FY25 Capital Plan

November 2, 2023

2 of 26

3 of 26

End of Life Replacement Cycle

  • Vehicle $ 80,000
  • Technology Districtwide $ 100,000
  • HVAC Districtwide $ 700,000
  • High School Track & Field 3 $ 350,000

Enrollment Growth

  • Marathon Playground $ 1,000,000
  • Hopkins School Addition $ 43,940,000

Total $ 46,170,000

4 of 26

VEHICLE $80,000

This vehicle represents a replacement of one of five vehicles for the eight maintenance staff. The vehicles are used for maintenance, towing equipment, plowing, sanding etc. throughout the district. The vehicles are incurring costly repairs. This continues a replacement plan and improves efficiency and effectiveness.

The Parking Revolving Account will be used for this purchase.

5 of 26

TECHNOLOGY DISTRICTWIDE $100,000

All district wireless networks are designed to support high density classroom environments and large venue events in all of the schools’ common spaces. These wireless networks are composed of over 400 wireless access points districtwide. The school system is currently on a 5 year replacement cycle and is looking to replace all of these access points over two years. This represents year two of the replacements.

In addition to the capital funding, the district receives ERATE reimbursement for a percentage of the cost.

6 of 26

HVAC DISTRICTWIDE $700,000

(Hopkins School)

The HVAC replacements represent the large air handling units and roof top units. In FY25 the proposal is to replace 3 of 9 units at the Hopkins School. These units are in poor condition and are end of life replacements.

The replacements can be all electric and tie into the new system in the Hopkins addition OR a one-for-one replacement and continue on fossil fuel, if the Hopkins addition does not move forward.

7 of 26

HVAC DISTRICTWIDE $700,000

8 of 26

The Track and Field 3, with an amenities building, was identified as the priority to increase access for students and the community. The Track is at the end of its useful life. The Track has base layer deterioration. Field 3 is only utilized a few times a year to preserve the grass for football games only. There is not enough seating for events.

This funding will be for design and engineering for the track, field 3 and an amenities building.

HIGH SCHOOL TRACK & FIELD 3 $350,000

(Design & Engineering)

Current use:

  • XC, Football, Track
  • 100 XC, 125-150 Football, 346 Track
  • Field 3 reserved for games only
  • All TVL football games on Turf except 1 school

9 of 26

MARATHON PLAYGROUND $1,000,000

The Marathon School was built with a planned enrollment of 395 students. The K-1 enrollment, the grades that share this playground, is currently over 575 students. The existing playground is not able to accommodate the increased enrollment.

The playgrounds at the schools are also used by the community at large

A Community Preservation Act Funding Application has been submitted for this project.

10 of 26

The Hopkins School is currently unable to fit two grades. The existing school was designed to hold 628 students. The current enrollment is 677 students and is expected to reach 802 students, an increase of 174 students over capacity. The addition will include a new gym space, general and special education classrooms, and increased parking. It will also include relocation of the new modular classrooms from the Elmwood School (assuming the Elmwood Project moves forward). There will also be levels of renovation in the existing building as required by code.

The addition is currently in the design phase.

HOPKINS SCHOOL ADDITION $43,940,000

11 of 26

HOPKINS SCHOOL ADDITION $43,940,000

Districtwide Study Results

MSBA 10 Year Projected Average = Projected Enrollment

12 of 26

HOPKINS SCHOOL ADDITION $43,940,000

13 of 26

HOPKINS SCHOOL ADDITION $43,940,000

14 of 26

HOPKINS SCHOOL ADDITION $43,940,000

15 of 26

HOPKINS SCHOOL ADDITION $43,940,000

16 of 26

HOPKINS SCHOOL ADDITION $43,940,000

We are here

Public presentations - School Committee & Public Forums

17 of 26

HOPKINS SCHOOL ADDITION $43,940,000

Update:

The first cost estimates were received yesterday on the initial schematic design submission.

Concept Budget - December 2022 $43,940,000 (1)

(District Wide Study)

Initial Project Budget - November 2023 $46,226,723 (1)

Cost Increase to Concept Budget $ 2,286,723 (2)

  1. Cost excludes $3,000,000 already allocated at May 2023 town Meeting for this phase AND before any expected rebates.
  2. Scope added since Concept Budget such as geothermal, loop road paving close to school, walking track around playfields. The scope will continue to be defined.

18 of 26

HOPKINS SCHOOL ADDITION $43,940,000

  1. Early November update the School Committee on the initial Cost Estimate
  2. Early January Hopkins Design presentation to School Committee
  3. Mid-January hold Community Forum on the Hopkins School project
  4. Late January start permitting filings with Conservation Committee and Planning Board
  5. January CM-Selection Committee shortlists Construction Managers (CM) for 2nd round submission with fees.
  6. Late February CM-selection Committee Interviews 3 Construction Management teams and recommends award
  7. Early March School Committee reviews and authorizes hiring CM. Design team makes a presentation update
  8. April School Committee votes a Subcontractor Prequalification committee. (i.e. add 2 CM members to the CM-Selection Committee)
  9. May/June presentation of final design scope prior to bidding.

19 of 26

End of Life Replacement Cycle

  • Vehicle $ 80,000
  • Technology Districtwide $ 100,000
  • HVAC Districtwide $ 700,000
  • High School Track & Field 3 $ 350,000

Enrollment Growth

  • Marathon Playground $ 1,000,000
  • Hopkins School Addition $ 43,940,000

Total $ 46,170,000

20 of 26

Questions?

21 of 26

Capital Planning

Districtwide Study - Reminder

22 of 26

Districtwide Study Results

MSBA 10 Year Projected Average = Projected Enrollment

23 of 26

24 of 26

Capital Planning

Districtwide Study - Reminder

  1. The Elmwood Project will help to solve upstream enrollment growth.

  • A delay of additions to the middle and high school can only be achieved with a successful Elmwood Project.

  • A feasibility study for the Marathon School enrollment growth might include a reuse of the current Elmwood School space, only with a successful Elmwood Project.

  • The Hopkins Project will solve its own enrollment growth.

25 of 26