From "how long is a piece of string?" to proper project planning
Solving the e-learning costing conundrum�Tamsyn Smith & James Allen, University of Southampton
23/10/25
The impossible request:�
What we don't know...
Scope and complexity
Learning outcomes
Target audience
Platform requirements
Media needs
Compliance requirements
Timeline expectations
"Can you give me a quote for some e-learning? I need it for a research proposal deadline on Friday."
2
Beyond monetary costing: Why systematic scoping matters
Appropriate resource allocation
Realistic timeline estimation
Stakeholder expectation management
Quality assurance
Different institutional contexts, same challenge:
3
Building on research: Evidence-based time allocation
Chapman Alliance (2010): Industry benchmark study
Our framework: Three tiers for healthcare/HE context
4
What transforms "simple" projects into complex ones
Scenario-based learning
Compliance requirements
Subject matter expert involvement
5
5
From vague requests to defined projects: 20 essential questions
Resources and risk (Questions 14–20)
Timeline, SME availability, budget
Risk assessment and quality assurance
Compliance and delivery (Questions 8–13)
Regulatory requirements and accessibility
Platform selection and media specifications
Learning design (Questions 3–7)
Learning outcomes and instructional strategy
Content complexity and structure
Scenario and assessment requirements
Project fundamentals (Questions 1–2)
Purpose, audience, strategic alignment
Stakeholder management and governance
6
Calculator structure: From inputs to insights
7
7
Live demonstration: The systematic questioning in action
Key features:
8
8
Behind the scenes: Evidence-based calculations
What the calculator reveals:
9
9
Stakeholder-ready output: The Cost Breakdown sheet
Clear visualisation of:
Breakdown by category:
10
10
Before and after: How the calculator transforms conversations
Before the calculator
Vague requests with unrealistic expectations
Time estimates pulled from thin air
Scope creep during development
Frustrated stakeholders and overworked teams
Projects that don't deliver quality
After the calculator
Systematic discovery of true requirements
Evidence-based, defensible estimates
Clear understanding of trade-offs
Informed scope decisions
Realistic timelines and resource allocation
Early pilot results:
Improved accuracy of project scoping
Better stakeholder understanding of complexity
Reduced scope creep
More realistic timeline expectations
Higher confidence in delivery
11
Your expertise: What would make this work in your context?
1. What would you need to ask that we haven't included? Are there essential scoping questions we've missed?
3. Where do you lack reliable data for estimation? We've based our framework on Chapman, ATD, Moore, and our own experience, but are there areas where you simply don't have good benchmark data? This might be where we could collaborate as a sector
2. What institutional factors are critical in your setting that might not be as important in ours? For example, if you work in FE rather than HE, or in commercial training rather than public sector, what changes?
4. How would you need to adapt this approach for your context? Would you need different tiers? Different multipliers? Different outputs?
12
One framework, multiple applications
13
13
Limitations and honest reflections
Current limitations:
Ongoing development
What we still need:
14
Making this work available to the sector
1
CURRENT STATUS:
Piloting internally across multiple projects
Refining based on real-world use
Documenting implementation guidance
2
PLANNED RELEASE:
WordPress site with downloadable calculator
Full documentation and user guide
Question set openly licensed (CC BY-SA)
Video tutorials for implementation
Target: summer 2026
3
WHAT YOU'LL BE ABLE TO ACCESS:
Excel calculator (modifiable for your context)
Complete question framework
Lookup tables with evidence sources
Implementation guidance
4
COMMUNITY DEVELOPMENT:
Seeking feedback from early adopters
Open to collaborative improvement
Potential for sector-wide benchmarking initiative
15
Getting started with systematic scoping
You don't need the full calculator to start:
Minimum viable approach:
Use the '20 question' framework for scoping conversations
Start tracking actual project time honestly
Compare estimates vs actuals systematically
Build your own evidence base over time
Building institutional buy-in:
Start with one willing stakeholder
Document the improved outcome
Share success stories internally
Gradually expand adoption
Critical success factors:
Senior leadership support for realistic timelines
Willingness to have honest conversations
Commitment to tracking actuals vs estimates
Culture that values quality over speed
Quick wins:
Better scoping conversations immediately
Reduced scope creep
More realistic stakeholder expectations
Improved team morale
16
Beyond project costing: Broader professional implications
For learning technologists:
For the sector:
For stakeholders:
For learners:
17
Key takeaways
1. Systematic questioning transforms vague requests into defined projects
3. Transparency improves rather than complicates relationships
2. Evidence-based estimation is possible and valuable
4. Start simple and build over time
18
Resources and further reading
Key research cited:
Request access to the beta calculator:
19
19
Thank you
Contact:
20
20
University of Southampton
Detailed time breakdown by development phase
22
Platform comparison matrix
23
Assessment sophistication continuum
24
Compliance requirements detail
25
SME involvement model
26
Post-presentation actions
27