Background

2

On December 21, 2022, the MSBA Board of Directors voted to invite the Statement of Interest for the Salem High School into the Massachusetts School Building Authority Eligibility Period

Salem Public Schools

3 of 28

Why is the Project Needed?

  • Obsolete career and technical spaces
  • Antiquated academic learning spaces
  • Outdated security infrastructure
  • Ineffective and inefficient heating and cooling systems
  • Salem High is the biggest energy hog in the city

It is our turn now!

3

Salem Public Schools

4 of 28

MILESTONE SCHEDULE REVIEW

Vote to authorize submission of Preferred Schematic Report (PSR): June 18

5 of 28

MILESTONE SCHEDULE REVIEW

6 of 28

7 of 28

8 of 28

9 of 28

10 of 28

11 of 28

12 of 28

13 of 28

14 of 28

15 of 28

16 of 28

17 of 28

PRELIMINARY COST OVERVIEW

18 of 28

A “NO” VOTE MEANS …

  • $354M Project ($100M less)
  • No Shared Cost with MSBA (100% on City)
  • Projects Spread Out over 30 years or more
  • Cost of Escalation (assume 5% per annum)
  • Renovated Building, Code Compliant, Pedagogical Models Not Addressed, No Expanded CTE Programs, Modest Energy Improvements
  • Risk of Student Attrition

19 of 28

A “YES” VOTE MEANS …

  • $456M Project
  • Shared Cost with MSBA�(assume 50% for now, say $225M)
  • 30-year “Mortgage” Assumed by the City
  • Taxpayers Cover Payments through Property Tax Increase
  • New Building, Current Pedagogical Models, Expanded CTE and Arts Programs, Net Zero Energy, Expanded Athletic Fields

20 of 28

21 of 28

Update: Next Steps with Construction Manager at Risk Procurement (Chapter 149a)

June

June 18

Mid-July

Mid-August

August 21

Draft and submit an application for the use of Construction Manager at Risk delivery to the Office of the Inspector General (OIG)

Draft the CM at Risk Request for Qualifications (Step 1)

Present the CM at Risk Request for Qualifications to the HSBC

Advertise for Qualifications

Draft Request for Proposals (Step 2)

Review and Shortlist Applicants

Distribute Request for Proposal to shortlisted applicants

Interview and finalize selection (Step 3)

Integrate CM into the Team during month 2 of the 6-month Schematic Design phase