1 of 19

Earned Value Analysis (EVA)

Dr Adewale Abimbola, FHEA, GMICE

www.edulibrary.co.uk

2 of 19

Aim and Objectives

  • Aim: Earned Value Analysis (EVA)

  • Objectives: At the end of the lesson, the students should be able to:

• Assess the progress of a construction project based on the measured progress achieved.

• Forecast total cost and date of completion of a construction project.

• Explain the importance of monitoring costs in construction projects.

3 of 19

Learning Outcome and Assessment Criteria

P5. Describe the key principles of construction project management.

M3. Compare different techniques for planning and managing resources.

4 of 19

Earned Value Analysis - Definition

  • • Earned Value Analysis (EVA) is a project management methodology used to quantify the actual work accomplished in a project.
  • • EVA offers a means to assess a project's progress based on the measured progress achieved.
  • • Through progress measurement, project managers can forecast a project's total cost and completion date using trend analysis, relying on a crucial metric called "earned value."
  • • "Earned value" is defined as the "budgeted cost of work performed" (BCWP), facilitating the computation of cost and schedule performance indices.
  • These indices provide insights into how well the project aligns with its original programme.

5 of 19

Earned Value Management – Fundamental Notions

Earned value management (EVM) serves the purpose of addressing three critical questions in project management:

  • 1. Historical progress on the project?
  • 2. Current status on the project?
  • 3. Future trajectory on the project?

Three primary data sources in earned value management include:

  1. The planned value (PV) or budget cost of work scheduled (BCWS).
  2. The actual cost (AC) of work completed (ACWP).
  3. The “earned value; EV” or budgeted cost of work performed (BCWP).

6 of 19

VARIANCE ANALYSIS

  • Schedule Variance (SV)
  • Reflects the currency difference between work ahead or behind the plan.
  • Computed as budget cost of work performed minus budget cost of work scheduled.

SV = BCWP – BCWS

  • A variance of 0 signifies an on-schedule project, a negative variance indicates being behind schedule, and a positive variance implies being ahead of schedule.
  • Cost Variance (CV)
  • Defined as the difference between budget cost of work performed and actual costs of work performed

CV = BCWP – ACWP

  • A variance of 0 indicates an on-budget project, a negative variance signals being over budget, and a positive variance suggests being under budget.

• Variance refers to a measurable deviation from a known baseline or expected value.

• Two fundamental expressions of variance include schedule variance and cost variance.

7 of 19

PERFORMANCE INDICES

  •  

• To analyse project performance.

• Two key performance indexes are the Schedule Performance Index (SPI) and Cost Performance Index (CPI).

8 of 19

Case Study

  • The planned construction duration for a commercial project is 19 weeks (Figure 1). The contracting firm on a lump sum contract with the client estimates that the total direct costs will be £555,000.00 (See Table 1 for breakdown).

Activities

Start date

Duration (weeks)

Direct Cost (£)

Demolition / site preparation

01/11/2023

4

45,000.00

Substructure

29/11/2023

3

48,000.00

Prefab. Columns / slabs / beams

20/12/2024

3

117,000.00

Claddings

10/01/2024

3

80,000.00

Roof

17/01/2024

2

35,000.00

Wall, windows, doors & stairs

31/01/2024

2

90,000.00

Mechanical / Electrical services

14/02/2024

2

115,000.00

Drainage/Eternal works

28/02/2024

2

25,000.00

555,000.00

Table 1. Activity schedule.

Figure 1. Construction programme.

9 of 19

Case Study (Cont’d)

  • There has been sudden project delays and changes to the some of the material costs during construction. The project manager has compiled the summary report in Table 2 to monitor the cost and schedule.

Operations

Actual % Completion

Actual Cost

Site Preparation/Demolition

100

 

45,000.00

Substructure

100

 

48,000.00

Prefab Col./Slabs/Beams

100

120,000.00

Claddings

33.3

 

50,000

Roof

0

0

Wall, windows, doors, & stairs

0

0

Mechanical/Electrical services

0

0

Drainage/External works

0

0

Table 2. Field report compiled on January 17, 2024

Questions

  • Calculate the direct costs per week for each of the operations or activities.
  • Calculate the total values of the actual cost of work performed (ACWP), budgeted cost of work schedule (BCWS), and budgeted cost of work performed (BCWP).
  • Determine the cost performance index (CPI), cost variance (CV), schedule performance index (SPI), and schedule variance (SV).
  • Estimate the project cost at completion and the project duration.

10 of 19

Solution

Activities

Duration (weeks)

Direct Cost (£)

Direct costs per week (£)

Demolition/Site preparation

 

4

 

45,000.00

11,250.00

Substructure

3

48,000.00

16,000.00

Prefab. Columns / slabs / beams

 

3

 

117,000.00

39,000.00

Claddings

3

80,000.00

26,666.67

Roof

2

35,000.00

17,500.00

Wall, windows, doors & stairs

 

2

 

90,000.00

45,000.00

Mechanical / Electrical services

 

2

 

115,000.00

57,500.00

Drainage/Eternal works

2

25,000.00

12,500.00

555,000.00

 

Question 1

11 of 19

Solution

Refer to the EVA Excel file for breakdown

 

 

 

 

 

EARNED VALUE ANALYSIS (EVA)

 

 

 

