1 of 49

SIEMENS BIC 2021

GROUP 2 PROJECT

2 of 49

1. VISION

Maintaining a clean environment and obtaining maximum efficiency by using RENEWABLES

Reaching:

  • Decarbonization
  • Decentralization
  • Digitalization

2x electricity consumption by 2050

>50% renewable annual energy

82% households have smart meters in 2050

3 of 49

I am FREE to use everything the way I like!!

4 of 49

5 of 49

2. OBJECTIVE

Home is not just the building we live in, it is the whole planet with its streets, forests and deserts.

This is why it is not to be used temporarily for several years but for us and all the future generations, used with absolute care and attention.

6 of 49

3. PROJECT: A 48 MW INDUSTRIAL PARK

  • Location: At Suez
  • Consists of:

- 6 plants 40 MW total

- Services (lightings, Siharbor, gas stations…etc) 8 MW

  • This presentation contains 2 major topics:

3.1: HV S/S

3.2: Microgrid

7 of 49

3.1: HV S/S

  • Design digital substation 4.0 the future of grid IEC61850 known for: availability, efficiency and sustainability of the grid
  • Digitalization in substations means increased operational efficiency through use of new technologies, methods and processes delivering benefits around investment and operating costs
  • Components and protocol of digital substation 4.0: - Siprotec 5 protection relay - substation controller - HMI and SCADA system - IoT/IoE and cloud

8 of 49

9 of 49

3.1.1: HV PART

HV

Circuit Breaker

7 CB 220 kV

Transformer

2 transformers 50 MVA

(220/66 kV)

10 of 49

3.1.2: MV PART

MV

Switchgears

2 Distributers

1 to 5 and 10 to 14: Outgoings

6 to 9:

2 incomings

1 bus coupler

1 bus riser

2 Panels

26 CB

4 Transformers 25MVA (66/22 kV)

11 of 49

MV ILLUSTRATION

12 of 49

3.1.2.1: DISTRIBUTERS

1st Distributer:

  • LOOP (1): 6MW for factory(1): Divided into four ring main units , 1.5 MW each, rating: Dry Type transformer of RMU : 1.6 MVA, 1.44 MW
  • LOOP (2) 6MW for factory(2): Same as loop (1)
  • LOOP (3) 4MW for factory (3):
  • Divided into two ring main units, 1.5 MW each, rating transformer: 1.6 MVA, 1.44MW

+ 1 RMU: consumes 1 MW with rating transformer: 1 MVA, 0.9 MW

+ 2MW for Services: Divided into two ring main units, 1 MW each with rating transformer: 1 MVA, 0.9 MW

  • LOOP (4) 4MW for factory (4): same as (loop 3)

13 of 49

2nd Distributer:

  • LOOP (1) 5MW for factory (5) part 1:
  • Divided into two ring main units :each RMU consumes 1.5 MW, rating transformer: 1.6 MVA

+ two ring main units: each RMU consumes 1 MW, rating transformer: 1 MVA

+ 1MW for Services:1 RMU consumes 1 MW with rating transformer: 1 MVA

  • LOOP (2) 5MW for factory(5) part 2: same as loop (1)
  • LOOP (3) 5MW for factory (6) part 1
  • Divided into two ring main units :each RMU consumes 1.5 MW rating transformer: 1.6 MVA

+ two ring main units: each RMU consumes 1 MW with rating transformer: 1 MVA

+ 1MW for Services 1 RMU consumes 1 MW with rating transformer: 1 MVA

  • LOOP (4) 5MW for factory(6) part 2 same as loop (3)

14 of 49

NOTES:

  • Total 44 CB and 44 transformers in the HV S/S
  • Max. rating for distributer )22KV( : 30MVA, but the Egyptian Electricity Company stipulated that the max. rating is 28 MVA + 2MVA as spare .
  • Max. rating for any loop 7MVA (6.3MW) if PF=0.9
  • Max. length to loop :7.5 Km
  • Medium switchgear distributor is placed at the middle of the loads
  • There is a cell as spare & cell to feed the auxiliary transformer
  • We assumed that PF=0.9 , Diversity factor=0.9
  • Transformer load capacity :100%
  • Rating of the incoming & bus coupler CB :1250 A VACUUM
  • Rating of the outgoing CB :630 A VACUUM

