PUNE Division : Traffic Facility Works GM’s power

SN

Name of work

Year / Last San. Cost

Allocation/

Exec. Agency

ESP

SIP

Tender Status

CRS

Status

Engg.

S&T

Elect.

1

Hadapsar - Development as satellite terminal.

Scope: Extn. of PF 1 & 2 and additional 3rd PF, 2 Common loops for RBPC trains.

New EI.

2016-17

135.81 Cr.

(Rev.)

DF(3), RRSK &

EBR(S)

GSU/PA

TDC: Dec.’24

Rev.1:

June’25

25.5.21

Rev. 31.8.23

26.8.21

Rev.

20.4.24

Awarded

Awarded

Awarded

Ph-II:

To be processed

  • Ph.-I : Extn. of PF 1 & 2 with availability of add PF No.3 & slewing of Up & Dn common loop line were completed.
  • Ph.-II :10 turnouts laid. And 2 DS laid Revised estimates sanctioned. Track of two stabling lines of approx. 500m was laid and linking is pending for land acquisition. Linking line1 400m completed,line2 250m ,line3 400m completed.
  • Land acquisition : Total 4716.36 sqm of land from total 10 Gut are to be acquired. 20E has been notification issued for all Gut numbers. The valuation note was forwarded to the Town Planning Department on 03.06.2025 for verification of the land cost. 20F notifications for 09 out of the 10 land parcels have been published in local newspapers on 03.06.2025, and objections have been invited up to 16.06.2025. Publication under Section 20F for the balance 01 land parcel is under process.
  • 90% work of station building is completed. FOB work is in progress.

2 of 4

HADAPSAR-ESP

3 of 4

PUNE Division : Traffic Facility Works GM’s power

SN

Name of work

Year / Last San. Cost

Allocation/

Exec. Agency

ESP

SIP

Tender Status

CRS

Status

Engg.

S&T

Elect.

2

LONI:

Development of Goods shed with acquisition of land for increase of circulating area and in length of Goods line with shunting neck.

Scope: Extension of Goods Shed & Goods siding lines and provision of Shunting Neck.

2022-23

47.1 Cr.

CAP

GSU/PA

TDC: Dec.’24

Rev.1: To be fixed

23.05.23

Rev.

20.09.23

20.10.23

Rev. 02.05.24

Awarded

Awarded

Awarded

To be processed

  • Track work of proposed shunting neck is completed with connection to UP & DN Goods loop and also bridge extension completed but derailing switch & signaling facility is not provided yet
  • Land acquisition in progress as “Special Railway Project”. 20(A) Gazette Notification published on 08.12.23. Rs. 50 lac demanded as processing fee. Proposal vetted by finance on 07.10.24.
  • File pending at SDO office for land valuation.
  • Vishay company has filed case in High court for road dispute. State official, railway official with advocates visited the site on 11.02.25 for solution.
  • High court given date for hearing on 29/04/25.
  • Date postponed by High court. Next hearing on 30/07/2025.
  • Joint Site visit of CPM/GSU and Dy. Collector land Acq.no.3 along with Vishay company representatives on dt.11.04.2025 for Looking of all feasible options.
  • 03 feasible options have been identified and put up to HQ for consideration and further instructions.

4 of 4

Proposed ESP-LONI