Proposal Development as Project Management�Planning, Partnerships, and Critical Paths to Successful Submission

H. Christopher Frey

August 2026

New Faculty Orientation Workshop

2 of 20

Learning Objectives

  • At the end of this session, participants should be able to:
    • Recognize common proposal components.
    • Identify proposal elements that require institutional review or approval.
    • Recognize activities that create critical-path constraints.
    • Estimate realistic lead times for common proposal activities.
    • Understand that sponsor deadlines are not the only deadlines.
    • Recognize risk factors that can lead to delayed or unsuccessful submission.

3 of 20

Illustrative Event Sequence for a Proposal

Research Security Training

COI/COC Disclosures

Read the RFP Very Carefully

Principal Investigator leads the proposal

Co-PIs

Limited Submission

SubAwards

Vendors

Sponsor Requirements

Cost Share?

Space/Facilities?

F&A Waiver?

PI Eligibility?

Dept Intake, Support & Review

College Review

Univ/AOR Review & Approval

Unusual Compliance Requirements

Unusual Terms & Conditions

Sponsor Submission

Submission Compliance and Challenges

Not all proposals have all of these elements, not all possible elements are shown here, and the sequencing could vary

4 of 20

Core Technical Elements of a Proposal

  • Core Technical Elements
    • Project Summary / Abstract
    • Project Description / Research Strategy / Narrative: background, hypotheses, methodology, and work plan
    • References Cited / Bibliography:
  • Personnel and Administrative Documents
    • Biographical Sketches.
    • Current and Pending Support.
    • Facilities, Equipment, and Other Resources.
  • Agency-Specific Compliance and Special Plans
    • Data Management and Sharing (DMS) Plan
    • Special Regulatory Approvals: human subjects, clinical trials, vertebrate animal welfare
    • Broader Impacts / Relevance Statements
  • Subaward Statement(s) of Work
  • Letters of Support

5 of 20

Core Budget and Terms and Conditions

  • Budget & Justification
    • Direct Costs
    • F&A / Overhead
    • Cost Share / Matching
    • Justification.
  • Strategic Partnerships (Public-Private & Industry)
    • Mechanisms: Specific tracks (e.g., NSF GOALI, SBIR/STTR) require formal industry collaboration and commercialization roadmaps.
    • Allocation of Rights: Mandatory pre-award agreement defining who owns what intellectual property before work begins.
  • Global & Legal Compliance (Security & Trade)
    • Research Security: Mandatory disclosure of all foreign affiliations, gifts, and talent programs (strict federal scrutiny).
    • Export Control (ITAR/EAR): Strict trade laws governing defense items and dual-use commercial tech.
    • Limiting terms and conditions (e.g., publication rights)

​

6 of 20

Pre-Award Roles and Responsibilities

  • Faculty: develop technical content, include scope that informs the budget, and identify key partnerships and other resource needs (e.g., equipment)
  • Departmental staff: assist in preparing budgets, budget justifications, coordination, routing support.
  • CoE’s Office of Research Administration (ORA): proposals are compliant with University, Federal, State, and sponsor policies. ORA cannot review a proposal until it is released by the department.
  • NC State’s office of Sponsored Programs and Regulatory Compliance Services (SPARCS) assists with proposals that require Terms, Conditions, and special negotiations.
  • Departments have the responsibility to submit accurate and timely proposals to meet deadlines.

​

7 of 20

Pre-Award Timeline

Planned COE 8/2 day policy

SPARCS 5/2 day policy

Business Days

to Deadline

8

7

6

5

4

3

2

1

8 Days: 

  • Ensuring PI-eligibility status for PIs and CoPIs and senior person eligibility status for senior persons, or securing an exception when required.
  • Ensuring compliance for all senior persons, such as the new Research Training requirement
  • Review the solicitation and sponsor communication. 
  • Address any compliance items, such as securing university-level approval for Organizational Conflict of Interest (OCOI), OTL approval for Background IP,  addressing Export Control items, SPARCS approval review of T&Cs, or securing a proposal-stage agreement like an IP Management Plan. 
  • Ensure the submission mechanism and who has the authority to submit, and ensure they have access
  • Confirming Limited Submission endorsement, when applicable.
  • Review and address the budget breakdown and justification for compliance.
  • Confirming F&A when less than the federally negotiated rate agreement, or securing the required waiver.
  • Confirming cost share requirements and commitments, in addition to securing appropriate documentation for the final proposal.

2 Days:

  • Review the final proposal to ensure it's compliant with the solicitation
  • Ensure final proposal is compliant with sponsor, university, state, & federal guidelines.
  • Review sponsor required forms and secure signatures.
  • Ensure no errors within the sponsor portal, when applicable.
  • Address any submission issues and resubmit it if necessary
  • Either the college submits the final proposal or works with SPARCS to ensure submission or endorsement.
  • Ensure PINS is complete, secure all approval levels, and the college approves PINS

8 of 20

The COE 8/2 Policy

  • Eight (8) full business days prior to the sponsor due date:
    • The minimum proposal record in PINS must be released to the College of Engineering by the Dept/Unit for review. It must contain:
      • RFP/FOA/NOFO
      • Budget spreadsheet – free of errors
      • Budget justification – free of errors
      • Cost share documentation (if applicable)
      • F&A considerations (if applicable)
      • Any representation or certification forms and other administrative documents that require College or university signatures or input
      • Subaward documents (if applicable)
  • Two (2) full business days prior to the sponsor due date:
    • The College must receive the final proposal with permission for the College/University AOR to sign/submit

​

​

9 of 20

Managing a Schedule: Some Concepts

  • Critical Path: The longest sequence of dependent tasks that decides the shortest total time to finish a project (actual time cannot be less than this)
  • Slack (Float): The amount of time a task can slip without delaying the project finish date.

