV Assessment

9 of 40

Solar PV Assessment /Net Zero Energy Planning

9

10/15/2024

Estimated Annual Building Energy Use:

3,300,000 – 3,500,000  kWh

Based on EUI

25

KBtu/SF/Yr.

Solar PV Analysis caveats:

  • Sizing and quantities are PRELIMINARY and subject to change
  • Include a 10% margin of error
  • Preliminary HVAC layouts: subject to change with impact available roof areas and final PV layout: location, clearances, roof screens, etc.

10 of 40

Solar PV Assessment

10

10/15/2024

Estimated Solar PV System Site Sizing and Annual Production

Roof & Parking Spaces Only

C.1d Branch

C.5b Bloom

D.2 Weave

Simulated Total Annual Production (kWh)

4,221,028

4,193,761

4,117,464

Estimated Total Production (kWh) with Margin of Error (10%)

3,798,925

3,774,385

3,705,718

**Notes:

  1. The Simulated Total Annual Production values are PRELIMINARY and represent the highest possible yield of the modeled system. Values are subject to change as the system's design (layout, stringing, shading, roof equipment screens, etc.) advances that will impact the final Solar PV sizing. The estimated total capacity with a 10% margin of error has been calculated.
  2. The assessments take into the maximum total roof areas allocated for Solar PV within the preliminary roof equipment assessments. They are subject to reduction/adjustments in area available, pending HVAC design layouts/walkways, paths, and setbacks, and roof screens. They do take into account the 10-15' high shading from the HVAC equipment areas, shading from the buildings on the canopies, and canopy-to-canopy shading.

11 of 40

View of Roof + Parking Scenario

Solar PV Assessment / C.1d Branch

Solar Design Associates: Rooftop Solar PV Layout

11

10/15/2024

C1.d Branch

Roof & Parking Spaces Only

Estimated Annual Total Production (kWh)

4,221,028.1

Estimated Total Production (kWh) with Margin of Error (10%)

3,798,925

12 of 40

Solar PV Assessment / C.1d Branch

12

10/15/2024

13 of 40

Solar PV Assessment / C.1d Branch

13

10/15/2024

14 of 40

Solar PV Assessment / C.1d Branch

14

10/15/2024

15 of 40

Solar PV Assessment / C.1d Branch

15

10/15/2024

16 of 40

View of Roof + Parking Scenario

Solar PV Assessment / C.5b Bloom

16

10/15/2024

C5.b Bloom

Roof & Parking Spaces Only

Estimated Annual Total Production (kWh)

4,193,761.4

Estimated Total Production (kWh) with Margin of Error (10%)

3,774,385

Solar Design Associates: Rooftop Solar PV Layout

17 of 40

Solar PV Assessment / C.5b Bloom

17

10/15/2024

18 of 40

Solar PV Assessment / C.5b Bloom

18

10/15/2024

19 of 40

Solar PV Assessment / C.5b Bloom

19

10/15/2024

20 of 40

Solar PV Assessment / C.5b Bloom

20

10/15/2024

21 of 40

View of Roof + Parking Scenario

Solar PV Assessment / D.2 Weave

21

10/15/2024

D.2 Weave

Roof & Parking Spaces Only

Estimated Annual Total Production (kWh)

4,117,464.3

Estimated Total Production (kWh) with Margin of Error (10%)

