1 of 34

Essex Elementary School Project

Community Meeting No. 01

October 8, 2025 @ 6:00 PM

2 of 34

  1. Project Team Introduction
  2. MSBA Process and Schedule
  3. Existing Conditions
  4. Site Analysis
  5. Educational Programming
  6. Next Steps
  7. Q&A

2

10/08/2025

Agenda

3 of 34

3

10/08/2025

Organization/ Project Team

Massachusetts School Building Authority

4 of 34

4

10/08/2025

Process

Middle

High

School

Memorial

Elementary

School

Essex

Elementary

School

5 of 34

Dore + Whittier Team

Michael Burton

Partner In Charge

Christina Dell Angelo

Project Director

John Albright

Project Manager

Jacob Greco

Assistant Project Manager

JCJ Architecture Team

Jim LaPosta

Principal in Charge

Fawn Pellegrini

Project Manager

Jeff Elliott

Project Architect

Emily Czarnecki

Interior Designer

School Building Committee

Pam Beaudoin

Superintendent of Schools/SBC

Michelle Cresta

Director of Finance & Ops/SBC

Theresa Whitman

SC/SBC Co-Chair

John Binieris

SC/SBC Co-Chair

Annie Cameron

Essex Select Board/SBC

Tyler Virden

Project Executive/SBC

Gordon Brewster

OPM/SBC

Charlie Hay

Architect/SBC

Kim Provost

Essex Elementary School Principal/SBC

Henry Oettinger

Manchester ConCom/SBC

Tim McDonald

Architect/SBC

Andy Oldeman

Manchester Finance Committee/SBC

Lisa O’Donnell

Essex Planning Board/SBC Advisor

Ariel Fernando Brain

Architect/SBC

Jen Hocherman

Architect/SBC

Michael Gerhardt

Civil Engineer/SBC

David Pereen

Plumbing/Fire Design/SBC Advisor

Emily Dwyer

Essex ES Teacher Rep

Rachelle Russo

Essex ES Teacher Rep/SBC Advisor

Kim Field

Essex ES Teacher Rep/SBC Advisor

Steve Hunt

Facilities Director/SBC Advisor

Project Team

6 of 34

6

10/08/2025

Who is the Massachusetts School Building Authority (MSBA)?

A quasi-independent government authority created to reform the process of funding capital improvement projects in the Commonwealth’s public schools.

The MSBA strives to work with local communities to create affordable, sustainable, and energy efficient schools across Massachusetts.

Collaborating with municipalities to equitably invest in finding the right-sized, most fiscally responsible and educationally appropriate solutions to create safe, sound, and sustainable learning environments.

MSBA Process

7 of 34

7

10/08/2025

Where do MSBA grant funds come from? How are they issued?

The MSBA has a dedicated revenue source of 1% from the state’s 6.25% annual sales tax collections.

Grant funds are issued to the district using a “pay-as-you-go”

reimbursement system for the duration of the project.

More than $16.6 billion issued to-date to cities, towns, and regional school districts for school construction projects.

MSBA Process

8 of 34

8

10/08/2025

How does MSBA determine the level of financial support for projects?

Reimbursement rates are calculated based on a formula that is established in M.G.L ch.70B § 10

The formula starts all districts at a base rate of 31% (of eligible project costs).

The base rate may be adjusted based on three socioeconomic factors:

      • Community income factor
      • Community property wealth factor
      • Community poverty factor

*Essex ES Base Rate is 31%*

6% potentially available from Green School (4%) incentive points and District maintenance policy (2%)

MSBA Process

9 of 34

9

10/08/2025

What does “eligible project cost” mean?

The MSBA uses a total project budget template to apply and calculate their funding policies to determine the grant amount

The MSBA’s reimbursement rate is applied to “eligible project costs” to determine the MSBA’s participation on each budget line-item.

  • Construction and Site $605/sf + $73/sf
  • Furniture, Fixtures & Equipment (FF&E) $1,995/sf
  • Technology Equipment $1,570/sf

There are funding caps on certain budget items, as well as “categorically ineligible” items that the MSBA will not participate in.

  • Pools, Field Houses, Elementary School Auditoriums, Central Offices, Senior Centers, site acquisition, and offsite improvements

MSBA Process

10 of 34

10

10/08/2025

These caps and ineligible costs will have an impact to the final (or “effective”) reimbursement.