15 of 49

3.1.3: TRANSFORMERS

Protection devices:

Components of protection devices:

1.CT

2.VT

3.circuit breaker

4.batteries

5.communication channel

16 of 49

Siprotec 5:

  • Device: 7SA87 Distance Prot. 1-/3-p.
  • Product code
  • Short: P1A139463
  • Long: 7SA87-DAAA-AA0-0AAAA0-AN0111-12111B-BAA000-000AC0-CB1BA1-CE0
  • Firmware: Current version
  • Housing width: 1/2 x 19''
  • Housing type: Flush mounting
  • Binary inputs: 23
  • Binary outputs: 25 Relays (19 Standard, 6 Fast, 0 High-Speed, 0 Power)
  • Current transformers: 4 for protection
  • Voltage transformers: 4 standard

17 of 49

  • Measuring-transducer inputs: 0 (20 mA or 10 V, fast)
  • 0 (20 mA, standard)
  • Modules in 19" row 1: IO202 , PS201 , IO205
  • Modules in 19" row 2:
  • LEDs/Push-buttons: 16 LEDs
  • Operation Panel: Integrated
  • Key switch: Without
  • Display type: Small display
  • Front Design: Standard
  • Power Supply: DC 60 V-250 V, AC 100 V-230 V
  • Redundant Power Supply: No

18 of 49

3.1.4: SUBSTATION CABLES (LINE DIFFERENTIAL PROTECTION)

Transformer:

Rated less than 0.5 MVA protection is High voltage fuse

Rated above 0.5 MVA (Buchholz relay )

For rated above 5MVA ( diff protection

Relay siprotec5 7UT8 )

Depending upon the normal service condition, nature of transformer faults, degree of sustained over load, scheme of tap changing, and many other factors, the suitable transformer protection schemes are chosen

19 of 49

3.2: MICROGRID

  • The Micro grid will be able to supply approximately 47% of the total power at maximum rating
  • The micro grid consists of:

- 3.2.1: PV cells

  • 3.2.2: Wind turbines
  • 3.2.3: Battery storage systems
  • 3.2.4: Diesel Generators
  • 3.2.5: EV chargers

20 of 49

MICROGRID BOQ:

Serial Number

Name of Item

Quantity

1

PV

18630

2

Wind Turbines

5

3

Inverters

5

4

EV chargers

8

5

Battery Energy Storage System

19

6

Transformer

1

7

Diesel Generators

2

21 of 49

3.2.1: PV CELLS

  • System Power = 6.4 MW DC
  • System Power = 5.56 MW AC
  • No. of Inverters = 5.56 MW/ 1390KW = 4 Inverters
  • No. of Modules = 6.4 MW/ 345 W = 18630 Modules

22 of 49

3.2.1.1: SUNTECH MODULE CHARACTERISTICS

  • Rated Power 345W
  • Current at Pmax = 9.11 A
  • Voltage at Pmax = 37.9 V
  • S.C Current = 9.61 A
  • O.C Voltage = 46.6 V
  • Nominal Temp = 45 °C
  • Dimensions = 1960mm*992 mm*40 mm (Length / Width / Thickness)
  • Maximum System Voltage = 1500V

23 of 49

3.2.1.2: INVERTER CHARACTERISTICS

  • Manufacturer: Power Electronics – FreeSun
  • Operating Voltage = 565 V – 820 V
  • Nominal MPP Voltage = 635 V
  • Unit Nominal Power = 1390 KW AC
  • PF = 0.9
  • ηInv = 97.56%
  • Panel Protection: IP54

24 of 49

3.2.1.3: SYSTEM SIZING

  • No. of Modules = 6.4 MW/ 345 W = 18630 Module
  • No. of Modules in series = 18 Module
  • No. of strings in parallel= 1031 String
  • System Voltage = 18 * 37.9 = 682.2 V
  • No. of Trackers = 345 Tracker (Nextracker Tracking System)
  • No. of Junction Box = 45 JB
  • No. of Inverters = 5.56 MW/ 1390KW = 4 Inverters
  • Total Power of 4 Inverters = 4*1390 KW = 5560 KW AC
  • ηPV Module = 17.7%
  • ηInv = 97.56%
  • ηCables = 98%
  • PV Park Area = 36000 m2

