Action to be Completed | Proposed Date |
Board approves the submission to the NJDOE for all project approvals | COMPLETED - June 21. 2022 |
LRFP Board approval and submission to DOE for approval | COMPLETED - June 21, 2022 |
Referendum Committee recommends breakdown of questions | COMPLETED - December 2022 |
DOE project approval received | PARTIALLY COMPLETE |
Select PR firm to assist/manage communication strategy and develop community education resources | March 2023 for April BOE Agenda |
Public release of referendum proposal details and execution of strategy | TBD |
Provide notice to DOE for special election (60 days prior) | June, 2022 (or sooner) |
Referendum questions submitted to county (at least 19 days prior to vote) | July, 2023 (or sooner) |
Madison Referendum Vote | September, 2023 (tentative) |
Timeline
Question Structure Feedback Analysis
Proposed Referendum Costs
Question | Question Cost | Total Potential Cost |
Question 1 | $48,356,638 | $48,356,638 |
Question 2 | $12,876,550 | $61,233,188 (Q1 & Q2) |
Question 3 | $18,311,703 | $79,544,891 (Q1, Q2, & Q3) |
Current progress
2021-22 and 2022-23 Projects
MHS Ventilation Project ($2,367K)
CAS Partial Roof Replacement ($1,056K)
MHS Chairlift ($87K)
2023-24 Projects (Proposed)
ROD Grant submissions:
Additional Projects:
$6.98M in referendum projects have already been addressed
Questions?
Appendix
Proposed Referendum Costs
Approximate Referendum Cost | Estimated Annual Tax Increase | Estimated Monthly Amount |
Q1 $50,000,000 | $500 | $40 |
Q2 $60,000,000 | $600 | $50 |
Q3 $80,000,000 | $800 | $70 |
Central Avenue Addition Rendering