Memorial E.S. Example:

- Base Rate of 31%

- CM@ Risk 1% (no longer applicable)

- Maintenance 1.93%

- Energy Efficient School 2% (has increased)

MSBA reimbursement rate 35.93%

“Effective” reimbursement rate ~23% = $11.5 Million from the State

MSBA Process

11 of 34

MSBA Process

12 of 34

PROCESS & SCHEDULE

Preliminary Design Program (PDP)

  • Identify the issues/articulate the educational plan
  • List options to be studied in PSR

Preliminary Schematic Report (PSR)

  • Evaluate the site and building options/select a preferred option

Schematic Design (SD)

  • Develop schematic drawings and specifications

to establish the project budget

Feasibility Phase Process

13 of 34

PROCESS & SCHEDULE

Preliminary Design

Program

Dec ‘25

May ‘26

Oct ‘26

Nov ‘26

Module 3

Module 4

Module 5

Community input is important throughout the process

Preferred Schematic Report

Schematic

Design

Local

Approval

Feasibility Phase Schedule

14 of 34

PROCESS & SCHEDULE

Local Approvals

  • Receive local funding approval in Essex and Manchester-by-the-Sea
  • Approval November 2026
  • Depending upon preferred option

If Project is Approved

Proceed to detailed design and construction

Feasibility Phase Process

15 of 34

15

10/08/2025

MSBA Requires

Development of Several Options including:

Renovation Only

Addition/Renovation

New Construction

Feasibility Phase Requirements

16 of 34

16

10/08/2025

Feasibility Study

Enrollment Configurations to be Studied for Essex Students

Grades PreK-3

165 Students

Sited in Essex w/Grades 4 & 5

Integrated into Memorial

Grades PreK-5

250 Students

Sited in Essex

Pre-K to 5

515 Students

Sited at Manchester Memorial with all Essex & Manchester students in one school

SC Program Vote/Redistricting

SC Program Vote/Redistricting

SC Vote to Amend Regional Agreement

SC Vote to Amend Regional Agreement

Essex & Manchester Town Meeting Vote to Approve Regional Agreement Amendment

Essex & Manchester Town Meeting Vote to Approve Regional Agreement Amendment

Essex & Manchester Town Meeting Full Project Vote & Debt Exclusion Vote

Feasibility Phase Requirements

17 of 34

17

10/08/2025

The Essex Elementary School building

  1. Total building is approximately 52,900 SF
  2. Originally built in 1957 (68 Years)
  3. Addition provided in 1975 (50 Years) (media center and gymnasium)
  4. The design team's existing investigations began and are ongoing.
  5. Mechanical, electrical & plumbing systems has exceeded life expectancy
  6. Roofing, windows and building materials are deteriorating

Building History

18 of 34

18

10/08/2025

The roofing system is at life expectancy. There are several repairs, underlayment appears compromised, and water is ponding, so moisture is not shedding quickly

Existing Conditions

19 of 34

19

10/08/2025

Shedding water away from the school building through roofing and site drainage is important.  

Moisture accelerates:

  • Spalling at the existing roof eave
  • Lichen on the masonry
  • Compromises at the concrete foundation
  • Plant growth occurring in unplanned or undesirable areas 
  • Deterioration of the original wood windows

Existing Conditions

20 of 34

20

10/08/2025

Accessibility is being reviewed to enable students, staff and visitors of various abilities to enter the school together (not separate due to physical need, or otherwise).  Some of the items included in this review of the site conditions and the school interior include:

  • Exterior grade changes
  • Interior level changes
  • Pitch of sloped walkways and ramps
  • Handrail design
  • Push/pull clearances at doorways
  • Circulation space & turn around space
  • Mounting heights of accessories, plumbing, and equipment 
  • Furniture
  • Signage

Existing Conditions

21 of 34

21

10/08/2025

  • Mechanical, electrical, plumbing systems are beyond or at life expectancy.
  • Exhaust fans, unit ventilators and boiler are worn. 
  • Portable fans are seen throughout the school to supplement air circulation 
  • Interior finishes are buckling.
  • Wood windows are deteriorating.
  • The water heating system is at the end of its useful life. The mixing value is leaking.

  • Considerations include:
  • Efficiency of operation (operational costs for the District)
  • Efficiency to heat, cool, dehumidify and provide fresh air circulation
  • Availability of parts quickly for future repairs

Existing Conditions

22 of 34

22

10/08/2025

Existing Conditions

23 of 34

23

10/08/2025

Entry and exit sequence for students, staff, and visitors is being reviewed with the District to support the operational needs. 

