Local Agency Bridge Program Updates:�Bridge Load Rating Emergency Vehicles�IIJA�Implementing the new National Bridge Inspection Standards (NBIS)
OACES Fall Conference
Monday, October 17th, 2022
Jon Rooper, P.E.�ODOT Senior Load Rating Engineer Bridge Engineering Section
Bert Hartman, P.E.�ODOT Bridge Program & Standards Manager
Joel Boothe, P.E.�ODOT Bridge Operations Manager� ��
FAST Act Emergency Vehicles
OACES Fall Conference, October 17, 2022
Jon Rooper
FAST Act Emergency Vehicles
� �Legal Vehicles - Weight Table 1� (Single Axles = 20,000 lbs, Tandem Axles = 34,000 lbs, Gross Vehicle Weight = 80,000 lbs)
Type 3 Legal Vehicle (25 tons)
FAST Act Emergency Vehicles
2 Emergency Vehicle Models for Load Rating Analysis
FAST Act Emergency Vehicles
2 Emergency Vehicle Models for Load Rating Analysis
FAST Act Emergency Vehicles
FAST Act EV2 = 28.75 TONS
FAST Act EV3 = 43 TONS
Add the EV3 vehicle as one of the vehicles for strengthening designs in the BDM
Use the LRFD Strength II Limit State (1.35) for the design live load factor
FAST Act Emergency Vehicles
What about the rest of the bridges farther than 1 mile from an Interstate?
Since November 2016, all new LRFR load ratings have included EVs
Develop a risk based approach for the 4000+ bridges not yet rated for EVs in Oregon
Develop a risk based approach for the 4000+ bridges not yet rated for EVs in Oregon
EV3 GVW / Type 3 GVW = 86,000 / 50,000 = 1.72
Not likely the criteria FHWA used to determine high risk limit
EV3 tandem / Type 3 tandem = 62,000 / 34,000 = 1.82
FHWA likely used this ratio and conservatively rounded it up to 1.85 to differentiate high risk vs low risk EV bridges.
Develop a risk based approach for the 4000+ bridges not yet rated for EVs in Oregon
Compare unfactored load effects for longitudinal girders for simple spans
Develop a risk based approach for the 4000+ bridges not yet rated for EVs in Oregon
For the existing load ratings, determined if the Type 3 rating factor was controlled by a longitudinal girder or by a transverse (or other) member.
If longitudinal girder controlled:
Equivalent EV3 RF = Type 3 RF * 1.62
If transverse (or other) member controlled:
Equivalent EV3 RF = Type 3 RF * 1.85
Develop a risk based approach for the 4000+ bridges not yet rated for EVs in Oregon
245 ODOT bridges resulted in equivalent EV rating factors less than 1.0 and would need to be restricted.
263 local agency bridges resulted in equivalent EV rating factors less than 1.0 and would need to be restricted
** Based on Tier 1 load rating results, which focused on maximum force locations. More bridges may require EV postings/restrictions once they are rated in LRFR
Emergency Vehicle Bridge Restriction Lists
Once CCD gets caught up with getting all emergency vehicles permitted within Oregon, ODOT (and local agency) bridge restriction lists will be part of their permits.
381 ODOT Bridges will be restricted
(136 with low LRFR EV ratings + 245 low equivalent EV ratings)
ODOT will recommend that 859 local agency bridges be restricted
(596 with low LRFR EV ratings + 263 low equivalent EV ratings)
Local Agency Bridge Program Updates: IIJA�
Local Bridge Funding (21-24 STIP)
22
Original Funding = $80.6 M
Added IIJA Funding = $69.4M
Total = $150M
Local Bridge Funding (24-27 STIP)
23
Original Funding = $80.0 M
Added IIJA Funding = $54.4M
Total = $134.7M
Off-System Bridges
24
Based on Federal Functional Class
- Urban Local
- Rural Local
- Rural Minor Collector
IIJA (FY 22-26)
25
Bridge Formula Program (BFP)
- 15% Off-System Requirement
- No waiver
- $8.6 M per year
IIJA (FY 22-26)
26
Surface Transportation Block Grant
(STBG)
- 20% Off-System Requirement
- Waiver is possible
- $16.9 M per year if there is no waiver
Off-System Requirement Potential Impact
27
Local Bridge Funding (24-27)
- $134.7M ( $44.9M/year)
- BFP ($8.6M/year)
- STBG ($16.9M/year)
- Big & On ($19.4M/year)
Oregon Will Apply for the Off-System Waiver
28
Implementing the “New Rule” National Bridge Inspection Standards
Implementing the “New Rule” NBIS
What is the NBIS?
National Bridge Inspection Standard
National Bridge Inspection Standard
Who needs to comply with the NBIS?
The Owners
Subject to NBIS
All owners or operators of public road bridges are required to comply with the NBIS
Major owners of public road bridges in Oregon include:
What has changed in the latest NBIS
Changes, Requirements, and Costs
Changes in June 6, 2022 NBIS
Official Scope of Changes:
Changes in June 6, 2022 NBIS
More Detailed Summary of changes:
bridge inspectors
inspectors and team leaders
Changes in June 6, 2022 NBIS
More Detailed Summary of Changes (Part 2):
Changes in June 6, 2022 NBIS
More Detailed Summary of Changes (Part 3):
Changes in June 6, 2022 NBIS
More Detailed Summary of Changes (Part 4):
National Bridge Inventory (SNBI)”
Requirements Found in SNBI – Oregon Impacts
Annual submittal of data to FHWA has grown
Requirements Found in SNBI – Oregon Impacts
Scour documentation needs to be recreated
Requirements Found in SNBI – Oregon Impacts
Scour Critical Bridges to be inspected on 12 month interval
Requirements Found in SNBI – Oregon Impacts
Seismic Assessment
Added Cost to Comply
The Added Cost to reach compliance is still being evaluated, but at this point it appears to be:
Added Cost to Maintain Compliance
The added cost to maintain compliance is still being evaluated, at this point it appears to be:
When is Compliance Required?
Now
Compliance Deadlines
Scour Documentation: June 6, 2024
Reduced Inspection Frequencies to 12 months: June 6, 2024
Seismic Assessment: Program in place June 6, 2024
Annual Submittal Larger Database: Full compliance 2028