1 of 40

SAP Production Planning & Execution (PP)

Repetitive Manufacturing

Flow

Part 4

REM Backflush

2 of 40

  • Material Master (MM03)
  • Configuration of Repetitive Profile (OSP2)
  • Bills of Material (CS03)
  • Rate Routing (CR23)
  • Production Version (C223)
  • Production Cost Collector (KKF6N)
  • Create PIR (MD61)
  • MRP run (MD02)
  • Stock Requirement List (MD04)
  • Planning Table (MF50)
  • Print Production List (MF51)
  • Stock of Raw Material before Staging (MB52)
  • Material Staging (MF60)
  • Raw Material Stock after Staging (MB52)
  • Material Document of Stock Transfer (MB51)
  • REM Backflush (MFBF)
  • Planning Table after REM backflush (MF50)
  • Stocks of Raw Material and Assembly after REM backflush (MB52)
  • Material Document of GR and GI (MB51)
  • An overview of Cost Collector Cost Actual Cost (KKF6N)

Part 4

3 of 40

This REM Planned Order Qty is 60, we shall perform REM Confirmation of 10

4 of 40

REM Confirmation using MFBF

5 of 40

Confirmation and Backflush to Production Line T-L310

6 of 40

7 of 40

Calculated based on BOM, but change as needed

Backflush/GI from this Storage Location where Materials were Staged

8 of 40

Goto Rate Routing

9 of 40

10 of 40

Change hours as needed

11 of 40

GR, GI and Confirmation done

12 of 40

  • Material Master (MM03)
  • Configuration of Repetitive Profile (OSP2)
  • Bills of Material (CS03)
  • Rate Routing (CR23)
  • Production Version (C223)
  • Production Cost Collector (KKF6N)
  • Create PIR (MD61)
  • MRP run (MD02)
  • Stock Requirement List (MD04)
  • Planning Table (MF50)
  • Print Production List (MF51)
  • Stock of Raw Material before Staging (MB52)
  • Material Staging (MF60)
  • Raw Material Stock after Staging (MB52)
  • Material Document of Stock Transfer (MB51)
  • REM Backflush (MFBF)
  • Planning Table after REM backflush (MF50)
  • Stocks of Raw Material and Assembly after REM backflush (MB52)
  • Material Document of GR and GI (MB51)
  • An overview of Cost Collector Cost Actual Cost (KKF6N)

Part 4

13 of 40

100 before the GR

Original Planned Order Qty of 60

Before

GR

14 of 40

100 + GR of 10

= 110

Original Planned Order qty was 60,

60 - GR of 10 = 50 Remaining to be produced

After GR

15 of 40

  • Material Master (MM03)
  • Configuration of Repetitive Profile (OSP2)
  • Bills of Material (CS03)
  • Rate Routing (CR23)
  • Production Version (C223)
  • Production Cost Collector (KKF6N)
  • Create PIR (MD61)
  • MRP run (MD02)
  • Stock Requirement List (MD04)
  • Planning Table (MF50)
  • Print Production List (MF51)
  • Stock of Raw Material before Staging (MB52)
  • Material Staging (MF60)
  • Raw Material Stock after Staging (MB52)
  • Material Document of Stock Transfer (MB51)
  • REM Backflush (MFBF)
  • Planning Table after REM backflush (MF50)
  • Stocks of Raw Material and Assembly after REM backflush (MB52)
  • Material Document of GR and GI (MB51)
  • An overview of Cost Collector Cost Actual Cost (KKF6N)

Part 4

16 of 40

Check Warehouse Stock

17 of 40

Staging Location Before Backflush

T-B710 PL03 100

T-T610 PL03 120

T-T710 PL03 100

T-TE10 0088 1000

Before Raw Material backflushed

18 of 40

Staging Before Expected

Location Backflush Backflush Remaining Qty

T-B710 PL03 100 10 100 - 10 = 90

T-T610 PL03 120 20 120 - 20 = 100

T-T710 PL03 100 10 100 - 10 = 90

T-TE10 0088 1000 10 1000 - 10 = 990

(The above are Raw Materials to produce T-B1010)

To be Backflushed

Before Raw Material backflushed

19 of 40

Staging Before Expected

Location Backflush Backflush Remaining Qty

T-B710 PL03 100 10 100 - 10 = 90

T-T610 PL03 120 20 120 - 20 = 100

T-T710 PL03 100 10 100 - 10 = 90

T-TE10 0088 1000 10 1000 - 10 = 990

After Raw Material backflushed

20 of 40

Assembly GR into Storage Location PL01

Just now received

T-B1010 into SLoc PL01

21 of 40

  • Material Master (MM03)
  • Configuration of Repetitive Profile (OSP2)
  • Bills of Material (CS03)
  • Rate Routing (CR23)
  • Production Version (C223)
  • Production Cost Collector (KKF6N)
  • Create PIR (MD61)
  • MRP run (MD02)
  • Stock Requirement List (MD04)
  • Planning Table (MF50)
  • Print Production List (MF51)
  • Stock of Raw Material before Staging (MB52)
  • Material Staging (MF60)
  • Raw Material Stock after Staging (MB52)
  • Material Document of Stock Transfer (MB51)
  • REM Backflush (MFBF)
  • Planning Table after REM backflush (MF50)
  • Stocks of Raw Material and Assembly after REM backflush (MB52)
  • Material Document of GR and GI (MB51)
  • An overview of Cost Collector Cost Actual Cost (KKF6N)

Part 4

22 of 40

Assembly GR

(red)

Component Backflush (red)

23 of 40

Movement Types defaulted from the REM Profile assigned to the Material Master MRP4 data view

24 of 40

  • Material Master (MM03)
  • Configuration of Repetitive Profile (OSP2)
  • Bills of Material (CS03)
  • Rate Routing (CR23)
  • Production Version (C223)
  • Production Cost Collector (KKF6N)
  • Create PIR (MD61)
  • MRP run (MD02)
  • Stock Requirement List (MD04)
  • Planning Table (MF50)
  • Print Production List (MF51)
  • Stock of Raw Material before Staging (MB52)
  • Material Staging (MF60)
  • Raw Material Stock after Staging (MB52)
  • Material Document of Stock Transfer (MB51)
  • REM Backflush (MFBF)
  • Planning Table after REM backflush (MF50)
  • Stocks of Raw Material and Assembly after REM backflush (MB52)
  • Material Document of GR and GI (MB51)
  • An overview of Cost Collector Cost Actual Cost (KKF6N)

Part 4

25 of 40

Actual Costs posted can be found in the Cost Collector

26 of 40

Display Actual Costs

27 of 40

GR of Assembly Credit the Cost Collector

28 of 40

Backflush of Components Debits the Cost Collector

29 of 40

Confirmation of Machine hours Debit the Cost Collector

30 of 40

Overhead costs absorption are not done at MFBF backflush step. It will be calculated via month end Period Closing Settlement process

31 of 40

Check Material Documents

32 of 40

Check the

Material Document

33 of 40

This is a different Material Document number as it is done on a different day, but the Qty confirm and backflush is the same

34 of 40

Check FICO Documents Posted from MFBF

35 of 40

check

CO Document

36 of 40

The Costs is charged to the ORDER in the Costs Collector

Material and Machine Costs are Debited to the Order

while

GR is Credited to the Order

37 of 40

The Order in the Cost Collector

38 of 40

check

FI Document

39 of 40

GR of the FG

Debit Stock A/C

Credit Factory Output A/C

40 of 40

Backflush of Components

Debit Expenses A/C

Credit Stock A/C