ROOTED SCHOOL VANCOUVER · BOARD WORKSHOP · IX.B
Facilities and renewal:
where the numbers stand
Expansion workshop 2: Colas cost estimates and affordability against the facilities guardrail. Renewal work session: evidence status before the Nov 15 binder and Nov 19 Gate 1.
Tuesday, November 10, 2026 · Dr. Jamila Singleton, Executive Director · Blueprint and Green Channel joining
BOTTOM LINE
7607 works physically. At today’s price, it does not fit the guardrail.
$4.3–5.2M
Colas build-out, hard costs
High school only, or with a 3-classroom addition. Design, permits and abatement are not included.
$12.3–14M
All-in project
$6.3M purchase + ~$1.7M to exit our lease and loan + build-out and soft costs.
19–21%
of revenue at 350 students
Against a 10–11% target and 14% ceiling. Only a ~490-student 6–12 campus comes near 14–15%.
Sources: Colas schematic budgets (Nov 6); Green Channel update (Nov 2); Blueprint/JGP guardrail figures (Oct 19). Debt service modeled at 7.5%, 30 years.
EXPANSION WORKSHOP 2 · COLAS ESTIMATES
Two schematic budgets, received Nov 9
Option A · High school, existing footprint
$4,285,003
23,629 SF · $181/SF · 6-month build
Direct $3.06M + markups $1.22M
Option B · Adds 3 classrooms (~3,100 SF)
$5,172,008
26,748 SF · $193/SF · 7-month build
Direct $3.69M + markups $1.48M
Both include: finishes (~$1M, the largest line), one science lab (6 gas stations, fume hood, eyewash/shower), CTE health rooms with exam stations, secure vestibule, dropped classroom ceilings, 13% contingency/escalation, 8.5% tax. Option B is the footprint that could hold a middle school.
Source: Colas Construction, “Rooted Test Fit Schematic Budget” Options A and B, dated Nov 6, 2026 (ROM concept pricing on LSW schematic plans).
ALL-IN PROJECT COST
The build-out is only a third of what has to be financed
Component | Option A · HS | Option B · +3 rooms |
Purchase price (seller’s ask) | $6.30M | $6.30M |
Exit current lease (~$619K) and Raza loan (~$879K), est. | $1.70M | $1.70M |
Colas build-out (hard costs) | $4.29M | $5.17M |
Soft costs not in Colas (design, permits, fees), 15% placeholder | $0.64M | $0.78M |
Total to finance | $12.9M | $14.0M |
Annual debt service / rent (7.5%, 30 yrs) | $1.10M | $1.18M |
Without the soft-cost placeholder: $12.3M / $1.04M a year (A) and $13.2M / $1.12M a year (B). Today RSV spends about $170K a year on facilities.
Lease/loan exit per Oct 23 Green Channel meeting notes. Soft-cost rate is an ED planning assumption, not a quote. Payment factor 0.0847 per $1 financed.
AFFORDABILITY VS. THE GUARDRAIL
Facilities cost as a share of revenue
Target 10–11%
Ceiling 14%
Stressed 15%+
Enrollment | Revenue (est.) | Option A · $1.10M/yr | Option B · $1.18M/yr |
260 (lender haircut) | $4.2M | 26% · stressed | 28% · stressed |
350 (HS full) | $5.6M | 20% · stressed | 21% · stressed |
420 (6–12) | $6.7M | no room | 18% · stressed |
490 (6–12) | $7.8M | no room | 15% · at the edge |
Even the best case only reaches the stressed line, and it depends on 490 students fitting in 26,748 SF and on a middle school budget JGP has not yet delivered.
Revenue ≈ $16K per student, from the Blueprint/JGP figure (10% ≈ $560K at ~350). Includes the 15% soft-cost placeholder; hard costs only lower each figure by about one point.
WORKING BACKWARD FROM THE GUARDRAIL
What each guardrail level can finance
Share of revenue | At 350 (HS) | At 490 (6–12) |
10% target | $6.6M | $9.3M |
11% target | $7.3M | $10.2M |
14% ceiling | $9.3M | $13.0M |
15% stressed | $9.9M | $13.9M |
Project needs | $12.9M (A) | $14.0M (B) |
High school only, at 14%
Purchase price would need to fall to about $2.6M, less than half the $6.3M ask.
6–12 at 490, at 14%
Purchase price near $5.3M, about $1M off the ask, or the same gap closed by grants or a lease-to-own.
Supportable project = annual payment ÷ 0.0847 (7.5%, 30 years). Price targets keep the $1.7M exit cost and Colas costs plus 15% soft costs.
Still a draft
Net cash margin: –$1.70M (2027-28), –$856K (2028-29), –$1.44M (2029-30), –$132K (2030-31). 2027-28 is the pre-opening year; 2029-30 includes the ~$830K Raza loan payoff.
MIDDLE SCHOOL MODEL · JGP DRAFT, NOV 9
Grades 6–8 add students – Two Campuses vs. One Campus
Year | Grades | Students | State rev. |
2028-29 | 6 | 30 | $679K |
2029-30 | 6–7 | 60 | $1.18M |
2030-31 | 6–8 | 90 | $1.75M |
2032-33 | 6–8 | 90 | $1.84M |
The cliff at 100 students
The state’s small-school top-up ends above 100. Per-student revenue falls from $17.7K at 90 to $14.6K at 135 and $13.6K at 180. A 490-student 6–12 campus needs about 140 in grades 6–8.
Source: MS_RSV_20261109.xlsx (State Revenue Summary, Sensitivity at 2026-27 rates, Personnel, Enrollment). JGP’s own check: 430 students at 14% supports about $11.5M.
Still a draft: assumes $500K a year in CSP funding for 2028–31, 25% special education (ours is ~35%), and the middle school in the current building.
MIDDLE SCHOOL MODEL · NET OPERATING INCOME
Losses shrink as grades fill, then widen again when CSP ends
–$1.68M
2027-28
–$753K
2028-29 · 30
–$605K
2029-30 · 60
–$122K
2030-31 · 90
–$543K
2031-32 · 90
–$528K
2032-33 · 90
■ Pre-opening year ■ With $500K/yr CSP ■ After CSP ends · Labels show year · students. Source: MS_RSV_20261109.xlsx, 5 YR Budget tab.
BEFORE ANYONE RELIES ON THESE NUMBERS
What the estimates leave out
Excluded by Colas
Program and code gaps
Each of these can only push costs up. Still pending: JGP’s middle school budget, Blueprint’s affordability assessment, the seller’s response on price and lease-to-own.
Sources: Colas clarifications and exclusions (Nov 6); LSW test fit; ED staffing model (13 stations incl. two science-capable rooms).
FOR BOARD DISCUSSION
Three asks tonight
1
Affirm the facilities guardrail
10–11% of revenue as the target, 14% as the ceiling. Any site is negotiated against this number, not the seller’s price.
2
Direct 7607 forward only as a 6–12 option
With a lower price or lease-to-own, no binding commitment before expansion approval, and 2–3 site options carried into the renewal.
3
Hold Gate 1 on Nov 19 as a real go/no-go
Every gap gets an owner and date or goes on the risk register; the Chair receives the Nov 30 status.
Next: Colas walkthrough this week · JGP middle school budget · seller response · Dec 15 building update and go/no-go on a purchase agreement (no earlier than January)