1 of 29

The Last Year of SLS Operation and Progress towards SLS 2.0

Felix Armborst on behalf of the SLS & SLS 2.0 Teams

31st European Synchrotron Light Sources Workshop at DESY, Hamburg, November 21th - 22th, 2023

WIR SCHAFFEN WISSEN – HEUTE FÜR MORGEN

2 of 29

Outline

  1. SLS
    1. Operation Statistics
    2. Outage Highlights 2023
    3. Final Machine Development Week
    4. Final Shutdown
  2. SLS 2.0
    • Milestones
    • SLS Disassembly
    • SLS Super-3HC Incident from 2022
    • New Components Preparation
    • Magnet Measurements
    • First Arc String Assembly
    • Arc String Installation in Magnets
    • ARS10 Activation

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 2

courtesy of

Andreas Lüdeke,

Lukas Stingelin,

Christian Geiselhart,

Jonas Kallestrup

courtesy of

Romain Ganter,

Stephane Sanfilippo,

Lukas Stingelin

3 of 29

SLS - Operation Statistics 2023

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 3

4 of 29

SLS - Operation Statistics 2023

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 4

The year 2023 was … the worst in the entire SLS history (greytime)!

  • Beam availability of 92.3%.
  • MTBF was still 92 hours.

5 of 29

SLS - Operation Statistics 2023

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 5

Many outages due to system upgrades, partly related to the SLS 2.0 project

  • Upgrades require in-situ testing (BPM electronics, …)
  • Reduced maintenance due to experts working on new systems

    • Water-to-vacuum leak caused 73% of downtime: more than a week!
    • Feedbacks: BPMs, FPFB/Timing

6 of 29

SLS - Outage Highlights 2023

Overview

  • 03.02. Flooding of diagnostic beamline (4 h)
  • 18.02. Water leak at LINAC quadrupole (17 h)
  • 04.04. Water leaks at booster RF-cavity (2 h)
  • 13.05. Water to UHV leak in absorber (> 1 week)
  • 15.07. Issue with Super-3HC Cryoplant (17 h):
  • Some others:
    • Defective water-leak sensor
    • Issue with Circulator Temperature Compensation Unit (drifting reflected power)
    • Broken charging-unit in LINAC → broke power contactor and tripped fuse.

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 6

7 of 29

SLS - Outage Highlights 2023

Flooding of the diagnostic beamline

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 7

February, 1st: The Front End X09DA was isolated from ring due to bad vacuum

  • Two days later 100 l cooling water were missing
  • Investigations showed that the front end had been flooded
  • End of life for the diagnostic beamline (no repair before SLS2)
  • No beam size measurement for user operation
  • Shared beamline available only for MD�with FZP beam size measurement

8 of 29

SLS - Outage Highlights 2023

Water leak at LINAC quadrupole

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 8

Incident in 2023

  • Pressure drop in water cooling for ring RF initialized investigations
  • 300 l cooling water lost
  • 17 hours of downtime

Possibly a general maintenance issue for SLS

  • 10 QT-type quadrupoles, manufactured in 1991, installed in LINAC
  • Obtained from the Dutch National Institute for Subatomic Physics, Nikhef.
  • Previously installed in the Amsterdam Pulse Stretcher (AmPS) ring.
  • In recent years, several of these quadrupoles have had water leaks.

9 of 29

SLS - Outage Highlights 2023

Water leak at booster RF-cavity

  • Investigations initiated after “Tunnel Leak” Interlock at SSA
  • Tunnel access showed water puddle under booster cavity
  • Temporary “fix” 1: bridged leak sensor and bucket enabled operation until next day
  • Temporary “fix” 2: closing water valve of the affected circuit enabled operation until following shutdown
  • 40 l cooling water lost

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 9

10 of 29

SLS - Outage Highlights 2023

Water to UHV leak in SLS Absorber

  • May 13th 2023: �> 20 mbar in whole Arc12 !
  • Leak due to corrosion from water with X rays
  • 10 days to recover UHV !

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 10

Leaking Absorber

Only 3 mm of copper

11 of 29

SLS - Outage Highlights 2023

Water to UHV leak in SLS Absorber

  • May 13th 2023: �> 20 mbar in whole Arc12 !
  • Leak due to corrosion from water with X rays
  • 10 days to recover UHV !

