SAP Procurement Processes
in S/4 HANA
Purchase Order Doc Type “FO”
Framework Order
for Consumable Scenario
(“Periodic” Invoicing Plan)
Field Selection for PO Doc Type “FOF” is unique (Header Validity Start is Mandatory)
Check Allowed Item Categories for PO Doc Type “FO”
Not the Doc Type “FO” can be applied with Item Category “B” or “D” (In this example will use “B” Limit Scenario)
Check
Link PR to
the PO
This is PR Doc Type “FO”” with Item Category “B”
Meaning
PR Doc Type
“FO” + Item Category “B”
can be
converted to
PO Doc Type
“FO” + Item Category “B”
In this SPRO step, let’s check the Configuration of the Field Selection “FOF”
In this SPRO step, let’s check the Configuration of the Field Selection “FOF”
Note “Start of Validity period” is Mandatory
Check Account Assignment “K” and “U”
Note Cost Center is Mandatory
Account Modification is use to determine to G/L in the PO
GR is not allowed for Invoicing Plant but since A/A “K” can be used for GR-based Consumable PO, we will uncheck this indicator in the PO instead and not here
This will default the selection of the “IR” indicator in the PO
Create a new Cost Center “ZCC2” for Controlling Area “A000”
Enter Appropriate CO data for the new Cost Center
Create a new G/L Account 66999999 for Expenses
The new G/L 66999999
is a P&L account Hence it is also a Primary Cost Element
In this example,
the Controlling Area “A000” is assigned with
Company Code “1010”
Chart of Accounts “YCOA” is from the Company Code “1010”
Create a new Material Group “ZMG1”
Create a new Valuation Class “ZVC1”
Assign
Valuation Class “ZVC1” to
Material Group “ZMG1”
Influencing Factor 1
Plant = Valuation Area = 1010 is assigned to
Valuation Grouping Code (VGC) “0001”
Influencing Factor 2
Account Assignment “K” is assigned with Account Modification “VBR”
Influencing Factor 3
Valuation Class “ZVC1” is assigned to Material Group “ZMG1”
Assign the new G/L “66999999”
to Trax Event Key “GBB”
using the 3 influencing factors (previous 3 slides)
Double click
Trx Event Key “GBB”
use Chart of Accounts “YCOA” the the Company Code “1010” where the G/L “66999999” was created
Assign the G/L “66999999”
Influencing Factor 2
Account Assignment “K” is assigned with Account Modification “VBR”
Influencing Factor 3
Valuation Class “ZVC1” is assigned to Material Group “ZMG1”
Influencing Factor 1
Plant = Valuation Area = 1010 is assigned to
Valuation Grouping Code (VGC) “0001”
New Entries
to create
assignment of Cost Center “ZCC1” to
the Primary Cost Element (G/L) “66999999”
Assign Cost Center “ZCC2” to
the Primary Cost Element (G/L) “66999999”
Invoicing Plan PO will be using Invoice Settlement via MRIS and the “ERS” setting is a Prerequisite
GR-Based Invoice indicator if selected will have to be deselected in the PO (GR-Based IV is for Classic ERS)
Invoicing Plan Types and its related configuration are done here
Invoicing Plan Types for Partial Inv.Plan are simpler; here, we create new Inv.Plan type “ZZ” for Periodic Inv.Plan
The Date Determine Rules are the basis of how the Inv.Plan dates will be generated in the Inv.Plan PO
“X” means Deadlines in the Periodic Invoicing Plan Invoice due schedule will be generated Automatically
Use Standard SAP
Date Category “T1” for Partial Inv.Plan
Date Category “P1” for Periodic Inv. Plan
The descriptions are merely to differentiate between the invoicing dates and have no control character.
This configuration defines Dates Rules for the Date Determination
Duration of the Invoicing Plan due dates (our case will be monthly therefore 12 periods will be generated)
Start and End Dates
For Invoicing Plan
Enter in the PO Header
For Invoicing Plan
Enter in the PO Item level
un-check the “GR” indicator and it is not allowed for the Invoicing Plan Scenario
G/L Account was determined via
OBYC
Cost Center was determined via OKB9
GR-Based IV is defaulted from the BP (but not allowed for Invoice Plan Scenario)
Auto Invoice scenario requires a Tax Code
Deselect the GR-Based IV indicator, click the “Invoicing Plant” button and select “ZZ” Period Invoicing Plan Type and click CONTINUE
Back and SAVE
Invoicing Plan PO created
First, run “Test Run” mode to check Postable Invoicing Plan Schedules
Today is 19.11.2023 and therefore this Item is Postable
Uncheck the Test Run to now generated the Invoice
SAP Internal Invoice Document
Accounting Document
check any updates in the “Invoicing Plan” details
01.11.2023
Scheduled Payment due today 19.11.2023 now with Status
“C” (Invoiced)
SAP Internal Invoice Document
Debit Expenses
Credit Down Payments
Cost Center charged