SAP Procurement Processes
in S/4 HANA
Service Contract with Outline �Service Master - Service Contract
MM only
PR to PO to SES steps
Create new Service Master
Activity number = Service Master
also enter
4 Service Masters created
S1, S2, S3, S4 for this demo
Create a Value-Based Contract using Doc Type “WK” for
External Services
Mandatory fields�Validity period
Target Value
Item Category “D” for External Services
It is possible to assign Account Assignment “U” (Unknown) in the Contract and decide the Account Assignment in the PR or via PM/PS Network Order or Maintenance Order
Minimum required entry is the Material Group and Short Text
and press ENTER
to create Outline for Service Masters, click this ICON
Right click the TOP folder, and select “New Subgroup”
Enter Outline Level and a Short Text for “Stage 1”
Enter Service Masters S1, S2
with Contract Quantity, Contract Price
for
Outline Stage 1
To create Level 2, Right click the TOP folder again, and select “New Subgroup”
Enter Outline Level and a Short Text for “Stage 2”
Enter Service Masters S3, S4
with Contract Quantity, Contract Price
for
Outline Stage 2
SAVE the Service Contract
Service Contract created
In the PR for Services, enter Account Assignment “K” (for Cost Enter,
Item Category “D” (for External Services),
Short Text,
Material Group,
Plant,
Purchasing Group
Account Assignment is not entered in this TAB, but shortly in the “Services” TAB
In the “Source of Supply” TAB, enter the Service Contract and Item here
In the “Services” TAB, select Service Selection to get to the Service Contract assigned
The Service Contract is defaulted from the “Source of Supply” TAB
In this example, we shall select Service Masters from the Stage 1 Outline
Enter Cost Center for Service Master S1 and click “Repart AA on” for S2
Cost Center repeated auto filled for Service Master S2
PR for Service Master with reference to Service Contract created
Note the Service PR and Service Contract
Service S1 1hour x $10
Service S2 1hour x $20
SAVE
Service PO created
Check the PO Released here
Total Released Value to-date
Get the Service PO
Enter the Service PO and click Continue
Get Services rendered from he Service PO
Since ALL services done, select both and click COPY
Immediately approval in this example
Service Entry Sheet (SES) and Save to create Material Document
the SES and the Material Document (generated when SES is approved)