NEW YORK-NEW JERSEY HARBOR AND TRIBUTARIES�COASTAL STORM RISK MANAGEMENT STUDY
Request for Additional Resources
New York District
December 2023
1
STUDY AREA
COASTAL STORM RISKS & DAMAGES
STUDY SCOPE
STUDY SCHEDULE
OVERVIEW
2
ALTERNATIVE 3B – THE TENTATIVELY SELECTED PLAN
63.0% Study Area at
Direct Risk Benefited
Feature Type | Approx. Miles |
Storm Surge Barriers | 2.2 |
Shoreline Based Measures | 50.6 |
Induced Flooding-Mitigation Features | 11.8 |
HFFRRF (not shown) | 18.7 |
Alternative | |
First Cost ($B): | $ 52.7 |
Total Present Value Cost ($B): | $ 76.2 |
Estimated Construction Duration (years): | 14 |
3
TENTATIVELY SELECTED PLAN FEATURES IN DETAIL
Note High Frequency Flood Risk Reduction Features behind Storm Surge Barriers
Black lines – Primary structural features approximately 15-25 ft. NAVD88
Purple lines – Structural induced flooding mitigation features also approx. 15-25 ft. NAVD 88
Red lines – High Frequency Flood Risk Reduction Features approximately 10 ft. NAVD88
4
TYPES OF NEPA ANALYSIS
�Level of Analysis & Numberof Reviews
Least
Most
TIER 1 – Consists of a broad-scale review of the Alternatives.
TIER 2 – Consists of subsequent more detailed reviews as the designs are further refined (during the preconstruction engineering and design phase).
5
ENVIRONMENTAL �JUSTICE
Defining Disadvantaged Communities (DAC):
below the federal poverty level
identify as minority
Environmental Burdens:
Additional Vulnerability
Factors Considered:
households
EJ and the TSP/Alternative 3B |
63% of census tracts in the Reduced Risk Areas meet the criteria for DAC |
63 census tracts in the construction footprint meet the criteria for DAC |
Virtually every feature of the Tentatively Selected Plan touches a DAC |
6
PUBLIC COMMENTS
2,767 comments received
Breakdown by Theme
Note: Some comments included more than one theme, so total percentage adds up to >100%
7
PUBLIC COMMENTS: MAIN THEMES
8
OVERVIEW OF RECENT BRIEFS
9
STUDY PLAN/SCOPE AT FIRST REQUEST FOR ADDITIONAL RESOURCES (OCTOBER 2018)
10
STUDY PLAN/SCOPE AT SECOND REQUEST FOR ADDITIONAL RESOURCES (APRIL 2021)
11
CURRENT APPROVED STUDY PLAN/SCOPE �(COURSE OF ACTION #1)
12
FUTURE PATH OF STUDY TO COMPLETION
Refine and Optimize Plan with Existing Approved Funding and Schedule and Proceed to Final Report?
(Course of Action #1 – No further additional resource requests)
3rd Request for Additional Resources
Expand Study Scope and Schedule to more fully address comments received
?
13
COURSES OF ACTION
Course of Action #1 – Complete the study under the currently approved schedule and budget
Course of Action #2 – Increased schedule, results in conceptual plan (framework) with no actionable items
Course of Action #3 – Increased schedule and budget, results in Comprehensive (Programmatic) Plan with no actionable items
Course of Action #4a – Increased schedule and budget, results in Comprehensive (Programmatic) Plan with limited small-scale actionable items
Course of Action #4b – Increased schedule and budget, results in Comprehensive (Programmatic) Plan with limited small-scale and large-scale actionable items
Course of Action #5 – Increased schedule and budget, results in Recommended Plan with all actionable items
14
COURSE OF ACTION #1 – COMPLETE THE STUDY UNDER THE CURRENTLY APPROVED SCHEDULE AND BUDGET
DESCRIPTION: Given unexpected impacts to the study schedule, complete study with remaining allocated DRSAA funding with Chief’s Report NLT 15 June 2024, with remaining DRSAA funding and one month for optimization following ADM.
OUTCOME: Study would result in a conceptual plan (framework) with no recommendations for construction authorization (actionable items). No further reports would be published.
PROS:
CONS:
OVERALL STUDY FUNDING: $19.4M – unchanged ($3.274 million remaining)
OVERALL STUDY SCHEDULE: 95 months – unchanged
DELIVERABLES:
15
COURSE OF ACTION #2 – CONCEPTUAL PLAN (FRAMEWORK) WITH NO ACTIONABLE ITEMS (INCREASED SCHEDULE ONLY)
DESCRIPTION: Recovers schedule to complete the study by adding time for past unplanned impacts to study execution (e.g., federal funding cessation in FY 20-21, extended public outreach with Draft Report, etc.).
OUTCOME: Study would result in a conceptual plan (framework) with no recommendations for construction authorization (actionable items). No plan components would have full environmental compliance. No further reports would be published.