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 11

Leaks

May 13th

Pressure (mbar)

  • Drying period
  • N2 rinsing
  • Crotch exchange

Leak source found: May 17th

Turbo pumping

6 bar He stress test

Ion pumping

Ti sublimation

May 24th: 2E-9mbar without beam

Leaking Absorber

12 of 29

SLS - Outage Highlights 2023

Water to UHV leak in SLS Absorber

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 12

24 h

Vacuum conditioning with beam:

< 20 Ah to get 10 hours lifetime!

13 of 29

SLS - Outage Highlights 2023

Issue with Super-3HC Cryoplant

  • Incident detection due to Helium loss at broken connections from vibrations
  • Bearing damage on the compressor screws of the compressor
  • Such strong vibrations that approaching the plant was impossible without hearing protection due to noise levels way above pain threshold
  • Compressor screws beyond repair after just 61000 h of operation
    • Screws were grinding into each other and scraping the housing
    • Metal abrasion in oil
    • Motor power went up from 100 kW to maximum of 131 kW during incident
  • Reduced cooling power due to impurities in Helium

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 13

14 of 29

SLS - Final Machine Development Week (5 days)

  • BD Collaboration with BESSY / HZB on Coupling
  • Tests of SLS 2.0 MBFB and FPFB
  • Tests of New SLS 2.0 FOFB
  • Machine Learning for SLS 2.0: Train Model
  • Investigation of the Super-3HC failure and impedance of the vacuum-components
  • Robinson stability measurements at lower current
  • SLS 2.0 Injection Chain Setup for 2.7 GeV
  • 50 mA Storage Ring Kicker Matching
  • Software Development for BPM TbT Data
  • Tests on influence of ELM brake for servo motor on stored beam with/without FOFB
  • Tests of the booster inj/ext with the upgraded timing system and fine delay feature
  • Tests of the timing master software with beam
  • Machine Learning for SLS 2.0: Test Model
  • Optimizing the Beam Size to Lifetime Ratio
  • Beam Size Minimization Measurements
  • Software Development for Emittance Measurement
  • Tests of Spare PCT Hardware
  • Ceremonial Beam Dump

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 14

15 of 29

SLS - Final Shutdown / Beginning of the Darktime

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 15

16 of 29

SLS 2.0 - Milestones

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 16

3

Funding Secured

01.01.2021

5

Dark Time

30.09.2023

6

Close Tunnel

16.12.2024

7

Nominal Beam

01.05.2025

8

First User Operation

01.08.2025

22.11.2023

1

Lattice Defined

30.06.2020

2

Beamline Geometry Defined

30.09.2020

2020

2021

2022

2023

2024

2025

2026

4

Dark Time Ready

17.10.2022

9

Shutdown Phase 2

21.12.2025

10

User Operation

01.06.2026

22 months without user operation

17 of 29

SLS 2.0 - SLS DisassemblyWeekend after SLS has been switched OFF→ Start of Dismantling

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 17

Dismantling is going according to plan

1st half of October

  • Removal of tunnel roof bars
  • Removal of cable trays and cooling distribution along Ring

2nd half of October

  • Removal of to be reused components: Super-3HC, Kickers, Undulators, …
  • Removal of RF modulator & Klystron and most electrical cabinets

November

  • Removal of girders�with magnets

18 of 29

SLS 2.0 - SLS Disassembly

Arc Section 09

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 18

03.10.2023

02.11.2023

19 of 29

SLS 2.0 - SLS Dismantling

Post Mortem Pictures from SLS Components

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 19

Bellow in front of the Super-3HC

  • Molten, welded and bent RF finger

Absorber in front of the Super-3HC

  • Scorch marks on vacuum chamber and absorber-block
  • Needs closer inspection.

20 of 29

SLS 2.0 - SLS Super-3HC Incident from 2022

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 20

Orbit problems, current drops

Vacuum increase, voltage asymmetry starts

Operator tries to increase voltages

Beam-loss (CBI)

Vacuum-controller did not interlock the beam!

Orbit off by several mm!

