SAP Production Planning & Execution

Simulating Production Order

Dispatch in

the Graphical Display Planning Board

for Work Center with Shift

(Setup for Shift Sequence

and Leveling choices with

different Shift Dispatch Strategies combinations)

2 of 92

  1. Configuration of Shift Sequence and its setup in the Work Center.
  2. Check Material assigned with Production Version with Work Center (with 1 Shift).
  3. Production Orders and the run times.
  4. Graphical Leveling CM21 (setup screen for Leveling).
  5. Graphical Leveling CM21 (basic finite + forward direction)
  6. Graphical Leveling CM21 (basic finite + backward direction)
  7. Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  8. Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  9. Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  10. Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  11. Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  12. Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  13. Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

3 of 92

Shift Grouping is assigned to Work Center Capacity Header

Shift Sequence begins with the Shift Grouping for

defining

Shift Definitions for a Work Center

4 of 92

Define Shifts for a Work Center

Shift Grouping Z

5 of 92

Insert Interval

6 of 92

Note Shift Sequence “S2”

Shift Sequence is assigned with Shift Definitions

7 of 92

Day 1 is Monday with

Shift F-11 and S-11

8 of 92

Shift definitions defines the

Start-End time of a Shift

Note, the Break Schedule 002

which is 45 mintues

9 of 92

System automatically check the Shift-Definitions work time

06:00:00 to 14:00:00

to find what Break time in the Break Schedule is valid.

(in this case, Break time 1 & 2 will be used for F-11)

10 of 92

Break time 3 & 4 falls within the Start-End time of S-11, so this time is applied for the Shift automatically

11 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

12 of 92

Work Center WC0 is not assigned with any Shift Definition and uses the Capacity Header data as work times and break times

13 of 92

Work Center WC1

is

only assigned

with the F-11

Morning Shift

14 of 92

Work Center WC2

is

assigned

Shift F-11 and S-11

2 Shift

15 of 92

Work Center WC3

is

assigned

all 3 Shifts

16 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

17 of 92

Prod Version 0001

with Work Center WC1

with 1 Shift

18 of 92

Material FG

with Planned Order assigned to PV 0001

19 of 92

Work Center WC1

100 pcs /1 hours

20 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

21 of 92

use CM21 to Level the Planned Order to earliest date possible and Shift 1

22 of 92

Each Prod Order is 300pcs

Prod Time 3 Hours

23 of 92

Work Center WC1

is assigned with

Shift 1

06:00:00 to 14:00:00

8 hours

24 of 92

Set Scale

to “Daily Period Shift”

25 of 92

Select the Work Center and SWITCH on the Shift Calendar

26 of 92

Work Center WC1

is with

1 Shift

27 of 92

Set Dispatch Strategy for Shift Simulations (see next slides)

28 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

29 of 92

Basic

Finite + Forward Direction

30 of 92

Dispatch Order 1

(Finite + Forward Direction)

31 of 92

Order 1 Dispatch to beginning of Shift

32 of 92

Edit - Select Chart to select all Prod Orders and Dispatch

33 of 92

Hide Break Times to better view all Dispatched Operations to the Shift

34 of 92

Finite + Forward Direction

Orders Dispatch to start of current Shift but all Orders will Finite + Forward but Order can continue next shift

35 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

36 of 92

Basic

Finite + Backward Direction

37 of 92

Dispatch Order 1

(Finite + Backward Direction)

38 of 92

Order 1 Dispatch as the the Order Time and Finite - Backward Direction

39 of 92

Select an Order,

then

Edit - Select - Chart

(for Strategy

Finite - Forward Direction)

40 of 92

System Backward Direction until

Order cannot have Start Date in the Past

Last Planned Order in the list not possible to Dispatch due to will end up Start Date in the Past

check Planning LOG

41 of 92

System Backward Direction until

Order cannot have Start Date in the Past

42 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

43 of 92

Finite + Dispatch at Earliest Point in Time + Forward Direction

(Forward/Backward Direction is no longer relevant for this combination)

44 of 92

Dispatch

Finite + Earliest time + Forward Direction

45 of 92

Today

Next earliest date,

Shift tomorrow

beginning time

46 of 92

Dispatch the rest

47 of 92

From the first initial dispatch Order to the Earliest date, the rest of the Orders are Forward Scheduled from that order

48 of 92

Finite + Dispatch at Earliest Point in Time + Backward Direction

(Forward/Backward Direction is no longer relevant for this combination)

49 of 92

Dispatch 1st Prod Order

in this case

Finite + Dispatch Earliest + Backward

OR

Finite + Dispatch Earliest + Forward

will eb the SAME RESULTS

50 of 92

Dispatch the rest of the Prod Orders using

Finite + Dispatch Earliest + Backward

51 of 92

Dispatch the rest of the Prod Orders

Finite + Dispatch Earliest + Backward

OR

Finite + Dispatch Earliest + Forward

will eb the SAME RESULTS

52 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

53 of 92

Finite + Direction Forward

+ “Always adhere to period Split”

54 of 92

Dispatch the first Prod Order

55 of 92

Finite + Direction Forward

+ “Always adhere to period Split”

the first Prod Order Dispatched to the Beginning of the current Shift

56 of 92

Dispatch next 2 Prod Orders

57 of 92

Finite + Direction Forward

+ “Always adhere to period Split”

Each Prod Order starts beginning of Next Shift (result in One Order per Shift)

58 of 92

Dispatch the rest of the Orders

59 of 92

Finite + Direction Forward

+ “Always adhere to period Split”

