THRU PEDESTAL INSTALLATION SEQUENCE
SUGGESTED STEPS FOR EFFICIENT INSTALLATION WHEN SYSTEM REQUIRES DIRECT BOND TO SUBSTRATE OR MEMEBRANE.
Establising pedestal placement. Able to set the heights with the base plate and rod installed.
Template or paver without stainless straps installed -speeds up pedestal placement
When pedestal placement determined, trace around the base. Apply glue within outline.
Glued down plate.
After stainless Base Plate has been glued down, it is time to trim the threaded rod height to fit the pedestal. This short video is also available on website: https://www.underlockusa.com/videos
Finished Installation Under Paver Surface
Direct Bond Termination of System
Double Plate connected by internal Threaded Rod
Termination of System At Perimeter