1 of 18

BHS Building 100 Replacement

24 SEPTEMBER 2018

COMMUNITY PRESENTATION

Bainbridge Island School District No. 303

2 of 18

PROJECT DESCRIPTIONA new centralized dining commons will share work space with a modern CTE and Fine Arts facility, which will also house Music. The existing 200 Building commons will be renovated to become a Theater, with full technical support. The SPED programs displaced by the demolition of the existing Building 100 will be embedded with classrooms in renovated space with in Building 300.��PROJECT SCOPE�Site Area (acres) : 2.5 - 3.4�Building Size (GSF): +/-34,000; single story�

PROJECTED CONSTRUCTION TIMELINE:September 2019 – July 2021��PROJECTED COMPLETION�August 2021

3 of 18

© MAHLUM

100 BUILDING

300 BUILDING

SPED

200 BUILDING THEATER

Building 100 Replacement :: Scope of Work

4 of 18

© MAHLUM

Building 100 Replacement :: Concept

5 of 18

Building 100 Replacement

Design Overview

6 of 18

© MAHLUM

Building 100 Replacement

7 of 18

Context

Context photos

8 of 18

Building 100 Replacement :: Site

rendered

9 of 18

Proposed Massing & Context

10 of 18

Proposed Massing & Materiality

11 of 18

Proposed Massing & Materiality

12 of 18

PUBLIC WAY

View From Public Way

13 of 18

View From Public Way

14 of 18

© MAHLUM

Building 100 Replacement

15 of 18

Theater Renovation

200 Building Commons �

Transformed �

16 of 18

Campus Transformation

17 of 18

Memorial

Current location

18 of 18

Building 100 Replacement

Questions?