10 of 20

What Often Requires Extra Lead Time?

  • Subawards
  • Cost Share
  • Reduced F&A
  • Equipment
  • Other facilities, space
  • Regulatory requirements (e.g., IRB, IACUC)
  • Industry sponsors
  • International collaborators
  • PI Eligibility
  • Limited submissions
  • Unusual sponsor terms

These items often require conversations outside your group.

11 of 20

Example: PI Eligibility

  • I want a postdoc, graduate student, or undergraduate student to be PI or Co-PI. Can I do that?:
    • Some positions are not automatically PI eligible
    • Requests require review and approval
    • COE endorsement is needed before university approval
    • Supporting documentation is required
    • Student approvals are generally limited to programs that specifically require that a student apply as the PI, such as specific fellowships
    • Requests should be submitted well before proposal deadlines (at least 12 business days before sponsor deadline)
    • Submit well enough in advance to give yourself time to pivot if you don’t get the answer you hoped for

​

12 of 20

Example: Cost Share

  • The university policy is generally to provide cost share only if required by the sponsor, at the minimum required level
    • For “small” cost share requirements, typically faculty academic year released time, and the associated fringe benefits and unrecovered F&A, can be counted
    • Startup funds may be eligible
    • Subawardees are generally expected to contribute to cost share
    • In-kind contributions from vendors may count if they are not standard academic discounts
    • Contributions can be sought from a department: consult dept. head
    • Contributions may be possible from the college, university: discuss well in advance with Associate Dean for Research (who expects all of the above)

The more complicated the cost share plan, the earlier the discussion should begin

13 of 20

Example: Facilities & Administrative Costs (F&A)

  • Standard federally negotiated rate.
  • Some sponsors have published caps that apply to all applicants for a given program or sponsor.
  • Published caps generally do not require special approval.
  • Reductions below allowable rates may require institutional review.
  • Industry and foreign sponsor situations often require additional scrutiny.

What is F&A

F&A costs consist of the construction and maintenance costs of laboratories and high-tech facilities; energy and utility expenses; and safety, security, and other government-mandated expenses. Research is impossible without the infrastructure investments that F&A costs create and sustain

14 of 20

Example: Subawards and Equipment

  • Subawards often require:
    • scope of work
    • budget
    • budget justification
    • institutional approvals
  • Equipment often requires:
    • Quote
    • Specifications
    • Justification
  • If you are a subawardee to a “direct” sponsor, they will ask for your input ahead of their deadline:
    • scope of work
    • budget
    • budget justification
    • institutional approvals
  • Your equipment cost needs to be part of your subaward budget when due to direct sponsor.
  • Originating and direct sponsor terms and conditions flow down to you

Direct Sponsor: source of funds to your subaward

Originating Sponsor: source of funds to the direct sponsor

Other organizations may not follow your timeline

15 of 20

The “80/20 rule”�The Complications are Usually in the Exceptions

  • While the “80/20” rule is really a heuristic and not an empirical rule, it is often demonstrated in the preaward process
  • Most proposals may be “straightforward”
  • However, the “edge cases” may have terms and conditions that require extra time and an institutional process for acceptance of limitations or risk. Examples:
    • Will you accept a publication restriction?
    • Will you and your students comply with a specific information security requirement?
    • Will you or the dept accept risk from currency fluctuations for international sponsors

16 of 20

Submission Systems

  • Submission systems may discover problems late:
    • Project description is allowed to be 15 pages with a specific font size, but submitted version has an extra line on page 16
    • Or, Current and Pending Support is missing key information
    • Or, an attestation is not checked
    • (and so on).
  • Submission systems may not be working:
    • Your proposal is not the only one being submitted at 5:00 pm EDT on a Friday afternoon.
    • Submission attempt at 3:47 pm
    • The system is down. Call wait times to the help desk are 2 hours.
    • The sponsor is not going to make an exception later

​

17 of 20

Most Proposal PreAward Problems Are Not Technical Problems

  • Proposal delays usually result from:
    • Missing approvals
    • Missing partner documents
    • Unresolved cost share
    • PI eligibility questions
    • Compliance issues
    • Sponsor-system validation errors

Not from writing the technical narrative (of course, the success of your proposal with the sponsor depends on the technical narrative and all of the other elements)

​

18 of 20

Three Rules for Success

  • Start earlier than you think you need to
  • Engage departmental and college staff support early
  • Recognize that unusual situations will need extra time.

19 of 20

Exercise: (for groups of 3-4)

Will this proposal make it out the door?

Scenario: Proposal is due in 30 days. It includes one subaward, one $150K equipment item, sponsor limits F&A to 20% for all proposals to a program for which the RFP is available online, and the sponsor requires 10% mandatory cost share.

Prompt: Who do you need to contact? What must be approved? What documentation is required? Which items should start immediately? Which activities are the critical path?

Your Answer: Please prepare a timeline that shows the key milestones/events for preparing this proposal.

20 of 20

Exercise: (for groups of 3-4)

Will this proposal make it out the door?

Surprise Events:

How does your answer change if any of the following “surprises” occur?

    • Surprise A: Your subaward colleague (PI at your subaward institution) just found out their university needs 10 business days to get institutional approval of their materials.
    • Surprise B: The key salesperson at the equipment vendor is working onsite on an emergency basis with a customer and will need another 7 days to get you a quote.
    • Surprise C: Actually, the cost share requirement is not mandatory, but the program manager would like for you to demonstrate 25% in voluntary cost share because they say reviewers will appreciate that. However, the RFP indicates that the technical review criteria do not include any budgetary considerations.