3,705,718

Solar Design Associates: Rooftop Solar PV Layout

22 of 40

Solar PV Assessment / D.2 Weave

22

10/15/2024

23 of 40

Solar PV Assessment / D.2 Weave

23

10/15/2024

24 of 40

Solar PV Assessment / D.2 Weave

24

10/15/2024

25 of 40

Solar PV Assessment / D.2 Weave

25

10/15/2024

26 of 40

Confirm New Construction on Fields Option

27 of 40

Confirmation/ New Construction on Fields

27

10/15/2024

B. Renovation & Addition

C. New Construction – On Fields

D. New Construction – Phased in Place

Alternative

B.1 Quad

B.4 Figure Eight

C.1d Branch

C.2b Braid

C.5b Bloom

D.2 Weave

Project Cost

School & CO

$672,000,000

$674,000,000

$619,000,000

$618,000,000

$621,000,000

$693,710,000

Construction Duration

6 Years

6.25 Years

4.5 Years

4.5 Years

4.5 Years

6.5 Years

# of Phases

4 + 1

5 + 1

1 + 1

1 + 1

1 + 1

4 + 1

Building Location

Existing Footprint

Existing Footprint

Fields

Fields

Fields

Existing Footprint

Modular Max Required

32

42

0

0

0

48

Costs are School Building and Central Office Only NO Field House or Pool

28 of 40

Confirm Phased in Place Option

29 of 40

Confirmation/ Phased in Place

29

10/15/2024

B. Renovation & Addition

C. New Construction – On Fields

D. New Construction – Phased in Place

Alternative

B.1 Quad

B.4 Figure Eight

C.1d Branch

C.2b Braid

C.5b Bloom

D.2 Weave

Project Cost

School & CO

$672,000,000

$674,000,000

$619,000,000

$618,000,000

$621,000,000

$693,710,000

Construction Duration

6 Years

6.25 Years

4.5 Years

4.5 Years

4.5 Years

6.5 Years

# of Phases

4 + 1

5 + 1

1 + 1

1 + 1

1 + 1

4 + 1

Building Location

Existing Footprint

Existing Footprint

Fields

Fields

Fields

Existing Footprint

Modular Max Required

32

42

0

0

0

48

Costs are School Building and Central Office Only NO Field House

30 of 40

Public Comment

31 of 40

Reflections & Action Items

32 of 40

Thank You!

SBC Meeting

10/15/2024

33 of 40

Scale Comparison

33

10/15/2024

Renovation 34,400 SF

Large

72,000 GSF

Medium

60,000 GSF

Small

36,000 GSF

Renovation & Addition

48,000 SF

34 of 40

Specifications

  • 146-meter track
  • 4 lane oval
  • 300 - 750 seat bleachers
  • Infield all rubber surface

Approximate Total Gross Area: 34,400 GSF

Renovation Only/ 34,400GSF

34

10/15/2024

35 of 40

Specifications

  • 200-meter track
  • 4 lane oval
  • ~1500 seat bleachers
    • to be confirmed
  • Infield half rubber half wood surface

Approximate Total Gross Area: 48,000 GSF

Addition & Renovation/48,000 GSF

35

10/15/2024

36 of 40

Specifications

  • 146-meter track
  • 4 lane oval
  • ~750 seat bleachers
  • Infield all rubber

Approximate Total Gross Area: 36,000 GSF

Small New Construction /36,000 GSF

36

10/15/2024

37 of 40

Specifications

  • 200-meter track
  • 4 lane oval
  • ~1500 seat bleachers
  • Infield half rubber, half wood

 surface

Approximate Total Gross Area: 60,000 GSF

Medium New Construction/60,000GSF

37

10/15/2024

38 of 40

Specifications

  • 200-meter track
  • 6 lane oval
  • ~1500 seat bleachers
  • Infield half rubber half wood

 surface

Approximate Total Gross Area: 72,000 GSF

Large New Construction/72,000 GSF

38

10/15/2024

39 of 40

Progress Update/ 9.30

39

10/15/2024

Choose a “New Construction on Fields” Option

Introduction

Discussion

Confirmation

Choose a “Phased in Place” Option

Introduction

Discussion

Confirmation

Confirmed 9.03.24

  • 470 Parking Spaces – Existing Footprint
  • 500 Parking Spaces – on Fields

Confirmed 9.16.24

  • 461,513 Total GSF
  • 1st Floor Gymnasium
  • 4 Stories
  • Horizonal Expansion

40 of 40

Progress Update/ 10.15

40

10/15/2024

Choose a “New Construction on Fields” Option

Introduction

Discussion

Confirmation

Choose a “Phased in Place” Option

Introduction

Discussion

Confirmation

Confirmed 9.03.24

  • 470 Parking Spaces – Existing Footprint
  • 500 Parking Spaces – on Fields

Confirmed 9.16.24

  • 461,513 Total GSF
  • 1st Floor Gymnasium
  • 4 Stories
  • Horizonal Expansion