Presentation to Selectboard: Rates 101 and Kickoff Meeting

February 4, 2025 | Town of Brattleboro | Water and Sewer Rate Study

Mike Maker, Partner

Nick Short, Senior Consultant

2 of 16

Presentation Agenda

2

Challenges Facing Water and Sewer Utilities

Principles of Rate Setting

Rate Design: Fixed and Variable Charges

Brattleboro Water and Sewer Rate Study

NEWGEN STRATEGIES AND SOLUTIONS, LLC

3 of 16

State of the Industry / Challenges

3

AWWA State of the Water Industry 2024

  1. Watershed/source water protection
    • Increase system resilience
    • Protect drinking water supplies
  2. Financing for capital improvements
    • Federal (EPA, CWA, SDWA) and State (DEC, PUC, VDH, DWGPD) regulatory compliance (PFAS, lead pipes)
    • Pressure on rates and affordability
  3. Renewal and replacement of aging water infrastructure
    • Depreciation and deferred maintenance
    • Repair and replacement reserve for buried assets

S&P Outlook for Municipal Utilities 2024

NEWGEN STRATEGIES AND SOLUTIONS, LLC

4 of 16

MHI, CPI, and Water and Sewer Service Increases

4

From 2000 to 2023:

  • Median household income (MHI) increased 78% (2.6% per year)
  • Inflation (CPI) increased 71% (2.5% per year)
  • Water and sewer service costs increased 177% (4.7% per year)

Index: 2000 = 100; Bureau of Labor Statistics (BLS), Bureau of the Census

NEWGEN STRATEGIES AND SOLUTIONS, LLC

5 of 16

Basic Principles of Water and Sewer Rate Setting

5

  • Water and Sewer Systems Should Be Self-Sufficient
    • mitigate subsidies from the General Fund
    • customers pay costs of systems on basis of demand/usage

  • Objective is to Keep Rates and Fees Low Over Time
    • adequate maintenance funding to keep facilities in good condition to prolong useful life
    • adequate funding of reserves
    • rate and fee increases regularly, gradually, and smoothly

  • Someone Must Pay
    • most operating and capital costs are fixed
    • discounts/rebates for any group or class of customers means other customers must pay more

NEWGEN STRATEGIES AND SOLUTIONS, LLC

6 of 16

Rate Study Steps / Financial Model Table of Contents

6

NEWGEN STRATEGIES AND SOLUTIONS, LLC

7 of 16

Revenue Requirement

7

Operating and Maintenance

Expenses

Current Debt Service

Cash Funded Capital Projects

=

Annual

Revenue

Requirement

New Debt Service

Reserve Contributions

NEWGEN STRATEGIES AND SOLUTIONS, LLC

8 of 16

Rate Design – Pricing Utility Service

8

Discouraging Use

Ease of Understanding and Implementation

Economic Development

Affordability

Encouraging Use

Detail and Equity

Existing Service Area

Revenue Stability

Rate design is largely influenced by policy objectives of the utility

NEWGEN STRATEGIES AND SOLUTIONS, LLC

9 of 16

Rate Design – Fixed vs. Variable Costs

9

  • Trend of long-term water usage (and sewage generation) declines
    • Conservation policies
    • Installation of low-flow fixtures
    • Decline in average household size
    • Economic downturns
    • Increased efficiencies in the use of water by industries or the loss of major industries
  • Therefore, many utilities are establishing policies to recover more revenue from fixed charges

NEWGEN STRATEGIES AND SOLUTIONS, LLC

10 of 16

Fixed Rate Design – Common Charges

10

  • Billing (or Customer) Charge
    • Cost Basis: cost of metering, billing, collection, contract administration, and accounting costs related to serving the customer
    • Typically, charge per bill and does not vary by meter size

  • Service (or Meter Charge)
    • Cost Basis: costs that vary with meter size (meter testing, repairs, replacements)

  • Minimum Charge
    • Cost Basis: billing charge and/or service charge
    • May include usage allowance that may vary by meter size

  • Advantages and Disadvantages
    • The higher the fixed charge, the greater the revenue stability
    • The higher the fixed charge, the more expensive service is for smallest users

NEWGEN STRATEGIES AND SOLUTIONS, LLC

11 of 16

Rate Design – Common Variable Rate Designs

11

NEWGEN STRATEGIES AND SOLUTIONS, LLC

12 of 16

Factors/Assumptions Affecting Brattleboro’s Charges and Rates

  • Operating and maintenance expense changes
    • Majority of expenses escalated by 3.0%
  • Capital improvement plans
    • investment in the treatment, distribution, and collection systems
  • Debt service
    • existing and future debt
  • Customer changes
    • no change in water or sewer customers per year based on future growth expectations
  • Water usage and sewage generation changes
    • no change in water or sewer usage per year based on future growth expectations
  • Miscellaneous revenue changes
    • 0% increase per year
  • Reserve targets
    • minimum operating fund balance of 90 days (25%) of operating expenses
    • minimum capital reserve balance gradually built up to 2% of system value (50-year useful life) after 10 years

12

NEWGEN STRATEGIES AND SOLUTIONS, LLC

13 of 16

Current Rates and Charges (effective October 2024)

13

Water

Sewer

Quarterly Base Fee

Meter Size

5/8"

$40.78

$49.70

3/4"

$61.18

$74.56

1"

$101.96

$124.26

1.5"

$203.89

$248.51

2"

$326.23

$397.61

3"

$652.46

$795.23

4"

$1,121.44

$1,366.80

6"

$1,376.29

$1,677.44

8"

$2,079.74

$2,534.79

Quarterly Usage Charge

Per 100 cubic feet

$2.96

$6.84

Quarterly Unmetered Use Charge

Single Tenement or Trailer

$68.29

Each Additional

$68.29

Water

Annual Fire Line Charges

Connection Size

2"

$175.00

3"

$390.00

6"

$550.00

each additional 6"

$440.00

4"

$275.00

each additional 4"

$220.00

8"

$1,100.00

each additional 8"

$880.00

hydrant

$440.00

Water

Sewer

Miscellaneous Fees

Permit Violation

$500.00

Permit Waiver Fee

$250.00

Permit and Inspection Fee

$35.00

Illegal Connection Violation

$100.00

Illegal Connection Waiver

$50.00

Illegal Discharge Violation

$100.00

Illegal Discharge Waiver

$50.00

Connection Charge

$1,000.00

$1,000.00

Turn-On / Turn-Off Fee

$25.00

After Hours Trip Fee

$90.00

NEWGEN STRATEGIES AND SOLUTIONS, LLC

14 of 16

FY 2025 Combined Local Quarterly Bill Comparison

14

9,000 gallons of usage

NEWGEN STRATEGIES AND SOLUTIONS, LLC

15 of 16

Next Steps

      • Preliminary kickoff meeting with staff (January 9, 2025, Microsoft Teams)
      • Kickoff meeting with Selectboard (today, in person)
      • Status meeting to discuss revenue requirements with staff (TBD, Microsoft Teams)
      • Presentation of revenue requirements and preliminary required revenue adjustments (TBD, in person)
      • Status meeting to discuss preliminary findings with staff (TBD, Microsoft Teams)
      • Status meeting to discuss revised findings with staff, if needed (TBD, Microsoft Teams)
      • Presentation of the results of the study to the Selectboard (planned for Tuesday, April 15, 2025, in person)

15

NEWGEN STRATEGIES AND SOLUTIONS, LLC

16 of 16

QUESTIONS?