PROS:
CONS:
OVERALL STUDY FUNDING: $19.4M – unchanged ($3.274 million remaining)
OVERALL STUDY SCHEDULE: 95 + 14 months = 9 years, 1 month
DELIVERABLES:
16
COURSE OF ACTION #3 - COMPREHENSIVE (PROGRAMMATIC) PLAN WITH NO ACTIONABLE ITEMS
DESCRIPTION: Extends schedule and funding beyond that in second request for additional resources to perform technical studies largely to address other resource agencies comments, particularly related to storm surge barrier effects.
OUTCOME: Study would result in a Comprehensive (Programmatic) Plan with no recommendations for construction authorization (actionable items). No plan components would have full environmental compliance. A final integrated programmatic feasibility report and Tier 1 EIS would be published.
PROS:
CONS:
OVERALL STUDY FUNDING: $19.4M + ~$7M = ~$26.4M
OVERALL STUDY SCHEDULE: 95 months + ~30 months = ~10 years, 5 months
DELIVERABLES:
17
COURSE OF ACTION #4A – COMPREHENSIVE (PROGRAMMATIC) PLAN WITH LIMITED SMALL-SCALE ACTIONABLE ITEMS
DESCRIPTION: Further extends schedule and funding beyond COA #3 to carry out technical studies and advance designs and environmental compliance on limited number of small-scale actionable items.
OUTCOME: Study would result in a Comprehensive (Programmatic) Plan with limited recommendations for construction authorization (small-scale actionable items). Full environmental Tier 1 compliance would be complete. A revised draft and final integrated programmatic feasibility report and Tier 1 EIS would be published. The draft report would undergo public review.
PROS:
CONS:
OVERALL STUDY FUNDING: $19.4M + ~$10M = ~$29.4M
OVERALL STUDY SCHEDULE: 95 + ~42 months = ~11.5 years
DELIVERABLES:
18
COURSE OF ACTION #4B – COMPREHENSIVE (PROGRAMMATIC) PLAN WITH LIMITED SMALL-SCALE AND LARGE-SCALE ACTIONABLE ITEMS
DESCRIPTION: Further extends schedule and funding beyond COA #4a to carry out technical studies and advance designs and environmental compliance on limited number of small-scale and large-scale actionable items.
OUTCOME: Study would result in a Comprehensive (Programmatic) Plan with limited recommendations for construction authorization (small-scale and large-scale actionable items). Full environmental Tier 1 compliance would be complete. A revised draft and final integrated programmatic feasibility report and Tier 1 EIS would be published. The draft report would undergo public review.
PROS:
CONS:
OVERALL STUDY FUNDING: $19.4M + ~$19.5M = ~$38.9M
OVERALL STUDY SCHEDULE: 95 months + ~48 months = ~12 years
DELIVERABLES:
19
COURSE OF ACTION #5 – COMPREHENSIVE (PROGRAMMATIC) PLAN WITH ALL ACTIONABLE ITEMS
DESCRIPTION: Substantial increase in study schedule and funding to make designs, costs and environmental analyses on all plan components fully environmentally compliant (i.e., traditional feasibility study with least risk).
OUTCOME: Study would result in a Recommended Plan with recommendations for construction authorization (all small-scale and large-scale actionable items). Full environmental Tier 1 compliance would be complete. A revised draft and final integrated programmatic feasibility report and Tier 1 EIS would be published. The draft report would undergo public review.
PROS:
CONS:
OVERALL STUDY FUNDING: $19.4M + ~$40-50M = ~$60-70M
OVERALL STUDY SCHEDULE: 95 + ~84 months = ~15 years
DELIVERABLES:
20
SUMMARY
Course of Action #1 - Complete Study under Currently Approved Budget and Schedule | Course of Action #2 Restore Study Schedule to that Planned at Second Request for Additional Resources | Course of Action #3 Additional Scope and Schedule with Technical Studies | Course of Action #4a Refine & Expand Study Scope with Revised Draft Report | Course of Action #4b – Refine & Expand Study Scope with Revised Draft Report 🠉Recommended🠉 | Course of Action #5 – Substantial Increase in Scope & Schedule |
+$0 / 0 months | +$0 / +14 months | +$7M / +2.5 years | +$10M / +3.5 years | +$19.5M / +4 years | +$40M+ / +7+ years |
TOTAL (Costs / Duration) |
|
|
These may include:
|
|
|
$19.4M / 7.9 years | $19.4M / 9 years | $26.4M / 10.4 years | $29.4M / 11.4 years | $38.9M / 11.9 years | $59.4M+ / 14.9+ years |
21
THE PROCESS
Draft Feasibility Report / Tier 1 EIS (September 2022)
Revised Draft Feasibility Report / Tier 1 EIS
-Same Comprehensive Plan (Alternative 3B)
-More Analysis(Modeling)
-TSP Refinements
-Enhanced public and agency engagement
Final Feasibility Report / Tier 1 EIS
-Tier 1 NEPA Complete
-Comprehensive Plan after HATS study complete
Chief’s Report
-Interim response to study authority
-includes construction recommendations for small-scale actionable items (TBD)
-Assume all separable “stand alone” features*
Engineering and Design Report, with multiple Tier 2 NEPA documents
Chief’s Report
-Recommending comprehensive plan
-Enabling continuation of the feasibility study into Tier 2 Analyses
-Authorization
-New phase of project (budgeted)
NOTE: "Stand alone" features must be shown to have independent utility (not dependent on other features of the comprehensive plan) and be economically justified (See also, slide 26).
