1 of 41

VERONA BOARD OF EDUCATION� REFERENDUM PROJECTS UPDATE�SEPTEMBER 21, 2015

Prepared by:

Joe Trause, Director of Facilities

2 of 41

Projects by Type

  • VHS Mechanical System Replacement
  • General Construction – Music Addition, Vestibules, Main Offices, Kitchens at VHS and HBW
  • Site Improvements – Sidewalks, Curbs, and Asphalt at VHS, HBW, Forest, and FN Brown
  • Bleacher Upgrades at VHS (Both Gyms) and Brookdale
  • Exterior Door Replacements – District Wide
  • Back Up Generator – VHS
  • Fire Panel Replacements – FNB, Forest
  • Technology and Security Upgrades – District Wide
  • Masonry Repairs
  • Multi-Purpose Field Project

3 of 41

�Mechanical System �Replacement - VHS�

  • Scope includes replacement of all “original” HVAC equipment installed prior to 2007, much was original to 1956 and 1975.
  • Project addresses IAQ concerns in common areas, classrooms and main office along with upgrades to equipment and controls in classrooms. Energy efficient equipment and controls will be installed.
  • Due to the extensive engineering involved and the difficulty of executing this work during the school year, mechanical work will be executed primarily in the summers of 2015 and 2016.
  • AMCO Mechanical is the Contractor and work is on schedule.

4 of 41

Verona HS Mechanical � System Upgrades

FORMER VHS BOILERS

NEW AERCO CONDENSING BOILERS

5 of 41

Mechanical System �Replacement - VHS

NEW VICTAULIC FITTINGS AND PIPING

NEW EXPANSION TANKS

6 of 41

Verona HS Mechanical � System Upgrades

NEW AIR HANDLERS

7 of 41

General Construction Project

VHS MAIN OFFICE DURING CONSTRUCTION

8 of 41

General Construction Project

VHS MAIN OFFICE AFTER CONSTRUCTION

9 of 41

General Construction Project

VHS MAIN OFFICE

AFTER CONSTRUCTION

10 of 41

General Construction Project

FN BROWN MAIN OFFICE DURING CONSTRUCTION

11 of 41

General Construction Project

FN BROWN MAIN OFFICE AFTER CONSTRUCTION

12 of 41

General Construction Project

FN BROWN MAIN OFFICE AFTER CONSTRUCTION

13 of 41

General Construction Project

FOREST MAIN OFFICE DURING CONSTRUCTION

14 of 41

General Construction Project

FOREST MAIN OFFICE AFTER CONSTRUCTION

15 of 41

General Construction Project

FOREST MAIN OFFICE AFTER CONSTRUCTION

16 of 41

General Construction Project

ELEMETARY SCHOOLS VESTIBULES

17 of 41

Site Improvements Project

VHS

VHS

18 of 41

Site Improvements Project

VHS

VHS

19 of 41

Site Improvements Project

HB WHITEHORNE

HB WHITEHORNE

20 of 41

Site Improvements Project

HB WHITEHORNE

HB WHITEHORNE

  • After reviewing the new sidewalk, it was decided to add a railing for safety.

21 of 41

Site Improvements Project

FOREST AVE

FOREST AVE

22 of 41

Site Improvements Project

FOREST AVE

FOREST AVE

23 of 41

Site Improvements Project

FOREST AVE

24 of 41

Bleacher Upgrade Project

VHS

  • The old gym bleachers were completed by refinishing the fir boards that were collected from both gym’s bleachers, sanded, repaired, refinished, installed with new hardware and ADA compliance.
  • The new gym estimated completion date is the beginning of October 2015 because awaiting new bleacher seating that will be installed as soon as they are delivered.

25 of 41

Bleacher Upgrade Project

BROOKDALE

BROOKDALE

26 of 41

Exterior Door Project

EXISTING DOORS

NEW DOORS

  • Installation began September 14, 2015.

