CEB 6 Grate Deflectors

Assembly Summary

Open Source Ecology Developer’s Manual

2 of 9

Before you begin

3 of 9

The grade deflectors are bolted to the grate and act as an extension of the hopper, funnelling earth into the hopper mouth.

It’s construction relies upon meticulous weldments, build-time ~.5 hr.

4 of 9

Welding Procedure

Clear work table.

Grind weld splatter off table if necessary.

To minimize warping, tack weld critical points in weld joint

Weld in 1-2” segments.

Order the welding so each wield are far apart from the previous weld, welding about 2%, then 5%... 10%... 20%... 50%... 100% at each spot.

5 of 9

Bill of Materials

x2

x1

GD1

GD3

Collect and Label all parts

Perforate metal tails and bend upwards with a hammer and flat surface

6 of 9

Secure Deflectors to the Grates with 3/4’’ Bolts

x2

Duration 20min

7 of 9

Grate Deflector Module