Boat Chart Work Plan -�Guidance and Template
Capability Building
1
Creative Commons Attribution-ShareAlike 3.0 Unported License - �you may use and share this file, but please attribute it to thepsc.co.uk
Creative Commons Attribution-ShareAlike 3.0 Unported License - �you may use and share this file, but please attribute it to thepsc.co.uk
2
Estimated Duration | X weeks | X weeks | X weeks | X weeks |
Key activities |
|
|
|
|
Key meetings |
|
|
|
|
End products |
|
|
|
|
Date 2
Date 4
Date 3
Date 1
Boat Chart work plan
Template
<Phase 1>
<Phase 2>
<Phase 3>
<Phase 4>
Creative Commons Attribution-ShareAlike 3.0 Unported License - �you may use and share this file, but please attribute it to thepsc.co.uk
How to use a Boat Chart work plan (from our FEP & PSAT programmes)
3
What is this tool?
A Boat Chart is a very simple style of work plan showing end products, key activities and meetings, and the overall timing of each project phase. The name ‘Boat Chart’ comes from the way the chevrons look like a line of boats following each other.
Tips for work planning
When to use this tool?�It is useful for projects involving complex problems without clear solutions, where the detailed path of the project is not evident at the outset (e.g., decision-making, option generation, reviews)