22
RISKS FOR EACH COURSE OF ACTION
RISK FACTORS | Course of Action #1 - Complete Study under Currently Approved Budget and Schedule. | Course of Action #2 – Restore Study Scope to that Planned at Second Request for Additional Resources | Course of Action #3 – Additional Scope and Schedule with Technical Studies (No 2nd Draft) | Course of Action #4a – Refine & Expand Study Scope | Course of Action #4b – Refine & Expand Study Scope 🠉Recommended🠉 | Course of Action #5 – Substantial Increase in Scope & Schedule |
Stakeholder Support and Public Outreach | Insufficient | Insufficient | Partly Sufficient (No 2nd Draft) | Partly Responsive to stakeholder and public feedback | Responsive to stakeholder and public feedback | Responsive to stakeholder and public feedback |
Environmental Compliance | InsufficientA | InsufficientA | SufficientB | SufficientC | SufficientC | SufficientD |
Cost Risk: Class 3 Cost Estimate | Non-compliant | Non-compliant | Non-compliant | Compliance for Limited Actionable ItemsE | Compliance for All Actionable ItemsE | Full Compliance |
Actionable Items | No Actionable Items | No Actionable Items | No Actionable Items | Limited Small-Scale Items | Limited Small-Scale and Large-Scale Items | All Items |
Implementation | Doubtful | Doubtful | Possible | Phased | Phased | Delayed |
A NEPA incomplete
B NEPA (Tier 1) complete for Recommended Plan only. Requires additional NEPA (Tier 2) to be completed in future phases of Study for the Recommended Plan.
C NEPA (Tier 1) complete for Recommended Plan and either small-scale (COA 4a) or large-scale (COA 4b) actionable components. Requires additional NEPA (Tier 2).
D NEPA complete during Feasibility Phase (not utilizing a Tiered NEPA approach).
E Class 3 Cost Estimate requires coordination with Vertical Team. No site-specific geotechnical, hydrographic/topographic, or utility investigations are included in budget.
23
SCHEDULE (AS CURRENTLY APPROVED)
Action/Milestone | Date |
Execute Feasibility Cost-Sharing Agreement (study start) | ✅ 15 July 2016 |
ASA(CW) Approval of First Request for Additional Resources | ✅ 31 October 2018 |
Release Interim Report | ✅ 19 February 2019 |
Public Meetings for Interim Report | ✅ March - October 2019 |
Delay due to lack of Federal funding | ✅ February 2020 – September 2021 |
Senior Official Approval (Acting on behalf of ASA(CW)) of Second Request for Additional Resources | ✅ 7 April 2021 |
Federal funding resumption | ✅ October 2021 |
FCSA Amendment Execution | ✅ 28 June 2022 |
Tentatively Selected Plan Milestone | ✅ 26 July 2022 |
Release Draft Integrated Feasibility Report and Tier 1 EIS | ✅ Late September 2022 (175+ day review period) |
Public Meetings for Draft Report | ✅ October 2022 – March 2023 |
Public Comment Closing Date | ✅ March 31, 2023 |
Agency Decision Milestone | TBD in December 2023/January 2024 |
Submit Final Integrated Feasibility Report and Tier 1 EIS | January 2024* |
Chief of Engineer’s Report Approval (study end) | NLT 15 June 2024* |
* Currently scheduled/approved dates – likely to be rescheduled if/as anticipated third request for additional resources is approved.
24
QUESTIONS?
25
SLIDE 22 NOTE CONT'D: NEPA CONSIDERATION
What are connected actions and how do they relate to segmentation?
Connected actions are closely related and therefore should be discussed in the same impact statement. Actions are connected if they:
(i) Automatically trigger other actions which may require environmental impact statements.
(ii) Cannot or will not proceed unless other actions are taken previously or simultaneously.
(iii) Are interdependent parts of a larger action and depend on the larger action for their justification.
State why the proposed project(s) can stand on its own without the implementation of other CSRM improvements (e.g., the project(s) provides CSRM to the affected shorelines by adding these structures which satisfies the project's need, and this would be true even if no other CSRM measures were built nearby).
Explain why the proposed project is not an irretrievable commitment of federal funds - this may be as simple as stating that, because the project stands alone, it cannot and does not irretrievably commit federal funds.
State why the proposed project would not restrict the consideration of alternatives for other CSRM measures, i.e., if the project has independent utility no future alternatives would be dictated or restricted.
26