SAP Production Planning & Execution (PP)
Routing assignment to
Multiple Assemblies
Use CA01 to create Standard Routing in PPDI
Plant is Mandatory
Material leave BLANK
Usage and Status are for Routing Selection
UOM to be entered as no default possible from Material
Routing description (good for locating the routing in the next section)
Save the Routing
GOTO Routing change mode
F4
Actual Text was
“Routing for FG100,200,300”
…
entered a wild card
Routing found, double-click
Goto Header of Routing
Goto material Assignment
Group Counter
Assembly and Plant
Goto Component Allocation
Select FG100 BOM
Assign these 2 components to Operation 10
Assign the 2 components to Operation 10
Assign the 3rd component to Operation 20
Assign the 3rd component to Operation 20
SAVE
CA02 again, proceed to do Component allocation for FG200
Select FG200 BOM
Assign these 2 components to Operation 10
REPEAT same methods...
Allocation done, SAVE and Repeat the same steps for FG300