SAP Project System 0837
Generate Settlement Rule
for Project
and Its related Configuration
The Period End Processing requires Results Analysis Key and Settlement Rules for Results Analysis, Incoming Orders, and Settlement.
Settlement Strategy for Project Profile
CJ20N
Strategy 10 is assigned to
Project Profile 2000
Settlement RULE
Check Settings for Strategy 10
Results Analysis Key
SD doc if assigned will be the Settlement Rule
Settlement Profile determine for the WBS
Settlement Receiver
Change in assignment of organizational units Stipulates that the settings made are only valid if the assignments of the current object and the object directly above it in the hierarchy differ in one of the following organizational units:
•Company code
•Business area
•Profit center
Settlement Profile
Default Settlement to WBS