NORTH ANDOVER PROPOSED PROJECTS �AS PART OF FACILITIES MASTER PLAN II

PUBLIC FORUMS

1

2 of 39

Welcome/Introductions

  • Dr. Gregg Gilligan, Superintendent
    • Town Manager, Melissa Rodrigues
    • Director of Administrative Services, Laurie Burzlaff
    • School Committee Members, Andrew McDevitt and Pam Pietrowski
    • Youth Services Director, Rick Gorman
    • Dr. James Mealey, Assistant Superintendent

2

3 of 39

3

Facilities Master Plan I Projects

Department of Public Works

Anne Bradstreet Early Childhood Center

Kittredge Elementary School

North Andover Town Hall

School Administration Building

North Andover Fire Department

Senior Community Center

4 of 39

FACILITIES MASTER PLAN II - PROJECTS

  • School renovations and additions
    • Atkinson Elementary
    • Franklin Elementary
    • Kittredge Elementary
    • North Andover Middle School
    • ABECC
  • North Andover Fire Station #2
  • North Andover Youth Center

4

5 of 39

FACILITIES MASTER PLAN II - SCHOOL PROJECTS

  • School focus for Plan II
    • Renovate older schools
    • Ensure equity and provide needed support spaces for 21st century learners
    • Impact class size
    • Build capacity for future growth
    • Eliminate portable classrooms

5

6 of 39

Building Assessments

  • Older schools are in need of renovations
  • Mechanical systems need to be modernized
  • Schools need to be brought up to modern code, including adding fire suppression sprinkler systems
  • Schools need to meet ADA requirements
  • Need to provide environments more conducive to learning
  • Want the ability to improve indoor air quality

6

7 of 39

Equity - School Capacity Analysis

  • All schools should have space to allow for growth
  • All schools should have space to impact class size
  • All schools should have appropriate support spaces
  • All schools should have dedicated, appropriate specialist spaces
  • All schools should provide environments conducive to learning

7

8 of 39

Kittredge Elementary School

  • Built in 1949. Extended in 2010 (modular classes) and 2013 (prefab gymnasium).
  • Exterior in good to fair condition
  • Interior in fair to poor condition
  • Needs renovation to meet ADA requirements and other modern codes
  • Replace steam boilers with hot water
  • Electrical mostly original and in fair to poor condition

9 of 39

Kittredge Elementary School

INTERIOR & EXTERIOR NON COMPLIANT ADA ACCESS /EGRESS

WATER INFILTRATION

NON ADA FIXTURES

ORIGINAL STEAM HEAT

ORIGINAL ELECTRICAL COMPONENTS

10 of 39

Kittredge Space Analysis

10

Room Type

Existing Rooms

Current Sq. Ft.

Planned Rooms

MSBA Guidelines for Sq. Ft.

Additional Sq. Ft.

Classrooms

12

10,800

20

19,000

8,200

Art

1

700

1

1,000

300

Music

0

0

1

1,200

1,200

Reading

1

140

1

500

360

Cafe/Kitchen

1

1,680

1

2,600

920

Gym

1

5,820

1

6,000

Library/Media Ctr

1

1,140

1

2,020

880

Support Spaces

6

965

8

2,500

1,535

Special Education

3

1,050

3

2,850

1,800

Nurse

1

250

1

410

160

OT/PT

1

220

2

800

580

11 of 39

Atkinson Elementary School

  • Built in 1964 as the middle school
  • Extended 1980s (portable classrooms)
  • Flat roof actively failing
  • Interiors mostly good to fair condition
  • Needs renovation to meet ADA requirements and other modern codes
  • Replace steam boilers with hot water
  • Piping 50+ years old and needs replacement
  • Electrical mostly original and in fair to poor condition
  • No fire suppression system
  • Has a lift instead of an elevator

12 of 39

Atkinson Elementary School

NON ADA HARDWARE & CLEARANCES

ROOF FAILING & AREAS NOT PROPERLY DRAINING

NON ADA TOILETS AND CLEARANCES

NON COMPLIANT VERTICAL ACCESS

ORIGINAL OUTDATED ELECTRICAL COMPONENTS

13 of 39

Atkinson Space Analysis

13

Room Type

Existing Rooms

Current Sq. Ft.

Planned Rooms

MSBA Guidelines for Sq. Ft.

Additional Sq. Ft.

Classrooms

14

13,300

20

19,000

5,700

Art

.5

530

1

1,000

470

Music

.5

530

1

1,200

670

Reading

1

300

1

500

200

Cafe/Kitchen

1

4,672

1

2,600

Gym

1

5,840

1

6,000

Library/Media Ctr

1

925

1

2,020

1,095

Support Spaces

4

1,126

8

2,500

1,374

Special Education

2

1,200

3

2,850

1,650

Nurse

1

240

1

410

170

OT/PT

1

350

2

800

450

14 of 39

Franklin Elementary School

  • Built in 1958. Extended in 1967, late 1980s (portable classrooms)
  • Exteriors mostly in good condition
  • Interiors mostly fair to poor
  • Needs renovation to meet ADA requirements and other modern codes
  • Replace steam boilers with hot water
  • Piping 50+ years old and needs replacement
  • Electrical mostly original and in fair to poor condition
  • No fire suppression system

15 of 39

Franklin Elementary School

NON ADA FIXTURES

NON ADA ENTRANCE/EXIT

ORIGINAL DOORS /NON ADA HARDWARE & CLEARANCES

ORIGINAL VAT FLOORING

OUTDATED ELECTRICAL

COMPONENTS

16 of 39

Franklin Space Analysis

16

Room Type

Existing Rooms

Current Sq. Ft.