  • MD shift with experimental orbit bumps
  • BPM system failure large orbit excursion
  • 1E-5 mbar vacuum at absorbers before and after Super-3HC
  • Asymmetry in detuning is permanent
    • Always observed during accumulation with drifts over 10s of minutes until new equilibrium reached

21 of 29

SLS / SLS 2.0 - Super-3HC Incident from 2022

Investigation of Observed Detuning

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 21

After the incident: detuning of the Super-3HC changed by -5.5 kHz (cav 1) and -10 kHz (cav 2) for the same voltage with

no obvious change in LHe consumption.

Could quality factor degradation explain the observed detuning?

  • Only for values around 2E4 with 100 kW loss, whereas the cooling can only sustain 50 W → No!

22 of 29

SLS / SLS 2.0 - Super-3HC Incident from 2022

Reconstruction of distorted orbit and Synrad Calculation

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 22

Reconstructed orbit during the first incident:

  • Bending magnet is around s=137m
  • Super-3HC starts at s=141m with flange-to-flange length: 1.1m

Synrad

Increased power at tapers before and after the cavity for reconstructed orbit�

Orbit data: M. Boege, Synrad template: L. Schulz, Locations: N.Kirchgeorg

Heating during incident due to what ?

  • Wakefield at valve/bellow
  • Synchrotron-radiation

RF Fingers

Absorber

23 of 29

SLS / SLS 2.0 - Super-3HC Incident from 2022

Investigations: Measurement of Flange Temperature and Movement

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 23

View from outer wall, beam indicated by blue arrow

Temperature change 0 …400mA:

ΔT1=+4.3°C ΔT2=+3.2°C�ΔT3=+0.4°C ΔT4=+0.3°C

View from inner wall

Longitudinal position of the flange changes with same time-constant as the voltage-drift �(after accumulation 0…400mA)

Driving offset-bumps with up to 0.5mm horizontally and 1.6mm vertically did not show any significant effect. → Damage likely caused by synchrotron radiation and not wakefields.

Installation by D. Kunz

24 of 29

SLS 2.0 - New Components Preparation

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 24

  • Girders and racks are assembled in large external storage and assembly hall
  • 1100 Power supplies – 10 A ready at PSI
  • One 500 MHz HOM-Damped RF Cavity conditioned to 600 kV
  • Two more cavities passed the FAT
  • Delays with Solid State Amplifiers

BPM Electronic tested including FOFB test in last shifts of SLS

30 nm RMS position noise* reached

(~1% of minimum beam size) !

25 of 29

SLS 2.0 - Magnets Measurements

  • 7 benches to measure 950 magnets
  • 3 months delays with Permanent Magnets measurements: critical path of project !
  • Quadrupole Series: 112 /112 ready
  • Steerers: 117 / 117 ready
  • Sextupoles: 59 / 270 ready
  • Octupoles: 16 / 268 ready

  • Triplet Bending magnet: 1 / 60 ready

BN 22/60 ready

VB 2/120 ready (rotating coil bench not ready)

  • Reverse Bends: 0 / 150 ready

Yokes to be delivered in october

Rotating coils benches

Vibrating wires benches

Hall Probe bench

Moving wire benches

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 25

26 of 29

SLS 2.0 - First Arc String Assembly

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 26

18 m long arc assembly

Successful transport of arc

Arc transport & storage frame

(fits baking oven)

Status November 2023:

  • 3 Arc vacuum string assembled and activated => pressure around 1E-11 mbar

27 of 29

SLS 2.0 - Arc String Installation in Magnets

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 27

  • Vacuum arc fits in the magnets apertures !
  • Installation Procedure is validated !
  • … minor corrections of cooling pipes.

Sept. 12th , 2023

28 of 29

SLS 2.0 - ARS10 Activation

31st ESLS@DESY | Status SLS & SLS 2.0 | 21.11.2023 Page 28

Bake out 130 deg

> 48 h

IP flashing

NEG cartridges

activation

NEG activation

200 deg

> 24 h

IP ON

Valves closed (13H)

& Arc Gauges ON (16H)

2.e-11 mbar

4.e-11 mbar

3.e-10 mbar

18/08/2023

25/08/2023

Arc Gauges:

29 of 29

Swiss Light Source

Thank you for your attention

And thanks to the many colleagues

who provided slides and input

for this presentation