27 of 41

VHS BACKUP GENERATOR

  • Generator will serve critical components of Verona HS including;
  • Main Server Room, Boiler Room, Kitchen Equipment, and Emergency Lighting
  • Unit is in production. The delivery date is approximately the end of October 2015 and completion is approximately end of November 2015.

28 of 41

Fire Panel Replacement

  • Replace existing fire system panels at FN Brown and Forest Ave School. Both systems were antiquated and obsolete.
  • Scope consists of replacing panels and end devices while still utilizing existing wiring.

29 of 41

��Technology Upgrades District��

  • Project includes network replacement which includes a switch count to allow for future growth, wi-fi access points throughout the district, phone system replacement at VHS, a back-up generator at VHS and cabling for both technology and security purposes.
  • Security plan includes 120 cameras (district wide), 29 card reader/access control locations and a web-based management system to integrate all components.
  • Visitor management systems at 8 locations:
    • Each schools Main Entrances, the Board Office and Laning Pre-School Entrance.
  • Work related to technology improvements will be completed in 2015.

30 of 41

Technology Upgrades Switch Replacement

31 of 41

Technology Upgrades Switch Replacement

32 of 41

Technology Upgrades Wireless Network

33 of 41

Technology Upgrade HS P.A. System

34 of 41

��Security Upgrades�District��

  • Project includes the creation of secure vestibules at each school, office reconfiguration at VHS, FNB and Forest. Also includes a security camera system, visitor management system, and enhanced access controls.
  • Installation of technology based hardware (cameras, etc) is largely complete and construction work for vestibules is 95% complete.
  • Until our new system is installed, we are continuing our visitor procedures as we had last year so our schools continue to be safe.

35 of 41

Security Upgrades

AXIS BRAND – EXTERIOR CAMERAS

IP VIDEO – INTERIOR CAMERAS

36 of 41

Security Upgrades

ISONAS CARD READERS

SISCO FAST PASS VISITOR MGT

  • Phase 1 is construction of the vestibule which has been completed. In the process of

phase 2 which is adding upgraded door strikes, buzzer system and isonas card readers

for staff to the security vestibules.

37 of 41

�� Multi-Purpose Field & Site Improvements at VHS��

  • Engineering firm, French & Parrello Associates, is in the process of developing a full site plan for the Verona Planning Board’s review on September 29, 2015. Phase 1 for tennis courts and parking has already been submitted and is awaiting a review date.
  • The full site plan for the upper and lower fields are nearly complete. The plans are with our attorney and engineering firm and we anticipate submitting them in the coming weeks.

38 of 41

�Energy Savings �Improvement Program�

Some highlights of the program include:

  • LED lighting district wide will begin installation approximately October 19, 2015.
  • New, High Efficiency Boilers at Laning ES will be completed approximately October 9, 2015.
  • Upgraded Boiler Burner Controls at 5 schools
  • Upgraded BMS at 5 schools
  • Vending and Computer Miser systems
  • Other ECM’s including steam trap replacement and building envelope improvements, etc.

39 of 41

Energy Saving Improvement Program

LANING AVE

40 of 41

Operating Budget Projects

Carpeting at Forest

  • Other Operating Budget Projects besides Forest are:
    • HBW science classroom renovation to begin December 2015 during school closing.

41 of 41

��Summary��

  • Masonry Repointing Project tentatively will be bid in January 2016.
  • Kitchen renovations will take place in summer of 2016. This is due to no bidders for the first bid that took place in May 2015. The second bid was not until the end of June 2015 which caused time constraints for the project to be completed in the summer of 2015.
  • All projects have an anticipated completion date of September 2016.
  • The Town’s Construction Official has been very cooperative in allowing work to progress unimpeded and work is progressing on all awarded projects although some delays have been experienced with regards to plan review for tennis courts and fields.
  • Long lead times on certain pieces of equipment will impact completion dates on certain HVAC components.
  • Given the diverse nature of the projects and the ability to implement certain aspects, completion dates for the various components will be spread across this 2 year period.
  • Various trades are cooperating to keep projects moving.