25 of 49

3.2.1.4: PVSYST DESIGN

26 of 49

27 of 49

28 of 49

29 of 49

3.2.1.5: MODULE WIRING

30 of 49

Communication System

  • SPC (Self Power Controller)
  • NCU (Network Communication Unit)
  • 8 NCU: 2 NCU for each Inverter
  • MC (Monitor Cabinet): 1 MC
  • SCADA System

Measurements

  • 1 weather station to measure:
  • Ambient Temp
  • Humidity
  • Irradiance
  • Wind Speed
  • Wind Direction
  • Module Temp

31 of 49

NOTES:

  • Modules Connections (Leapfrog Wiring).
  • Spacing between Strings is 5 m to avoid no shading.
  • 7111 tons of CO2 avoided per year.

32 of 49

3.2.2: WIND TURBINES

  • Manufacturer: GOLDWIND
  • Power Rating: 2.5 MW
  • No. of Wind Turbines = 2.5 * 5 = 12.5 MW
  • Total power rating = 2.5 * 3 + 2.5 * 2 * .9 ‘Wake Effect’ = 12 MW
  • Technology: PMDD (Permanent Magnet Direct Drive)
  • IEC Standard: IEC 61400 IEC 1A
  • Hub Height: 70 m – 80 m

33 of 49

  • Rated Wind Speed = 12 m/s
  • Cut in Speed = 3 m/s
  • Cut out Speed = 25 m/s (10 min Avg)
  • Rotor Diameter = 90 m
  • Swept Area = 6362 m2
  • Speed Range = 7 – 16 rpm
  • Rated Voltage = 690 V AC

34 of 49

  • Transformer 690V/ 22KV
  • Dry Transformer on the top of the turbine for 2 reasons:
  • Less maintenance
  • Going down with smaller cross-sectional area

35 of 49

36 of 49

Note:

Wake Effect

37 of 49

3.2.3: BATTERY ENERGY STORAGE SYSTEM(BESS):

  •  

38 of 49

3.2.4: DIESEL GENERATORS

  • Number of diesel Generators = 2
  • 1.2 MW each
  • Total Power rating = 1.2 MW * 2 = 2.4 MW

39 of 49

3.2.5: EV CHARGERS

  • Total number of EV chargers = 8

1- 2 versi charger (AC)

Power rated 22 kw

Charging time : some hours

Applications :car parks and home installation

2- 2 sicharge cc AC 22

Power rated : 2 * 22 kw

Charging time : some hours

Applications : public Parking

40 of 49

3- 2 sicharge D (dc fast charging)

Power rated: 160 kw up to 300 kw

Charging time : 30 min

Applications : travelling roads

4- 2 sicharge uc (dc ) ultra fast charging

Power rated :from 125 kw to 800 kw

Charging time : 150 min

Applications : buses

Number of EVs = 8 ( 2 evs from each type )

Total load (2*22 kw+2*2*22kw+2*200kw +2*500kw)=632 kw

41 of 49

MICROGRID CONTROLLERS

  • SICAM AK 3
  • SICAM A8000 Series

42 of 49

43 of 49

REFERENCES

44 of 49

45 of 49

46 of 49

Software used:

  • AutoCAD
  • PVsyst
  • SIPROTEC 5 Configurator

47 of 49

48 of 49

CONTACTS

  • Mohamed Tawheed

https://www.linkedin.com/in/mohamedtawheed

19p4083@eng.asu.edu.eg

01200595924

  • Ahmed Talaat

https://www.linkedin.com/in/ahmed-talaat-1165111a5 ahmedtalaatqu500@gmail.com

01272355369

49 of 49

  • Mohamed Barakat Masoud

01025401402

Mohamed.Barakat55@yahoo.com

linkedin.com/in/mohamed-barakat-033403176

  • Mirette wagdy sabry

mirettewagdy98@gmail.com

01289340284

https://www.linkedin.com/in/mirette-wagdy-0b904b205

  • Andriette Essam

01273199066

andriette.essam@gmail.com

https://www.linkedin.com/in/andriette-essam-b753421a2/