SAP Production Planning & Execution (PP)

Routing assignment to

Multiple Assemblies

2 of 28

  1. Create a Routing with Material
  2. Assign Routing to more than one Assemblies
  3. Component Assignments

3 of 28

Use CA01 to create Standard Routing in PPDI

4 of 28

Plant is Mandatory

Material leave BLANK

5 of 28

Usage and Status are for Routing Selection

UOM to be entered as no default possible from Material

Routing description (good for locating the routing in the next section)

6 of 28

7 of 28

Save the Routing

8 of 28

  • Create a Routing with Material
  • Assign Routing to more than one Assemblies
  • Component Assignments

9 of 28

GOTO Routing change mode

10 of 28

F4

11 of 28

Actual Text was

“Routing for FG100,200,300”

entered a wild card

12 of 28

Routing found, double-click

13 of 28

Goto Header of Routing

14 of 28

Goto material Assignment

15 of 28

Group Counter

Assembly and Plant

16 of 28

  • Create a Routing with Material
  • Assign Routing to more than one Assemblies
  • Component Assignments

17 of 28

Goto Component Allocation

18 of 28

Select FG100 BOM

19 of 28

Assign these 2 components to Operation 10

20 of 28

Assign the 2 components to Operation 10

21 of 28

Assign the 3rd component to Operation 20

22 of 28

Assign the 3rd component to Operation 20

23 of 28

SAVE

24 of 28

CA02 again, proceed to do Component allocation for FG200

25 of 28

26 of 28

Select FG200 BOM

27 of 28

Assign these 2 components to Operation 10

REPEAT same methods...

28 of 28

Allocation done, SAVE and Repeat the same steps for FG300