Each Prod Order starts beginning of Next Shift (result in One Order per Shift)

60 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

61 of 92

Finite + Direction Backward

+ “Always adhere to period Split”

62 of 92

Finite + Direction Backward

+ “Always adhere to period Split”

Dispatch one Order

63 of 92

Finite + Direction Backward

+ “Always adhere to period Split”

Orders Dispatched backward from End Time of Each Shift

but only One Order per Shift

64 of 92

Finite + Direction Backward

+ “Always adhere to period Split”

Dispatch 3 more Orders

65 of 92

Remaining Order not able to Dispatch because Start Date cannot be in the Past

Finite + Direction Backward

+ “Always adhere to period Split”

Orders Dispatched backward from End Time of Each Shift

but only One Order per Shift

66 of 92

Remaining Order not able to Dispatch because Start Date cannot be in the Past

67 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

68 of 92

Finite + Direction Forward

+ “Operation completion in period Split

69 of 92

Finite + Direction Forward

+ “Operation completion in period Split”

..

Dispatch the first Order

70 of 92

Finite + Direction Forward

+ “Operation completion in period Split”

71 of 92

Finite + Direction Forward

+ “Operation completion in period Split”

..

Dispatch the rend of the Orders

72 of 92

Finite + Direction Forward

+ “Operation completion in period Split”

..

3rd Order cannot start of the same shift as Order 1 and 2 as an Order Dispatched must finish on the same shift

73 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

74 of 92

Finite + Direction Backward

+ “Operation completion in period Split”

75 of 92

Finite + Direction Backward

+ “Operation completion in period Split”

Dispatch the first Order

76 of 92

Finite + Direction Backward

+ “Operation completion in period Split”

the first Order Backward Direction from today

77 of 92

Finite + Direction Backward

+ “Operation completion in period Split”

Dispatch the rest of the Orders

78 of 92

Finite + Direction Backward

+ “Operation completion in period Split”

all Orders Backward Direction until the final orders not allowed start date in the Past (also all Orders must start and finish on the same shift)

79 of 92

Backward Scheduling, last 2 Orders cannot be in the Past

80 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

81 of 92

Finite + Direction Forward

+ “Start search in plan direction

+Split Shift by SHIFT

82 of 92

Finite + Direction Forward

+ “Start search in plan direction”

+ “Split Shift by “SHIFT

Dispatch Order 1

(note Order before dispatch

start and end on same shift)

83 of 92

Period Split is by “2” (Shift)

Operation time 10:41 - 14:00

The Operation should be Dispatched on 10:41

The system start search for remaining capacity forward direction at NEXT Shift (due to Period Split)

84 of 92

Finite + Direction Forward

+ “Start search in plan direction”

+Split Shift by HOUR

85 of 92

Finite + Direction Forward

+ “Start search in plan direction”

+ “Split Shift by “HOUR

Dispatch Order 1

(note Order before dispatch

start and end on same shift)

86 of 92

Period Split is by “2” (Shift)

Operation time 10:41 - 14:00

The Operation should be Dispatched on 10:41

The system start search for remaining capacity forward direction at NEXT HOUR (due to Period Split) .. .which is 11:00

Order Dispatched to Start at

11:00

87 of 92

Before Dispatch

Start time 10:41

Dispatched to

start at 11:00

(Start of the NEXT HOUR)

Before Dispatch

After Dispatch

Finite Scheduling

Forward Direction

Period Split “HOUR”

“Start search in plan.direct.” SET

88 of 92

now we dispatch the rest of the orders

with

Period Split “HOUR”

Start search in plan direction

Forward Direction

The next Order’s Operation time is 10:41 - 14:00, and so it will try to start next hour from 10:41 which is 11:00

(but at 11:00am, Order #1 was already dispatched for that time)

89 of 92

with Strategy:

Finite + Forward Direction

  • Period Split by HOUR
  • Start Search in Plan Direction

The next Order try to start next hour from its start time of 10:41 to 11:00am

BUT

11:00am slot already taken, so it has no choice but to schedule from end of the Order #1, the same goes for the rest of the Orders.

90 of 92

  • Configuration of Shift Sequence and its setup in the Work Center.
  • Check Material assigned with Production Version with Work Center (with 1 Shift).
  • Production Orders and the run times.
  • Graphical Leveling CM21 (setup screen for Leveling).
  • Graphical Leveling CM21 (basic finite + forward direction)
  • Graphical Leveling CM21 (basic finite + backward direction)
  • Graphical Leveling CM21 (basic finite + dispatch at earliest time + forward/backward direction)
  • Graphical Leveling CM21 (basic finite + forward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “always adhere to period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + backward direction + “operation completion in period split”)
  • Graphical Leveling CM21 (basic finite + forward direction + “start search in plan direction” + Shift Split by “Shift or Hour”)
  • Graphical Leveling CM21 (basic finite + forward direction + “WITHOUT start search in plan direction” + Shift Split by “Shift or Hour”)

91 of 92

Strategy:

Finite + Forward Direction

Period Split “3” HOUR

“WITHOUT Start Search in plan direction

Dispatch order 1

with dates

10:41 - 14:00

in this case

Order will be dispatched at 10:00

(beginning of the hour of the start time)

92 of 92

Before Dispatch

Start time 10:41

Dispatched to

start at 10:00

(Start of the HOUR)

Before Dispatch

After Dispatch

Finite Scheduling

Forward Direction

Period Split “HOUR”

“Start search in plan.direct.” NOT SET