1 of 28

1

2 of 28

2

Monroe Town Council

February 2016

Masuk High School Benedict Stadium Track & Field Project

Monroe, Connecticut

3 of 28

Current Field Conditions

3

4 of 28

Current Sod

4

5 of 28

Current Sod (continued)

5

6 of 28

Current Track

6

7 of 28

Current Track (continued)

7

8 of 28

Fields in Neighboring Communities

8

9 of 28

Pomperaug High School

9

10 of 28

Trumbull High School

10

11 of 28

Oxford High School

11

12 of 28

Shelton High School

12

13 of 28

Joel Barlow High School

13

14 of 28

Newtown High School

14

15 of 28

A Masuk Transformation

15

16 of 28

16

Field Renovation

Design & Budget

17 of 28

17

Proposed Design Plan

  • New Synthetic Turf Field
  • Rebuild D Zones for Track Events
  • Add 2 Sprint Lanes
  • New Scoreboard
  • New Athletic Field Lighting
  • Resurface Track

18 of 28

18

Budget for Improvements

(This is the total project. Please see slide 24 for bonded amount.)

General Conditions

$ 100,000

Synthetic Turf Improvements

  • Synthetic Turf, Logo, Groomer, Football Goal Post
  • Ball Safety Netting
  • Earthwork/Drainage

$ 600,000

$ 20,000

$ 455,000

Track Improvements

  • Reconstruct North/South D Zones
  • Add 2 Sprint Lanes
  • Structural Spray Coat on Existing Track
  • Relocate Shot Put

$ 190,000

$ 100,000

$ 100,000

$ 25,000

Other Improvements

  • Athletic Field Lighting Upgrade
  • Audio System/Scoreboard/Security

$ 400,000

$ 65,000

Construction Contingency (10%)

$ 205,500

Project Budget

$ 2,260,500*

*If contingency not used, the following items could be included with project

    • Loose Field Equipment
    • Walkway from Field to School
    • Elevated Seating Platform

*Based on feedback from Town Council and Board of Finance, total bonding was reduced to $1.7 million. Please see slides 24 & 25.

19 of 28

19

Town Bond Appropriation

$1.7M

Booster Club/

Major Gifts

Naming Opportunity

Fundraising Plan

20 of 28

20

Field/Indoor Facility

July 1st 2014 – Jun 30th 2015

High School Total Hours by Field

High School % Of Use By Field

 

Community Total Hrs. By Field

Community % Of Use By Field

David Strong Gymnasium

815.5

79%

 

217.25

21%

John Giampaolo Field (Baseball)

178.5

62%

 

109.5

38%

Masuk Auxiliary Gym

375.25

87%

 

56

13%

Masuk Middle Field (Fall)

187

78%

 

52.5

22%

Masuk Pool

358

31%

 

814.7

69%

Masuk South Field

280

37%

 

487

63%

Masuk Stadium Field (Grass)

212.5

97%

 

6

3%

Masuk Upper Field

427.5

48%

 

464.85

52%

 

 

 

 

 

 

Total Field Use Hours/%

2,834.25

56%

 

2,207.8

44%

Additional 22-28 hours of usage on weekends (fall/spring) with

50% available for community use.

Community Usage – Big Opportunity

21 of 28

21

Turf Components

Alternative Infill

TPE

Organic

Alternative Rubber

Coated Sand

22 of 28

22

Turf Components – Underlayment

Shock Pad

E-Layer

23 of 28

Budget Options

23

24 of 28

Base/Alternate Contract Option - Base Budget (Bonded Amount)

24

General Conditions, Bonding, Site Preparation, Site Removals, Erosion Controls

$75,000

Synthetic Turf:

○ Synthetic Turf Field (alternate infill material)

  • 2 1/4” HT. Turf, Logo, Inlaid Field Lines
  • New Football Goal Posts, Field Groomer

○ Earthwork/Field Drainage

  • Strip and dispose of topsoil, mass earthwork, formation of subgrade
  • Collector pipe, underdrain, dynamic stone base, edge drain

$1,050,000

Track Improvements:

○ Reconstruct North D-Zone

  • High jump area
  • Discus cage/pad
  • New bituminous/track surfacing

○ Reconstruct South D-Zone

  • Long Jump Event with Sand Pit and Sand Catcher
  • Pole Vault Event (Vault Box/Lid)
  • New bituminous/track surfacing

○ Add 2 New Sprint Lanes

  • Move and Replace Fencing and Gates
  • New Sidewalk in front of Bleachers

○ Structural Spray Coat on Entire Track

○ Shot Put Relocation

$400,000

Other Improvements:

o Infrastructure for Future Lighting Upgrades and New Scoreboard

$50,000

Subtotal

$1,575,000

Construction Contingency

$125,000

Total Base Project Budget:

$1,700,000

25 of 28

Base/Alternate Contract Option - Add Alternates (fundraising)

25

Alternate #1 – Replace Field Lighting

$350,000

Alternate #2 – New Scoreboard and Audio System

$65,000

Alternate #3 – Ball Safety Netting in D-zones

$20,000

26 of 28

Use Capital Fund Account

Expend $274,196 from the capital account to fund a portion, or the balance, of costs not covered by fundraising.

26

27 of 28

27

27

&

28 of 28

28