1 of 11

BOARD OF EDUCATION

CONSTRUCTION UPDATE

April 13, 2026

2 of 11

KEARNEY HIGH SCHOOL

  • Project is on budget and on schedule
  • Sage Glass is complete including Owner training
  • Wall pads mostly complete
  • Flooring in progress
  • Lighting control wiring complete
  • Mirrors in ROTC/Dance room complete
  • Grading for turf installation complete
  • Turf install planned to begin this week
  • Expected Completion – July 2026

3 of 11

KEARNEY HIGH SCHOOL

4 of 11

KEARNEY HIGH SCHOOL

5 of 11

KEARNEY HIGH SCHOOL

6 of 11

CENTRAL UPDATE

  • Project is on budget and on schedule
  • Existing corridor flooring to be replaced this summer
    • Flooring demo and asbestos abatement to begin the week of May 25
    • New flooring installation to follow
    • Completion expected mid-July 2026

7 of 11

COTTONWOOD

  • Project is on budget and on schedule
  • State fire marshal inspection above ceiling complete
  • Casework installation complete
  • 1st coat paint complete
  • Flooring in progress
  • Soffit removal and replacement to begin in next couple of weeks
  • Completion expected end of June 2026

8 of 11

COTTONWOOD

9 of 11

COTTONWOOD

10 of 11

COTTONWOOD

11 of 11

THANK YOU!

QUESTIONS?