Municipal Contract Law �Maddie Cash �MAT Spring Short Courses 2024
Scope of MCL
- may be made by quotes or direct negotiation in the open market
- at least two quotes retained for one year
- no specific requirements for making the contract in the open market
- must be done by either direct negotiation by receiving two written quotes or upon sealed bids.
- if used, the two or more quotes must be retained for one year
- sealed bids require the most complicated procedure and are not typically used at this level
- MUST be let by sealed bids solicited by public notice using the procedures established for townships
- sealed bids process is a mix of statutory requirements, case law and common practice
- performance bonds and payment bonds quired
- Lowest responsible bidder requirement
$0-25,000
$25,000-175,000
Over $175,000
Contracting levels
Lowest Responsible Bidder Requirement
“a contract let on bid must be let to the lowest responsible bidder.” Minn. Stat. § 365.37, subd. 2
Separate from the requirements of MCL, but whenever the board initiated the sealed bidding process, the lowest responsible bidder requirement MUST be followed regardless of the value of the contract.
Simply giving a contract to the low bidder without considering whether the contractor can adequately perform the contract will not necessarily serve the public’s interests, so the municipality has some discretion.
If a low bid is rejected because it is made by an irresponsible bidder, the board must show some fact as to why the bidder is irresponsible (e.g. cannot complete the job, lacks the skill).
4
Lowest Responsible Bidder: Factors to consider
- FINANCIAL RESPONSIBILITY
- INTEGRITY
- SKILL
- ABILITY
- LIKELIHOOD OF PROVIDING FAITHFUL AND SATISFYING WORK
- PAST EXPERIENCE/RELIABILITY (NOT RUMORS)
Lowest Responsible Bidder: Equipment
CONSIDER:
Bid price
Quality
Suitability
Adaptability
DECIDING FACTORS MUST BE REASONABLE AND BASED ON SUBSTANTIAL DIFFERENCE IN QUALITY OR ADAPTABILITY.
OTTER TAIL POWER CO. V. VILLAGE OF ELBOW LAKE, 49 N.W. 2D 197, 201 (MINN. 1951).
Lowest Responsible Bidder: �Support Your Decision
Lowest Responsible Bidder: �Violations
8
Splitting contracts
9
Some townships may want to avoid the sealed bidding process by breaking up larger expensive contracts into smaller less expensive contracts.
Can we do that??
Not for the sole purpose of avoiding the need to advertise for sealed bids.
How??
Independent, identifiable parts of the project split in a reasonable way.
10
MCL Exemptions
Examples of excluded contracts:
Best Value Procurement Alternative
Violating MCL
12
Challenges can be brought by the losing bidder or by a taxpayer in the community
Injunction against the contract that was improperly awarded.
Re-let the contract to the lowest bidder or restart the process from the beginning.
Losing bidder is entitled to recover cost of preparing the bid, and town may still have to pay for benefits received under the voided contract.
Conflict of Interest
13
Conflict of Interest: Exemptions
14
To rely on an exemption, the board must:
Exemption
Unanimously vote, with the interested officer abstaining, to authorize the contract;
Vote
authorize the contract by resolution prior to performance of the contract; and
Resolution
The interested officer needs to file an affidavit with the clerk each time they submit a claim for payment.
Affidavit
Questions?
Thank you!
16