Existing Conditions

24 of 34

Identified Sites

Statement of interest includes:

  • Current Essex Elementary School
  • Current Manchester Memorial Elementary School

Search of other potential sites in Essex:

  • Town of Essex owned parcels 112
  • Minimum 9.75 acres 16
  • Street access & utilities 7
  • Not used by other town function 1

Town Hall, Spring Street Cemetery, Essex ES, Centennial Grove, DPW Transfer Station, Public Water Supply

30 Apple St

10/08/2025

24

09/30/2025

ESSEX ELEMENTARY SCHOOL

MANCHESTER ESSEX REGIONAL SCHOOL DISTRICT

25 of 34

Identified Sites

A

B

C

Current Essex Elementary School

12 Story Street, Essex MA

Current Manchester Memorial  Elementary School

43 Lincoln Street, Manchester MA

Apple Street Site

30 Apple Street, Essex MA

Identified Sites

10/08/2025

25

09/30/2025

ESSEX ELEMENTARY SCHOOL

MANCHESTER ESSEX REGIONAL SCHOOL DISTRICT

26 of 34

Current Essex Elementary School

Opportunities

  • Established identity in the community
  • Developed site utilities
  • Multiple options for site access

Constraints

  • Construction activities on occupied school site

Wetlands & pond

  • Some topography on north side of site

Unknowns

  • Soil conditions proximate to wetlands

A

Story St

Western Ave

Wetlands

Pond

10/08/2025

26

09/30/2025

ESSEX ELEMENTARY SCHOOL

MANCHESTER ESSEX REGIONAL SCHOOL DISTRICT

27 of 34

Current Manchester Memorial ES

B

Opportunities

  • Developed site utilities

Constraints

  • Construction activities on occupied school site
  • Dense site with limited expansion options
  • Wetlands and flood zone
  • Transportation from Essex to Manchester
  • Regional Agreement

Unknowns

  • MSBA funding considerations

Summer St

Causeway Brook

Lincoln St

Brook St

10/08/2025

27

09/30/2025

ESSEX ELEMENTARY SCHOOL

MANCHESTER ESSEX REGIONAL SCHOOL DISTRICT

28 of 34

Apple Street Site

C

Apple Street

Opportunities

  • No disruption to existing schools
  • Construction phasing

Constraints

  • Undeveloped site
  • Restricted site access
  • Impacts to adjacent residences

Unknowns

  • Environmental risks

DPW 

Bridge

Alewife Brook

Landing Rd

Lowland Farm Rd

10/08/2025

28

09/30/2025

ESSEX ELEMENTARY SCHOOL

MANCHESTER ESSEX REGIONAL SCHOOL DISTRICT

29 of 34

Site Evaluation Criteria

09/30/2025

ESSEX ELEMENTARY SCHOOL

MANCHESTER ESSEX REGIONAL SCHOOL DISTRICT

30 of 34

30

10/08/2025

Educational Programming

During the Feasibility phase, the District and its team collaborate to document their Educational Program.

  • The Educational Program enables an evaluation and creation of an initial space summary. 
  • Then the team evaluates the site and grade configuration alternatives to recommend the most cost effective and educationally appropriate preferred solution.

The Educational Program is developed through programming workshops to:

  • Build a shared understanding
  • Envision through an educational and scenario-based lens
  • Align renovated or new spaces with the educational program

31 of 34

Educational &

Community Priorities

Manchester Essex’s Educational Program

Developmental Impacts &

Enrollment Scenarios

Physical &

Social-Emotional Needs

Program

Adjacencies

High-Quality

Instructional Practices

31

32 of 34

32

10/08/2025

Upcoming Meetings/Next Steps

14 Oct.

SBC Meeting: Review Site Selection, Space Summary, Community Meeting Feedback

28 Oct.

SBC Meeting: Review Preliminary Evaluation of Alternatives, Accept Space Summary, Review Ed Program

6 Nov.

SBC Meeting: Preliminary Evaluation of Alternatives, Acceptance of Ed Program

20 Nov.

Community Meeting #2: Confirmed Site Selection and Alternatives Considered

25 Nov.

SBC Meeting: Community Meeting Feedback, Review Cost Estimating

9 Dec.

Community Meeting #3: Review Preliminary Design Program

15 Dec.

SBC Meeting: Approve Preliminary Design Program Submission to MSBA

33 of 34

33

10/08/2025

Project Website

34 of 34

Thank You!

Thank you!