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

Week 9

Week 10

Week 11

Week 12

Week 13

Week 14

Week 15

Week 16

Week 17

Week 18

Week 19

Operations

01-Nov

08-Nov

15-Nov

22-Nov

29-Nov

06-Dec

13-Dec

20-Dec

27-Dec

03-Jan

10-Jan

17-Jan

24-Jan

31-Jan

07-Feb

14-Feb

21-Feb

28-Feb

06-Mar

Site Preparation/Demolition

 

 

 

 

 

 

Substructure

 

 

 

 

Prefab Col./Slabs/Beams

 

 

 

 

Claddings

 

 

 

Roof

 

 

Wall, windows, doors, & stairs

 

 

 

 

Mechanical/Electrical services

 

 

 

 

Drainage/External works

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Direct costs per week

11,250

11,250

11,250

11,250

16000

16000

16000

39000

39000

39000

26666.67

26666.7

26666.7

45000

45000

57500

57500

12500

12500

 

 

 

 

 

 

 

 

 

 

 

 

 

17500

17500

 

 

 

 

 

 

Total, ∑

Total: Direct costs per week

11250

11250

11250

11250

16000

16000

16000

39000

39000

39000

26666.67

44166.7

44166.7

45000

45000

57500

57500

12500

12500

555000.01

Field report compiled on January 17, 2024.

12 of 19

Solution

Question 2

Operations

Actual cost of work performed (ACWP)

Budgeted cost of work performed (BCWP)

Budgeted cost of work schedule (BCWS)

Site Preparation/Demolition

45,000.00

45,000.00

45,000.00

Substructure

48,000.00

48,000.00

48,000.00

Prefab Col./Slabs/Beams

120,000.00

117,000.00

117,000.00

Claddings

50,000.00

26,666.67

53,333.34

Roof

0.00

0.00

17,500.00

Wall, windows, doors, & stairs

0.00

0.00

0.00

Mechanical/Electrical services

0.00

0.00

0.00

Drainage/External works

0.00

0.00

0.00

263,000.00

236,666.67

280,833.34

Field Reporting Date: January 17, 2024.

13 of 19

Solution

  •  

 

Question 3

 

14 of 19

Solution

Question 3

 

 

15 of 19

Solution

Question 4

 

16 of 19

CUMULATIVE COST – ACWP, BCWP, & BCWS

Duration (Weeks)

Cumulative ACWP

Cumulative BCWP

Cumulative BCWS

0

0

0

0

4

45,000.00

45,000.00

45,000.00

7

93,000.00

93,000.00

93,000.00

10

213,000.00

210,000.00

210,000.00

11

263,000.00

236,666.67

263,333.34

12

263,000.00

236,666.67

280,833.34

17 of 19

Group Exercise

  • The planned construction duration for a foundation is 13 weeks. The contracting firm on a lump sum contract with the client estimates that the total direct costs will be £14,350.00 (See Table 1 for breakdown).

Activities

Duration (weeks)

Direct Cost (£)

Strip site - topsoil to a depth of 150 mm minimum

1

1,000.00

Excavate to reduced level

1

1,500.00

Set out house foundations

1

750.00

Excavate foundation trenches (including ducts for services)

2

1,800.00

Cast concrete to deep strip foundations

2

2,000.00

Brickwork to dpc (damp proof course) level

2

2,400.00

Fill cavity below dpc level

1

800.00

Supply and compact 150 mm hardcore to ground floor slab (including 50 mm sand blinding)

1

1,650.00

Lay dpm (damp proof membrane)

1

650

Spread and compact hardcore to ground floor slab

1

500

Excavate trenches for drainage/inspection chambers & lay them

2

900

Test drain for leaks and backfill drainage

1

400

14,350.00

Table 1. Activity schedule.

18 of 19

Group Exercise (Cont’d)

  • There has been sudden project delays and changes to the some of the material costs during construction. The project manager has compiled the summary report in Table 2 to monitor the cost and schedule.

Table 2. Field report compiled on January 17, 2024

Questions

  • Calculate the total values of the Budgeted cost of work performed (BCWP) and Budgeted cost of work schedule (BCWS).
  • Determine the Cost performance index (CPI), Cost variance (CV), Schedule performance index (SPI), and Schedule variance (SV).
  • Estimate the project cost at completion and the probable project duration.

Operations

Actual % Complete

Actual Cost of Work Performed (ACWP)

Strip site - topsoil to a depth of 150 mm minimum

100

1000

Excavate to reduced level

100

1550

Set out house foundations

100

725

Excavate foundation trenches (including ducts for services)

100

2000

Cast concrete to deep strip foundations

50

1100

Brickwork to dpc (damp proof course) level

0

0

Fill cavity below dpc level

0

0

Supply and compact hardcore to ground floor slab (including 50 mm sand blinding)

0

0

Lay dpm (damp proof membrane)

0

0

Spread and compact hardcore to ground floor slab

0

0

Excavate trenches for drainage/inspection chambers & lay them

0

0

Test drain for leaks and backfill drainage

0

0

Total, ∑

£6375.00

19 of 19

References /

Bibliography

  • Engineer4Free (2017) Earned value analysis worked example. Available at: https://www.youtube.com/watch?v=z7b3SYQuqJM&list=LL&index=3 (Accessed: 30 January 2024)
  • Project Management Institute (2004) A Guide to the Project Management Body of Knowledge (PMBOK® Guide). (3 ed.) Newtown Square, PA: Project Management Institute.
  • Reichel, C. W. (2006). ‘Earned value management systems (EVMS): you too can do earned value management’ Paper presented at PMI® Global Congress 2006—North America, Seattle, WA. Newtown Square, PA: Project Management Institute.