SAP Material Manageemnt

Message no. 06 207

PO Effective Price check to

Material Master MAP Price

2 of 19

Often time, the Purchase Requistion is registered with the estimated price from the material master accounting view AND when the PR is converted to PO, the PO price will either be entered manually or from the Purchasing Info Record. This presentation is show a tolerance check possible when the PO is created.

3 of 19

Setup of Price Variance for the PO creation by Company Code ...

Use Tolerance Key “PE”

4 of 19

Version 00 for for all Users

“W” Warning

Message

06207

5 of 19

Set by Amount or Percentage (or both), which ever reach, the tolerance considered exceeded !!

Lets use 10% upper tolerance !

6 of 19

Current MAP is $100.00

7 of 19

PR estimated price from MAP material master

8 of 19

MAP $100

Effective Price $116.40

> 10% (warning)

9 of 19

MAP $100

Effective Price $101.85

< 10% (no message)

10 of 19

ERROR

11 of 19

MAP $100

Effective Price $116.40

> 10% (error)

12 of 19

MAP $100

Effective Price $101.85

< 10% (no message)

13 of 19

Create USER specific

warning or error for message 06207

14 of 19

15 of 19

Assign parameter ID

MSV = Z2 to user 2

with “Error”

Assign parameter ID

MSV = Z1 to user 1

with “Warning”

16 of 19

User PLM300-20

assign with PID

MSV = Z1

warning case

17 of 19

MAP $100

Effective Price $116.40

> 10% (warning)

for user PLM300-20

18 of 19

User PLM300-10

assign with PID

MSV = Z2

error case

19 of 19

MAP $100

Effective Price $116.40

> 10% (error)