Planned Rooms

MSBA Guidelines for Sq. Ft.

Additional Sq. Ft.

Classrooms

19

17,100

25

23,750

6,650

Art

1

500

1

1,000

500

Music

1

650

1

1,200

550

Reading

0

0

1

500

500

Cafe/Kitchen

1

2,520

1

2,600

Gym

1

1,750

1

6,000

4,250

Library/Media Ctr

1

1,760

1

2,020

Support Spaces

4

1,040

8

2,500

1,460

Special Education

2

1,800

3

2,850

1,050

Nurse

1

200

1

410

210

OT/PT

2

300

2

800

500

17 of 39

North Andover Middle School

  • Built in 1953 as the high school. Extended in 1962, 1995
  • Most exteriors and interiors in good to fair condition
  • Needs renovation to meet ADA requirements and other parts of modern code
  • Needs classrooms/science labs

18 of 39

North Andover Middle School

MISCELLANEOUS NON ADA ITEMS

MISCELLANEOUS ROOF REPAIRS AND REPLACEMENT REQUIRED

MASONRY & LINTEL REPAIR REQUIRED @ 1953 ADDITION

19 of 39

Enrollment Projections

  • Since 1990, enrollment has increased at a steady average rate of 35 students/year
  • Recent drop in enrollment attributed to COVID
  • Independently-commissioned projection studies by Wagman and TBA represent upper and lower bounds for growth
  • Expect enrollment to continue to increase at an average rate of 35 students per year

19

20 of 39

Enrollment Data and Projection

21 of 39

RECOMMENDATION

  • Maintain current grade distribution
  • Maintain neighborhood schools
  • Add capacity and renovate to address:
    • Equity
    • Support Spaces
    • 21st Century Learning
    • Class Size
    • Enrollment Growth
  • Remove portables
  • Be fiscally responsible

21

22 of 39

22

23 of 39

Kittredge Project

  • Build new school on the same site
  • Utilize existing gym and 4 existing classrooms attached to the gym

23

24 of 39

24

Kittredge Elementary School

25 of 39

Atkinson Project

  • Remove 2 portable classrooms
  • Renovate interior, including gym and cafeteria
  • Renovate exterior, including roof and paving
  • Upgrade electrical, plumbing, and hvac systems
  • Install fire suppression system
  • Install elevator
  • Add 6 classrooms
  • Add 4-8 support spaces

25

26 of 39

26

Atkinson Elementary School

27 of 39

Franklin Project

  • Remove 3 portable classrooms
  • Renovate interior, including cafeteria and library
  • Renovate exterior, including roof and paving
  • Upgrade electrical, plumbing, and hvac systems
  • Install fire suppression system
  • Add 6 classrooms
  • Add 4-8 support spaces
  • Build a new gym and repurpose existing gym

27

28 of 39

28

Franklin Elementary School

29 of 39

Middle School Project

  • Renovate interior, including cafeteria, gym, and library
  • Renovate exterior, including roof and paving
  • Upgrade electrical, plumbing, and hvac systems
  • Add 10-15 classrooms/science labs
  • Add 4-8 support spaces

29

30 of 39

30

North Andover Middle School

31 of 39

ABECC Project

  • Build new gym on site of preschool playground
  • Move preschool playground next to kindergarten playground
  • Add 2-4 support spaces in courtyard

31

32 of 39

32

ABECC

33 of 39

33

Fire Station #2

34 of 39

34

Youth Center

35 of 39

Facilities Master Plan II Working Group

Laurie Burzlaff

Steve Foster

Paul Hutchins

Jim Mealey

Lyne Savage

Jim Stanford

35

36 of 39

PUBLIC FORUM SCHEDULE

  • Atkinson Elementary - October 18, 2021 6:00 - 8:00 PM
  • Franklin Elementary - October 19, 2021 6:00 - 8:00 PM
  • Kittredge Elementary - October 25, 2021 6:00 - 8:00 PM
  • Middle School - October 26, 2021 6:00 - 8:00 PM
  • Senior Center - November 4, 2021 1:00 - 3:00 PM
  • Town Hall (Select Board Meeting) - November 8, 2021 7:00 PM
  • ABECC - November 9, 2021 6:00 - 8:00 PM
  • Youth Center - December 1, 2021 7:00 PM

36

37 of 39

Process Timeline

  • School Committee recommendation to Facilities Master Plan II Working Group - September, 2021
  • Facilities Master Plan II Working Group meetings to discuss cost estimation and timeline-September - December, 2021
  • School Projects Public Forums - October - December, 2021
  • Facilities Master Plan II Working Group deliberations - October, 2021 - March, 2022
  • Public Education and Support Initiatives - January - May, 2022
    • Messaging
    • CAM
    • Public Forums/Funding Plan
  • Town Meeting Approval - May, 2022 (Design of 1st Project(s))
  • Town Meeting Approval - May, 2023 (Construction of 1st Project(s) and Design of Next Project(s))
  • Subsequent Town Meetings - May of each Year (Construction of current project and Design of the Next - Depending on Funding)

37

38 of 39

Comments to date...

  • Make sure the renovation addresses 21st century technology needs
  • Are there partnering possibilities with the Stevens Library
  • Make sure the design phase addresses 21st century outdoor space needs (may add technology needs)
  • How can we make sure our children will be impacted by these projects?
  • When will we have the financial plan/timeline?

38

39 of 39

QUESTIONS???

39